Route 59 Area Transportation & Land Use Study Community Planning - - PowerPoint PPT Presentation

route 59 area transportation land use study community
SMART_READER_LITE
LIVE PREVIEW

Route 59 Area Transportation & Land Use Study Community Planning - - PowerPoint PPT Presentation

Route 59 Area Transportation & Land Use Study Community Planning Workshop #2 April 29, 2019 1 Welcome Why are we here today? We want to hear from you regarding land uses and vision for Route 59 3 Project Approach & Schedule 2019


slide-1
SLIDE 1

Route 59 Area Transportation & Land Use Study Community Planning Workshop #2 April 29, 2019

1

slide-2
SLIDE 2

Welcome

slide-3
SLIDE 3

Why are we here today?

3

 We want to hear from you regarding land uses and vision for Route 59

slide-4
SLIDE 4

Project Approach & Schedule

4

January February March April May June July August September October November December January February March

Task 1: Study Outreach Program Task 2: Existing Conditions Task 3: Focus Area Analysis Task 5: Draft Study Report Task 6: Public Review Task 7: Final Study Report

2019 2020

1 2 3 4

Outreach Program Document Socio-Economic Profile Draft Study Report Final Study Report How do you use Route 59? Focal Area Examination & Brainstorm Solutions Evaluate Land Use & Roadway Visualizations Identify Draft Recommendations Public Review

slide-5
SLIDE 5

What we heard in Workshop #1

5

 Heavy congestion throughout the day  Identified several hotspots  Rapid population and development growth  Zoning Codes not consistent  Safety on corridor an issue

slide-6
SLIDE 6

Workshop #2 builds on what we heard

6

 Cluster the hotspots into focal areas  Show examples from neighboring towns / similar conditions  Would those examples work on Route 59?

slide-7
SLIDE 7

Hudson Link Project Update

7

Route 59 Safety Improvements

 Pedestrian Safety Improvements including installation of sidewalks,

crosswalks, guide rail, and sign upgrades on Route 59 from Monsey to Spring Valley.

 Expected to be complete in the fall of 2019

Integrated Corridor Management and Ramp Metering – Fall 2020

Bus Shelter & Intersection Improvements

 2 bus shelters remaining to be installed  3 curb ramps currently installed and 10 more by the fall of 2020

slide-8
SLIDE 8

Hudson Link Project Update

8

Monsey Park and Ride Lot (Rockland County Project)

 Expected to be completed in 2019-2020

Future Programmed Projects will improve:

 Traffic signals and detectors  Traffic cameras  Variable Message Signs (VMS)

slide-9
SLIDE 9

Route 59 - 1945

9

slide-10
SLIDE 10

Route 59 - 1955

10

slide-11
SLIDE 11

Route 59 - 1995

11

slide-12
SLIDE 12

Transportation

slide-13
SLIDE 13

Challenges:

  • Long crossing distances for pedestrians at

intersections

  • Wide turning radius at intersections
  • No pedestrian signal on Route 59 crosswalk
  • n the east leg at the Dutch Lane intersection
  • Narrow sidewalk on the south side
  • High number of curb cuts on the north side
  • Poor access management
  • No crossing between shopping plazas

Spring Valley

Food Fair Fresh Market

slide-14
SLIDE 14

Spring Valley

Food Fair Fresh Market

slide-15
SLIDE 15

15

Signalized crosswalks

A signalized pedestrian crosswalk on Rt 119 in Elmsford, NY

slide-16
SLIDE 16

16

Curb extension

Main St @ Central Ave in Ossining, NY – Painted curb extensions Short curb extensions/reduce crossing distances on Rt 11 in Canton, NY Intersection curb extensions on Main St in Bismarck, ND

slide-17
SLIDE 17

Access management

Access management to a shopping plaza on Rt 110 in Huntington, NY Access management to a shopping plaza on Rt 9, Poughkeepsie, NY Access management to a shopping plaza on Rt 110 in Huntington, NY Access management to a shopping plaza on Rt 9, Poughkeepsie, NY

slide-18
SLIDE 18

Eastern Parkway in Brooklyn, NY – Photo by Evan Bindelglass

18

Wider Sidewalks

Eastern Parkway in Brooklyn, NY Improved & widened sidewalks along Rt 9N in Lake George, NY Improved & widened sidewalks along Rt 9N in Lake George, NY

slide-19
SLIDE 19

Midblock crossings

https://nacto.org/publication/urban-street-design-guide/intersection-design-elements/crosswalks-and-crossings/midblock-crosswalks/

Mid-block pedestrian crossing with HAWK signal, Rt 9, Lake George NY

https://nacto.org/publication/urban-street-design-guide/intersection-design-elements/crosswalks-and-crossings/midblock-crosswalks/

slide-20
SLIDE 20

Monsey

Evergreen Kosher Market Mandarin Fusion Steakhouse Park-and-Ride

Challenges:

  • No sidewalk on either side / Construction in 2019
  • High density of curb-cuts
  • Turning radius at driveways is too wide
slide-21
SLIDE 21

Continuous sidewalks

Continuous sidewalk along Rt 9N in Lake George, NY Continuous sidewalk along Main St in New City, NY

slide-22
SLIDE 22

22

Safer-curb cuts

Safer curb cuts along the Indianapolis Cultural Trail, IN

http://urbankchoze.blogspot.com/2015/05/sidewalks-and-driveways-is-it-time-to.html

slide-23
SLIDE 23

Safer & accessible bus stops

A safe & accessible bus stop on Cleveland Ave in Columbus, OH A safe & accessible bus stop on Rt 9 in Tarrytown, NY

slide-24
SLIDE 24

Airmont

Wendy’s Shop Rite Wal-Mart Sutter’s Mill

Challenges:

  • No sidewalks on the north side, and

discontinuous and narrow sidewalks on the south side

  • Wide turning radius
  • Long pedestrian crossings at intersections
  • Lack of bike infrastructure near bus stops

Airmont Diner

slide-25
SLIDE 25

Wider, continuous sidewalks

slide-26
SLIDE 26

26

Curb extensions

Curbed extensions on Rt 110 in Huntington, NY

slide-27
SLIDE 27

Bike racks at bus stops

https://cyclesafe.com/bike-parking/bike-racks/bike-u-rack-crossbar/ https://www.strongtowns.org/journal/2017/8/28/college-town-and-the-money-island

slide-28
SLIDE 28

Land Use

slide-29
SLIDE 29

What would you like to see at Rt 59 & Airmont Road?

Sutter’s Mill

slide-30
SLIDE 30

Could this intersection be reimagined as a mixed-use gateway to Airmont?

slide-31
SLIDE 31

Compact & pedestrian-friendly mixed-use development

slide-32
SLIDE 32

Are there opportunities to rethink the corridor’s older shopping centers?

Airmont – Wal-mart & Shop Rite

slide-33
SLIDE 33

What about in Monsey?

Monsey – Town Square Shopping Center

slide-34
SLIDE 34

Vehicle-centric & an abundance of parking

slide-35
SLIDE 35

A higher & better use at the southeast corner of Town Square Shopping Center?

slide-36
SLIDE 36

Older shopping centers could be integrated with new mixed-use development

slide-37
SLIDE 37

And what about the areas of Rt 59 that are ‘in-between’?

  • W. Central Ave
slide-38
SLIDE 38

What is the appropriate vision for the areas of transition along the corridor?

slide-39
SLIDE 39

Small-scale, contextual & pedestrian friendly

slide-40
SLIDE 40

Iconic landmarks integrated with traffic improvements

slide-41
SLIDE 41

Save the date

41

Workshop #3 –Tuesday, June 18 7-9pm

Finkelstein Memorial Library, Spring Valley

Land Use & Roadway Visualization Workshop #4 –Tuesday, July 30 7-9pm

Spring Valley High School

Draft Recommendations

slide-42
SLIDE 42

Thank you!

Ali Mohseni Project Manager New York Metropolitan Transportation Council Phone: (845) 431-5768 Email: Ali.Mohseni@dot.ny.gov

www.Route59Study.org