rockville maryland penn state ae senior capstone project
play

Rockville| Maryland Penn State AE Senior Capstone Project Justin A. - PowerPoint PPT Presentation

NATIONAL CANCER INSTITUTE Rockville| Maryland Penn State AE Senior Capstone Project Justin A. Woishnis | Construction Option Advisor: James Faust PROJECT OUTLINE Project Introduction Project Background NATIONAL CANCER INSTITUTE Site


  1. NATIONAL CANCER INSTITUTE Rockville| Maryland Penn State AE Senior Capstone Project Justin A. Woishnis | Construction Option Advisor: James Faust

  2. PROJECT OUTLINE Project Introduction Project Background NATIONAL CANCER INSTITUTE • Site Overview • Building properties Analysis #1: Solar PV Analysis • Site/Roof Investigation Rockville| Maryland • Shading Analysis • Energy Use Study • Panel Selection and Layout • System Costs  Structural Breadth Analysis #2: Technology to the Field • Material Tracking • Case Study • Feasibility Analysis #3: Interior CMU Wall To Precast • CMU Overview • CMU Estimate • Precast Overview • Precast Estimate • Results/Feasibility Analysis #4: Alternative Façade Sequence Penn State AE Senior Capstone Project • Initial Sequence • New Façade Scheduling/Sequence Justin A. Woishnis | Construction Option • Cost/Schedule Results Summary of Conclusions/Recommendations Advisor: James Faust Acknowledgements

  3. PROJECT OUTLINE Project Introduction Project Background NATIONAL CANCER INSTITUTE • Site Overview • Building properties Analysis #1: Solar PV Analysis Rockville| Maryland • Site/Roof Investigation • Shading Analysis • Energy Use Study • Panel Selection and Layout • System Costs  Structural Breadth Project Size| 600,000 S.F. Base Building Analysis #2: Technology to the Field 575,800 S.F. Parking Garage • Material Tracking • Case Study Building Function| Office/ Research • Feasibility Analysis #3: Interior CMU Wall To Precast Contract Value | $96 Million • CMU Overview • Contract Type| Design-Build CMU Estimate • Precast Overview Total # of Floors | 8 • Precast Estimate • Results/Feasibility Owner| The JBG Companies Analysis #4: Alternative Façade Sequence • Initial Sequence General Contractor| DAVIS Construction • New Façade Scheduling/Sequence • Cost/Schedule Results Summary of Conclusions/Recommendations Acknowledgements AE Senior Thesis | Justin A. Woishnis | Construction Management |

  4. PROJECT OUTLINE Base Building Project Introduction Project Background • Site Overview • Building properties Parking Garage Analysis #1: Solar PV Analysis • Site/Roof Investigation • Shading Analysis New Parking Lot • Energy Use Study • Panel Selection and Layout • System Costs  Structural Breadth Analysis #2: Technology to the Field • Material Tracking • Case Study • Feasibility Analysis #3: Interior CMU Wall To Precast Tenant Parking • CMU Overview • CMU Estimate • Precast Overview • Precast Estimate • Results/Feasibility Construction Parking Analysis #4: Alternative Façade Sequence • Initial Sequence • New Façade Scheduling/Sequence • Cost/Schedule Results Summary of Conclusions/Recommendations Acknowledgements During Construction Existing Site Site Plan NATIONAL CANCER INSTITUTE AE Senior Thesis | Justin A. Woishnis Rockville| Maryland

  5. PROJECT OUTLINE Features Project Introduction Project Background • Site Overview • Building properties Twin 7-story Towers w/ Analysis #1: Solar PV Analysis • Site/Roof Investigation 3-story Connector • Shading Analysis • Energy Use Study • Panel Selection and Layout • System Costs Lower-Level including:  Structural Breadth Analysis #2: Technology to the Field • • Data Center Material Tracking • Case Study • Feasibility • Fitness Center Analysis #3: Interior CMU Wall To Precast • CMU Overview • Auditorium • CMU Estimate • Precast Overview • Precast Estimate • Results/Feasibility Green Roof Analysis #4: Alternative Façade Sequence • Initial Sequence • New Façade Scheduling/Sequence • Cost/Schedule Results Summary of Conclusions/Recommendations Curtain Wall Acknowledgements NATIONAL CANCER INSTITUTE AE Senior Thesis | Justin A. Woishnis Rockville| Maryland

  6. PROJECT OUTLINE Co Core & Shell Project Introduction Precast Panel Facade Project Background • Site Overview Batch Plant • Building properties Cast-In-Place Concrete Analysis #1: Solar PV Analysis • Site/Roof Investigation Tower Cranes • Shading Analysis Structure • Energy Use Study • Panel Selection and Layout • System Costs  Structural Breadth Post-Tension Beams Analysis #2: Technology to the Field • Material Tracking • Case Study • Feasibility Analysis #3: Interior CMU Wall To Precast • CMU Overview • CMU Estimate • Precast Overview • Precast Estimate • Results/Feasibility Analysis #4: Alternative Façade Sequence • Initial Sequence • New Façade Scheduling/Sequence • Cost/Schedule Results Summary of Conclusions/Recommendations Acknowledgements NATIONAL CANCER INSTITUTE AE Senior Thesis | Justin A. Woishnis Rockville| Maryland

  7. PROJECT OUTLINE Problem Background Site/Roof Investigation Project Introduction Project Background • Site Overview • Building properties • LEED Gold Certification Analysis #1: Solar PV Analysis Blue- Available Roof • Site/Roof Investigation • Shading Analysis • Energy Use Study ANALYSIS TOPIC #1 • No Renewable Energy Sources • Panel Selection and Layout • System Costs Area: 28,441 S.F.  Structural Breadth Analysis #2: Technology to the Field SOLAR R (P (PV) AR ) ARRAY • Material Tracking • Large Energy Consumption • Case Study • Feasibility Red- Penthouse Analysis #3: Interior CMU Wall To Precast • Problem Solution CMU Overview • CMU Estimate • Precast Overview Area: 4,359 S.F. • Precast Estimate • Results/Feasibility • Roof-Mounted Solar Photovoltaic Array Analysis #4: Alternative Façade Sequence • Initial Sequence • New Façade Scheduling/Sequence • Cost/Schedule Results • Large Available Roof Areas w/ Minimal Sun Summary of Conclusions/Recommendations Acknowledgements Obstructions NATIONAL CANCER INSTITUTE AE Senior Thesis | Justin A. Woishnis Rockville| Maryland

  8. PROJECT OUTLINE Summer Spring Project Introduction Project Background Shading Analysis Solstice • Site Overview Equinox • Building properties June 20th Analysis #1: Solar PV Analysis March 20th • Site/Roof Investigation • Shading Analysis • Energy Use Study • Panel Selection and Layout • System Costs  Structural Breadth Analysis #2: Technology to the Field • Material Tracking • Case Study 10:00 AM 1:00 PM 4:00 PM 10:00 AM 1:00 PM 4:00 PM • Feasibility Analysis #3: Interior CMU Wall To Precast • CMU Overview Winter Fall Equinox • CMU Estimate • Precast Overview Solstice September 22nd • Precast Estimate • Results/Feasibility Analysis #4: Alternative Façade Sequence December 21st • Initial Sequence • New Façade Scheduling/Sequence Optimum Roof Area = 20,617 7 S.F. 20,617 S. • Cost/Schedule Results Summary of Conclusions/Recommendations Acknowledgements NATIONAL CANCER INSTITUTE AE Senior Thesis | Justin A. Woishnis Rockville| Maryland

  9. PROJECT OUTLINE Main Lobby & Corridor Lighting Count Watts Project Introduction Type Description Lamps West East West East Total Project Background Initial Investigation: RC1 9" Aperture Semi-Recessed Downlight 1-F32WTRT 17 25 544 800 1344 • Site Overview Energy Use Study RF1 6" Recessed Linear Light Fixture 2-F28T5 3 3 168 168 336 • Building properties • Full electricity Load = NOT FeasiblE Analysis #1: Solar PV Analysis RC2 5 1/2" Aperture Downlight 1-F32WTRT 9 12 288 384 672 • 50% Electricity Load = NOT Feasible • Site/Roof Investigation RM3 Adjustable Semi-Recessed Wall Washer 1-32W PMH 7 7 224 224 448 • Shading Analysis Decorative Lit Panel w/ Remote LED • 10% Electricity Load = Still NOT Feasible • Energy Use Study JL1C Driver/Transformer LED 4.5W/LF 4 4 360 360 720 • Panel Selection and Layout U.S. DOE, Annual Energy Review PM1 Decorative Pendant 1-70W 1 3 70 210 280 • System Costs JM2 Linear Light Fixture 3-CMH70 4 4 840 840 1680 2009  Structural Breadth JM1 Surface Mounted Lobby Fixture 14-CMH20 1 0 280 0 280 Analysis #2: Technology to the Field RM2 6" Lensed Wall Washer 1-70W, PAR30 3 4 210 280 490 • Material Tracking RM1 6" Aperture Downlight 1-70W, PAR30 1 1 210 210 420 • Case Study Average Site Energy Intensity per • Feasibility Decorative Lit Panel w/ Remote LED Analysis #3: Interior CMU Wall To Precast JL1A Driver/Transformer LED 4.5W/LF 4 4 360 360 720 Square Foot calculated to be • CMU Overview RF3 10" Recessed Linear Light Fixture 4-F21T5 0 4 0 336 336 Revised Approach: • CMU Estimate 19,344,000 kwh TOTAL 3554 4172 7726 • Precast Overview • Limit Energy Target • Precast Estimate Watts Total • Results/Feasibility • All 24 Hour Lighting Exit Signs ( 2-way) 3.4 408 Analysis #4: Alternative Façade Sequence Overall Total (Watts) 15023 Exit Signs (1-way) 1.8 281 • Initial Sequence • Main Lobby Entrance, Corridors, Elevator • New Façade Scheduling/Sequence Elevator 2-F28 2352 • Cost/Schedule Results Lobbies, Stairways and Exit Signs Stairway 2-F28 4256 kW 15.023 Summary of Conclusions/Recommendations 7297 Acknowledgements Overall Total (Watts) 15023 kW 15.023 NATIONAL CANCER INSTITUTE AE Senior Thesis | Justin A. Woishnis Rockville| Maryland

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend