support services building
play

SUPPORT SERVICES BUILDING PENN STATE MILTON S. HERSHEY MEDICAL - PowerPoint PPT Presentation

SUPPORT SERVICES BUILDING PENN STATE MILTON S. HERSHEY MEDICAL CENTER PENN STATE AE SENIOR THESIS FINAL PRESENTATION WILL LAZRATION CONSTRUCTION MANAGEMENT - DR. RILEY SUPPORT SERVICES BUILDING WILL LAZRATION PRESENTATION OUTLINE


  1. SUPPORT SERVICES BUILDING PENN STATE MILTON S. HERSHEY MEDICAL CENTER PENN STATE AE SENIOR THESIS FINAL PRESENTATION WILL LAZRATION CONSTRUCTION MANAGEMENT - DR. RILEY

  2. SUPPORT SERVICES BUILDING WILL LAZRATION PRESENTATION OUTLINE CONSTRUCTION MANAGEMENT PENN STATE MILTON S. HERSHEY MEDICAL CENTER PRESENTATION OUTLINE � I. PROJECT BACKGROUND II. INTRODUCTION OF ANALYSIS III. ANALYSIS #1: FOUNDATION RE-DESIGN I. Initial Conditions II. Re-Design IV. ANALYSIS #2: ROOFING I. Part I: Roofing Type Comparison II. Part II: Elimination of Offset Roof V. ANALYSIS #3: RENEWABLE ENERGY SOURCES I. Part I: Geothermal System II. Part II: Installation of PV Array I. Site Analysis II. System Design VI. SUMMARY & CONCLUSION VII. ACKNOWLEDGEMENTS

  3. SUPPORT SERVICES BUILDING WILL LAZRATION PROJECT BACKGROUND CONSTRUCTION MANAGEMENT PENN STATE MILTON S. HERSHEY MEDICAL CENTER PRESENTATION OUTLINE � � � � I. PROJECT BACKGROUND ������ � ����������������������������� II. INTRODUCTION OF ANALYSIS � ���������������������� III. ANALYSIS #1: FOUNDATION RE-DESIGN I. Initial Conditions ��������� II. Re-Design � ������������������������ ���������� IV. ANALYSIS #2: ROOFING �������� ����������� I. Part I: Roofing Type Comparison � ��������� II. Part II: Elimination of Offset Roof � ������������ �!!!����"���#��� V. ANALYSIS #3: RENEWABLE ENERGY � "$�������%�&'�����(���������)$���� I. Part I: Geothermal System II. Part II: Installation of PV Array ������������������� SSB Site I. Site Analysis � *��������������+�*���(�,"��,"$��� II. System Design � ���������)�%�+����-�.��/� VI. SUMMARY & CONCLUSION � ���0��������+�1 ��2�3�22 4!!�5�� � �������������*����+��, ,�! !�� 6,2 ,�! VII. ACKNOWLEDGEMENTS

  4. SUPPORT SERVICES BUILDING WILL LAZRATION PHOTOVOLTAIC ARRAY SYSTEM DESIGN CONSTRUCTION MANAGEMENT PENN STATE MILTON S. HERSHEY MEDICAL CENTER PRESENTATION OUTLINE � � � � ARRAY ORIENTATION & TILT COMPARISON I. PROJECT BACKGROUND Annual AC Energy Yearly Output per Module vs. Array Tilt Angle Array Orientation Min. Row Spacing Size of System Average Solar Radiation kWh/ Panel/ II. INTRODUCTION OF ANALYSIS Angle Max # of Panels (Deterate Factor of 0.8) to Avoid Shading (kW) (kWh/m^2/day) Year Due South Orientation (kWh) III. ANALYSIS #1: FOUNDATION RE-DESIGN 410.00 Rotated 31° 11'-10" 252 80.64 4.41 97,118 385.39 Yearly Output per Module 35° I. Initial Conditions Due South 9'-9" 253 80.96 4.55 101,033 399.34 400.00 (kWh/year/module) II. Re-Design Rotated 31° 10'-5" 248 79.36 4.42 95,832 386.42 30° 390.00 IV. ANALYSIS #2: ROOFING Due South 8'-8" 269 86.08 4.54 107,280 398.81 380.00 I. Part I: Roofing Type Comparison 370.00 II. Part II: Elimination of Offset Roof 9:00 AM 12:00 PM 3:00 PM 360.00 V. ANALYSIS #3: RENEWABLE ENERGY 350.00 I. Part I: Geothermal System 340.00 II. Part II: Installation of PV Array 0 5 10 15 20 25 30 35 40 45 50 I. Site Analysis Array Tilt Angle (°) II. System Design VI. SUMMARY & CONCLUSION Minimum Row Spacing Determined by Shadow Lengths VII. ACKNOWLEDGEMENTS Rotated 31° Orientation with 35° Tilt Due South Orientation with 35° Tilt

  5. SUPPORT SERVICES BUILDING WILL LAZRATION PHOTOVOLTAIC ARRAY SYSTEM DESIGN CONSTRUCTION MANAGEMENT PENN STATE MILTON S. HERSHEY MEDICAL CENTER PRESENTATION OUTLINE � � � � Feed From Inverter to Combiner Panel/Box Sizing I. PROJECT BACKGROUND � Max current from inverter data sheet: 91A/phase II. INTRODUCTION OF ANALYSIS 15kV Utility In DC Power From Array � 91A x 1.56 (NEC Multiplier) = 142A III. ANALYSIS #1: FOUNDATION RE-DESIGN I. Initial Conditions � NEC Table 310.15(B)(2)(a): Multiplier for 4-6 current carrying 500 kVA Transformer 500 kVA II. Re-Design conductors in a raceway = 0.8 Satcon 75kW Transformer Inverter IV. ANALYSIS #2: ROOFING � NEC Table 310.16 (90°C Wire): 2/0 AWG = 195A I. Part I: Roofing Type Comparison Inverter 1 set of (4) 2/0 AWG Main Electrical Room Net Meter 195A x 0.8 = 156A > 142A => OK II. Part II: Elimination of Offset Roof Production Meter Combiner V. ANALYSIS #3: RENEWABLE ENERGY AC FUSED DISCONNECT SWITCH SIZING Panel/Box I. Part I: Geothermal System � Max current from inverter data sheet: 91A/phase Load Meter 400A AC Fused II. Part II: Installation of PV Array Disconnect Switch I. Site Analysis � 91A x 3 phases 1.25 (NEC Multiplier) = 342A II. System Design Main Distribution Panel � Ideal fused disconnect switch size: 350A => not available => 400A VI. SUMMARY & CONCLUSION VII. ACKNOWLEDGEMENTS � Interrupt Rating must be greater than; 500kVA / (.480kV * 3^ (1/2) = 600A

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend