Riverwood HS Replacement School Proposed Final Building Phase Design Change February 12, 2019 AGENDA: Proposed Final Building Phase Design Change Current Construction Budget / Projected Costs / Advantages of New Design Previous


slide-1
SLIDE 1

Riverwood HS Replacement School

Proposed Final Building Phase Design Change February 12, 2019 AGENDA: Proposed Final Building Phase Design Change

  • Current Construction
  • Budget / Projected Costs / Advantages of New Design
  • Previous Plan / Sequencing
  • Elevation
  • Site plan
  • Floor Plan
  • Schedule

Questions

slide-2
SLIDE 2

Construction Summary

2

Riverwood High School Replacement

Current Project Status

By the Beginning of School Year 2019-20

✓ Core Academic Classrooms ✓ Career Tech Labs ✓ Media Center ✓ Cafeteria

Final Building Phase Includes:

❑ Performing Arts – Music, Drama, & Auditorium ❑ Physical Education and Health

slide-3
SLIDE 3

Advantages of the Proposed Design Change of Final Building Phase

  • Meets our building program / educational specifications
  • Includes full size practice field
  • Lessens impact on students during construction
  • Improves site plan and makes better use of campus acreage
  • Moves building further from I-285
  • Reduces the additional funding required by $10.8 Million

3

Riverwood High School Replacement

Budget / Projected Costs - Proposed Final Building Phase Design Change Riverwood HS Replacement Project Budget and Cost History

Combined SPLOST IV and SPLOST V Over/Under Initial Budget Additional Budget Required Initial Budget* November 2016

*Represents budgets from SPLOST IV and SPLOST V in November of 2016

$10,842,524

Costs Based Upon Proposal January 2019 Redesigned Final Phase Estimate February 2019

January 2019 Proposal - Redesigned Final Phase Estimate =

$14,665,152 $3,822,628 $117,581,508 $106,738,984 ($21,951,352) ($11,108,828) Current Approved Budget June 2018 Construction Estimate $95,630,156 $102,916,356 $112,057,812 ($7,286,200) ($16,427,656) September 2018 $9,141,456

slide-4
SLIDE 4

Riverwood High School Replacement

Current Project Sequencing

4

New Final Phase Design

slide-5
SLIDE 5

5

Riverwood High School Replacement

Elevations - Proposed Final Building Phase Design Change

slide-6
SLIDE 6

Riverwood High School Replacement

Revised Site Plan - Proposed Final Building Phase Design Change

6

slide-7
SLIDE 7

7

Riverwood High School Replacement

Level 200 - Proposed Final Building Phase Design Change

slide-8
SLIDE 8

8

Riverwood High School Replacement

Level 100 - Proposed Final Building Phase Design Change

slide-9
SLIDE 9

Draft Schedule

9

Riverwood High School Replacement

Schedule - Proposed Final Building Phase Design Change Design and Approvals February 2019 - November 2019 Procurement December 2019 - February 2020 Demolition of Admin/Classrooms and Enabling for Existing Gymnasiums April 2020 - July 2020 Auditorium/Fine Arts Construction Summer 2020 and Summer 2021 Construction of Physical Education and Health Building September 2020 – July 2021 Demolition of Existing Gymnasiums September 2021 - December 2021 Site Work/Parking/New Practice Field January 2022 – July 2022

slide-10
SLIDE 10

QUESTIONS?