replacement project
play

REPLACEMENT PROJECT PRESENTED BY Mary Grace Houlihan Larkspur - PowerPoint PPT Presentation

CITY OF LARKSPUR BON AIR BRIDGE REPLACEMENT PROJECT PRESENTED BY Mary Grace Houlihan Larkspur Public Works Director DATE August 20, 2014 Bon Air Bridge Why Replace the Bridge? The Bridge is structural deficient Improve access and


  1. CITY OF LARKSPUR BON AIR BRIDGE REPLACEMENT PROJECT PRESENTED BY Mary Grace Houlihan Larkspur Public Works Director DATE August 20, 2014

  2. Bon Air Bridge

  3. Why Replace the Bridge? • The Bridge is structural deficient • Improve access and safety for pedestrians and bicyclists – Multi-use paths, – dedicated Bike Lanes – Barrier separation

  4. What is the Project? • Replacement of Bon Air Bridge with a wider, seismically safe new bridge – Within sensitive environmental context • Barrier-protected multi-use path • Traffic and lighting improvements – Downcast nighttime lighting, meeting International Dark Sky standards • Organic, natural design

  5. Project History • 1958 – Original Bridge was built • 1970 - Major foundation repair due to damage from channel dredging • 1994 - walkway widening and a seismic retrofit • 2000 – Cal-trans inspections showed crumbling at several support locations. Further inspections in 2003 revealed severe deterioration of concrete, including visible cracks on some supports, and poor deck conditions. • 2002 - the City applied for and received funding through the Highway Bridge Replacement Grant to replace the Bon Air Bridge. • 2012 - temporary supports were added to stabilize the structure. A new replacement bridge was determined to be the most cost-effective measure to ensure continued unrestricted access for all modes of travel over the bridge.

  6. Project History • The final design for the bridge is the result of an extensive public outreach process and in 2008 the City Council approved the conceptual design for the new bridge.

  7. Project History • 2012 - Both California Environmental Quality Act and National Environmental Protection Act certifications were completed for the project • Permits have been obtained through RWQCB, US Fish & Wildlife, Army Corps of Engineers and California Fish and Wildlife. BCDC is nearing completion and is anticipated to be in place in the next couple of months. • Design has been completed • Utility relocations has been initiated by Comcast & MMWD • Contractor prequalification has been initiated

  8. Status and Schedule • PGE to initiated temporary relocation in Fall 2014 • Final Construction Authorization is anticipated by January 2015 • Project Bid in early 2015 • Bridge Construction slated to begin in Spring 2015 and anticipated to end Summer 2018

  9. Public Outreach • Council Presentation Update – Tonight • Neighborhood and Business community meetings to be scheduled from Sept – Dec, 2014 • Project Website to be opened in September 2014. larkspurbridges.com • Public Outreach boards to be placed on main trails and at City Hall, Recreation, Library & Piper Park

  10. Constraints on Construction Preservation and monitoring of fourteen regulated species: • California Clapper Rail and Black Rail • Central California Coast Steelhead and Coho Salmon • North American Green Sturgeon • Western Pond Turtle • Northern Harrier • White-tailed Kite • Short-eared Owl • San Francisco Common Yellowthroat • Samuels (San Pablo) Song Sparrow • Western Red Bat and Pallid Bat • Salt Marsh Harvest Mouse Photo: Flickr/Len Blumin

  11. Constraints (Continued) • In Water Work limited based on Clapper Survey and Fish Migration • Accessibility for vehicles, pedestrians, bicycles, and water traffic • Maintenance and installation of utility services • Maintenance of business access • Emergency access to hospital • Safe and functional work site

  12. Schedule of Construction • Spring 2015 Anticipated start; shift traffic, close bike lane & upstream walkway • Summer 2015/Spring 2016 Install temporary trestles, demolish upstream portion of existing bridge, abutment construction, utility & right-of- way work north and south of the bridge • Fall 2016/Winter 2017 Construct upstream side of new bridge

  13. Schedule of Construction (Continued) • February 2017 Move traffic to new upstream bridge (no bike lanes, one extra wide multi- use path) • July 2017/January 2019 Demolish remaining bridge, construct new downstream half • January 2019 Open to full traffic • Spring/Summer 2019 Complete restoration and removal of trestles Photo: Roger Tabor/USFWS

  14. Construction Impacts • Approximately 3-4 years of construction from Spring 2015 to Summer 2018, 5-6 days per week – Monday – Friday 7:30AM to 6:00PM, Saturday 8:30AM to 6:00PM • Periodic night work • Periodic pedestrian and bike traffic control for safety and utility service requirements • Periodic one-way traffic on bridge (10- to 15-minute delays) • Periodic waterway traffic control • Anticipated full closures: – 2 weeks for delivery and installation of precast girders – 1 week for closure pour between upstream and downstream halves of new bridge

  15. Public Info Updates during construction • Website • E-mail notifications • 24 hour hotline • Notice boards on key trails, Piper Park & City buildings • Contact signs at entrances to residential communities throughout the City • E-mail notices through schools and PD contact lists • Message Boards at either end of the bridge Trails & Neighborhoods

  16. Environmental Mitigation APE = Area of Potential Effect

  17. Bon Air Bridge Replacement APE = Area of Potential Effect

  18. Tidal Marsh Restoration and Dog Park Relocation at Piper Park

  19. Access and Dock Improvements at Bon Air Landing Park ADA Pathway

  20. Access and Dock Improvements at Marin Rowing Club ADA Pathway

  21. Drainage Improvements on Magnolia

  22. Questions?

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend