Removing Salt From Coal Mine Wastewater in a Remote, Wet Area: Full - - PowerPoint PPT Presentation

removing salt from coal mine wastewater in a remote wet
SMART_READER_LITE
LIVE PREVIEW

Removing Salt From Coal Mine Wastewater in a Remote, Wet Area: Full - - PowerPoint PPT Presentation

Removing Salt From Coal Mine Wastewater in a Remote, Wet Area: Full Scale Experience Srikanth Muddasani, P.E. Veolia Water Technologies, USA Project Background Centralized ZLW treatment facility to handle water from six mine locations


slide-1
SLIDE 1

Removing Salt From Coal Mine Wastewater in a Remote, Wet Area: Full Scale Experience

Srikanth Muddasani, P.E. Veolia Water Technologies, USA

slide-2
SLIDE 2
  • Centralized ZLW treatment facility to handle water from six

mine locations

  • All six mines located within Monongahela River Basin
  • Regulatory driver = Chlorides to < 218 mg/L
  • Solid wastes generated are disposed in on-site landfill
  • Treated effluent is discharged to creek and/or used as frac

water

Project Background

2

slide-3
SLIDE 3

Contributing Mine Locations

18” Force Main collects water from 4 mines to the North 14” Force Main collects water from 2 mines to the South CENTRALIZED TREATMENT FACILITY

slide-4
SLIDE 4
  • Centralized ZLW treatment facility is designed to treat

5 MGD (795 m3/h) of mine water

  • Mine water, pretreated for metals removal where needed,

conveyed from six source points to the facility through 32 miles of pipeline

  • Executed through a Design-Build-Operate contract with Veolia
  • June 2010 - Request for proposals issued
  • April 2011 - Project awarded
  • July 2011 - Construction began
  • May 2013 - Full operation

The Project

4

slide-5
SLIDE 5

Note 1: Average Value based on the data collected between Jun 1st 2014 to Dec 31st 2014 Note 2: Average Value based on the data collected between Aug 20th,2014 to Sep 5th, 2014

Design Basis - Influent Mine Water

5

Parameters Original Design Current Design1

Design Flow, gpm 3500 (795 m3/h) 2026 (460 m3/h) pH, S.U. 5 - 10 7.39 Temperature, deg F 38 – 85 (3 – 30 deg C) 60 – 72 (15-22 deg C) Calcium, mg/L 300 217 Magnesium, mg/L 200 104 Iron, mg/L 150 0.27 Manganese, mg/L 2 0.27 Alkalinity, mg/L CaCO3 700 - 1200 891 Sulfate, mg/L 5,500 2700 2 Chloride, mg/L 1,500 1530 2 TDS, mg/L 10,000 8600 Silica, mg/L as SiO2 10 10

slide-6
SLIDE 6

Note 1: Applied to product water prior to remineralization

Effluent Water Quality Requirements

6

Parameters Maximum Effluent Concentration

Chlorides, mg/L < 218 TDS, mg/L < 150 1 pH, S.U. 6 to 9 Minimum Hardness, mg/l as CaCO3 ≥ 50

slide-7
SLIDE 7
  • Raw Water Pretreatment System
  • Reverse Osmosis System
  • Thermal Brine Management System

The Process: Three Primary Components

7

slide-8
SLIDE 8

Process Overview

8

Primary Objectives

  • 1. Remove TDS and Chlorides
  • 2. Zero Liquid Waste
slide-9
SLIDE 9

Facility Overview

9

Evaporator Crystallizer RO Trains Raw Water Tank Multimedia Filters Lime & Soda Ash Silos Softening System 1st Stage Clarifier Dewatering Building

slide-10
SLIDE 10
  • Multi-stage process
  • Two aeration tanks for

precipitation of metals such as manganese and iron

  • Crystallization tank for removal of

alkalinity and hardness

  • Draft-tube reactor design
  • Solids recycle
  • Reduce chemical consumption
  • Enhance particle growth and

settling characteristics

  • Conventional circular clarifier

design

Chemical Softening System

10

slide-11
SLIDE 11
  • Removes residual suspended solids

in the effluent from upstream clarification and aluminum precipitation processes

  • Backwash water is returned to the

Raw Water Feed Tank

  • Filtrate is conveyed to the RO

System

Multimedia Filter System

11

slide-12
SLIDE 12

Reverse Osmosis System

  • RO Feed Tank, followed by Cartridge Filtration
  • RO Skids designed to achieve chloride and TDS specifications

while operating at a high recovery rate

  • Five parallel skids, each sized to handle 25% of the design

flow, 1 standby

  • Thirty-one pressure vessels per skid, each with seven

seawater RO membrane elements

  • Permeate flows to Product Water Tank, which also collects

distillate from Brine Management System

  • Prior to discharge, the Product Water Tank effluent is re-

mineralized using carbon dioxide and lime water, to protect aquatic life

  • Discharged to creek, or to a truck loading station for

reuse in energy-related operations.

  • Reject is sent to the thermal Brine Management System

The Process Flow - RO System

12

slide-13
SLIDE 13

Evaporator

  • Concentric falling film unit is divided into two sections

with a low concentration side and a high concentration side

  • Split design to reduce overall power consumption

by allowing a portion of the evaporation to occur at a lower boiling point rise than the final concentration

  • Evaporator operates as a Mechanical Vapor

Recompression System

  • Recycle of hot vapor in the system; minimize

auxiliary steam

  • Distillates from the Evaporator and Crystallizer are

pumped through a Feed Preheater for heat transfer to the incoming brine

  • Heat exchanger for efficient energy utilization

Evaporation

13

slide-14
SLIDE 14
  • Crystallizer includes a vapor body, recirculation

pump, and forces circulation heat exchanger

  • Vapors created by concentrating the slurry in

the Crystallizer are recompressed and recirculated through the heater

  • As the brine concentration increases, the

solution becomes supersaturated and salts precipitate, resulting in a brine slurry

  • A slip stream of the crystallizer slurry is sent to

centrifuges for dewatering

  • The result: Zero Liquid Waste
  • Dewatered salt cake is disposed in the on-site

landfill along with the dewatered sludge from the softening processes

Crystallization

14

slide-15
SLIDE 15

Thermal Brine Management System

15

Crystallizer Evaporator Heat Exchanger Distillate Tank Crystallizer

slide-16
SLIDE 16
  • Dewatered Salt and Softening

Sludge is brought separately to

  • nsite landfill
  • Dewatered Salt contains

approximately 90 – 95% in solids concentration and Sludge contains 50 – 65% in solids concentration.

  • Both passes paint filter press test
  • Both Salt and Sludge are mixed

before applied to landfill

  • Lechate generated in landfill is

collected in storage tank and metered back to thermal system

Land fill

16

slide-17
SLIDE 17
  • Chemical Storage and Feed Systems
  • Lime Water Preparation System
  • RO Membrane Clean-in-Place

System

  • Compressed Air System
  • Electrical and Control Rooms
  • Laboratory
  • Communications Equipment
  • Maintenance and Storage Areas
  • Personnel Amenities

Ancillary Support Systems

17

slide-18
SLIDE 18

Feed Water Conductivity

18

2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 06/01/14 07/06/14 09/16/14 10/21/14 11/25/14 12/31/14 Conductivity (µs/cm) Days Current Feed Conductivity Design Feed Conductivity

Original Design Conductivity = 13,000 µs/cm Current Avg Conductivity = 11,180 µs/cm

slide-19
SLIDE 19

Product Water Conductivity

19

Product water Cond before Remineralization = 63 µs/cm Final Effluent Discharge Cond = 142 µs/cm 20 40 60 80 100 120 140 160 180 200 06/01/14 07/06/14 09/16/14 10/21/14 11/25/14 12/31/14 Conductivity (µs/cm) Days Product Water Cond before Remin Final Eff Discharge Cond

slide-20
SLIDE 20

Feed Water Chlorides

20

1400 1450 1500 1550 1600 1650 8/20/14 8/22/14 8/26/14 8/28/14 9/1/14 9/2/14 9/3/14 9/4/14 9/5/14 Chlorides (mg/L) Days Current Feed Chlorides Current Avg Feed Chlorides = 1,530 mg/l

slide-21
SLIDE 21

Final Effluent Chlorides

21

0.00 5.00 10.00 15.00 20.00 25.00 1/1/2014 1/21/2014 2/10/2014 3/2/2014 3/22/2014 4/11/2014 5/1/2014 5/21/2014 6/10/2014 Effluent Chlorides, mg/l Days Final Effluent Chlorides = 16 mg/l

slide-22
SLIDE 22

Please Note: Waste Estimation for design condition was estimated based on 3500 gpm flow Waste Estimation for Current Average Condition was estimated based on 2026 gpm flow

Estimated Waste Generation

22

Waste Design Condition Current Average Condition

Softening Sludge (on a 100% dry basis) 6,666 lb/hr (3,030 kg/hr) 2,200 lb/hr (1,000 kg/hr) Salt (on a 100% dry basis) 17,500 lb/hr (7,954 kg/hr) 8,710 lb/hr (3,960 kg/hr) Total Waste Generated (on 100% dry basis) 24,166 lb/hr (10,984 kg/hr) 10,910 lb/hr (4,960 kg/hr)

slide-23
SLIDE 23
  • Treatment process achieves > 99% removal of chlorides using

state-of-the-art membrane technology

  • Energy efficient evaporation and crystallization technology for brine

management

  • Solid waste generated onsite is disposed into onsite landfill and leachate

generated at the landfill is sent back to the facility’s thermal treatment process

  • Since no liquid waste leaves the property, this facility is termed as

a “zero liquid waste” (ZLW) facility

Summary

23

slide-24
SLIDE 24

Thank You!