REFERENDUM OVERSIGHT COMMITTEE September 10, 2019 AGENDA image - - PowerPoint PPT Presentation

referendum oversight committee
SMART_READER_LITE
LIVE PREVIEW

REFERENDUM OVERSIGHT COMMITTEE September 10, 2019 AGENDA image - - PowerPoint PPT Presentation

REFERENDUM OVERSIGHT COMMITTEE September 10, 2019 AGENDA image Approval of Minutes from June 3rd Meeting All Projects image - Budgets - Progress Review Active Projects image - Design/Bidding/Construction Updates -


slide-1
SLIDE 1

REFERENDUM OVERSIGHT COMMITTEE

September 10, 2019

slide-2
SLIDE 2

image image image image image image image image image

AGENDA

  • Approval of Minutes from June 3rd Meeting
  • All Projects
  • Budgets
  • Progress Review
  • Active Projects
  • Design/Bidding/Construction Updates
  • Spending Updates
  • Financial Update
  • Overall Spend
  • Financial Oversight Committee
  • Revenue Sources
  • Elementary and Middle School Capacity Discussion and Options
slide-3
SLIDE 3

image image image image image image image image image

PROJECTS/BUDGETS

  • Central High School
  • Centennial High School
  • Edison Middle School
  • Dr. Howard Elementary
  • South Side Elementary
  • International Prep Academy
  • Spalding Park Fields
  • McKinley Fields

$ 87.1M $ 63.3M $ 15.0M $ 16.1M $ 11.1M $ 6.0M $ 3.6M $ 6.2M $208.4M $ 9.2M $ 8.2M $ 10.1M $ 2.0M $ 1.0M $ - $ 0.3M $ 0.6M $31.4M

REFERENDUM INCREASE CURRENT

$ 96.3M $ 71.5M $ 25.1M $ 18.1M $ 12.1M $ 6.0M $ 3.9M $ 6.8M $239.8M

slide-4
SLIDE 4

image image image image image image image image image

PROGRESS

No Summer 2021 work Updated Substantial Completion Date - January 2020 TBD

slide-5
SLIDE 5

CENTRAL HIGH SCHOOL

slide-6
SLIDE 6

New Gym Basement Foundations

slide-7
SLIDE 7

New Gym Basement Foundations

slide-8
SLIDE 8

Renovated Seely Hall

slide-9
SLIDE 9

Third Floor Renovated Hallway

slide-10
SLIDE 10

Third Floor Renovated Classroom

slide-11
SLIDE 11

Third Floor Renovated Classroom

slide-12
SLIDE 12
  • Finalizing open items and punch list items inside the recently

renovated spaces.

  • Structural work for the north gym addition will continue. Precast

concrete walls will be installed this Fall.

  • After the structure starts taking shape, then the mechanical,

electrical, and HVAC infrastructure rough-in work will begin.

  • Hazardous material work will likely not happen until Spring or

Summer Breaks.

CENTRAL HIGH SCHOOL

FALL CONSTRUCTION UPDATE

slide-13
SLIDE 13

CENTRAL HIGH SCHOOL

PHASING PLAN - SPRING 2020

slide-14
SLIDE 14

CENTRAL HIGH SCHOOL

PHASING PLAN - SUMMER 2020

slide-15
SLIDE 15

CENTRAL HIGH SCHOOL

FIRST FLOOR PHASING PLAN - SUMMER 2020

slide-16
SLIDE 16

CENTRAL HIGH SCHOOL

FIRST FLOOR PHASING PLAN - SUMMER 2020

slide-17
SLIDE 17

CENTRAL HIGH SCHOOL

UPCOMING PROJECT ACTIVITIES (not construction related)

  • Finalize the Furniture, Fixtures, and Equipment design and

procurement package.

  • Begin planning and coordination for Summer 2020 moving,

abatement, and construction.

  • Owner provided equipment purchasing.
  • North Fields design - 2021.
slide-18
SLIDE 18
slide-19
SLIDE 19

CENTENNIAL HIGH SCHOOL

slide-20
SLIDE 20

South Addition

slide-21
SLIDE 21

North Addition - Storm Shelter

slide-22
SLIDE 22

Centennial High School

CONSTRUCTION PROGRESS PHOTO – STOCKPILE FOR FUTURE FILL

CENTENNIAL HIGH SCHOOL

CONSTRUCTION PROGRESS PHOTOS

North Addition - Storm Shelter

slide-23
SLIDE 23

2nd Floor Renovated Corridor (painting of wall tile not yet completed)

slide-24
SLIDE 24

Centennial High School

CONSTRUCTION PROGRESS PHOTO – STOCKPILE FOR FUTURE FILL

Scaffold structure built inside existing pool New interior partitions

CENTENNIAL HIGH SCHOOL

CONSTRUCTION PROGRESS PHOTOS

Renovated Gym

slide-25
SLIDE 25

CENTENNIAL HIGH SCHOOL

FALL CONSTRUCTION UPDATE

  • Finalizing open items and punch list items inside the recently

renovated spaces.

  • Structural work for the north and south additions will continue.

Precast concrete walls will continue at both additions.

  • After the structure starts taking shape, then the mechanical, electrical,

and HVAC infrastructure rough-in work will begin.

  • Coordination and preparations have started for moving and abatement

work over Winter Break.

slide-26
SLIDE 26

CENTENNIAL HIGH SCHOOL

FIRST FLOOR PHASING PLAN - SPRING 2020

slide-27
SLIDE 27

CENTENNIAL HIGH SCHOOL

SECOND FLOOR PHASING PLAN - SPRING 2020

slide-28
SLIDE 28

CENTENNIAL HIGH SCHOOL

FIRST FLOOR PHASING PLAN - SUMMER 2020

slide-29
SLIDE 29

CENTENNIAL HIGH SCHOOL

SECOND FLOOR PHASING PLAN - SUMMER 2020

slide-30
SLIDE 30

CENTENNIAL HIGH SCHOOL

UPCOMING PROJECT ACTIVITIES (not construction related)

  • Hazardous material design and bidding for Winter Break.
  • Finalize the Furniture, Fixtures, and Equipment design and

procurement package.

  • Begin planning and coordination for Summer 2020 moving,

abatement, and construction.

  • Spring 2020 renovations.
  • Owner provided equipment purchasing.
slide-31
SLIDE 31
slide-32
SLIDE 32

EDISON MIDDLE SCHOOL

slide-33
SLIDE 33

EDISON MIDDLE SCHOOL

PHASING PLAN - SUMMER 2020

slide-34
SLIDE 34

EDISON MIDDLE SCHOOL

PHASING PLAN - SUMMER 2020

slide-35
SLIDE 35

EDISON MIDDLE SCHOOL

PHASING PLAN - SUMMER 2020

slide-36
SLIDE 36

EDISON MIDDLE SCHOOL

UPCOMING PROJECT ACTIVITIES

  • DESIGN

○ Community Meeting - September 18, 2019 ○ Design Development Approval - October 15, 2019 Board Meeting

  • BIDDING

○ Early 2020 ○ May have package in late 2019

  • CONSTRUCTION

○ June 2020 - August 2021 ○ Hazardous Material abatement may occur earlier

slide-37
SLIDE 37
slide-38
SLIDE 38
  • DR. HOWARD

ELEMENTARY

slide-39
SLIDE 39

Updated 4/9/2019

Exterior Site View from James St.

slide-40
SLIDE 40

Exterior Site View from New Entrance on University Ave.

slide-41
SLIDE 41

Metal Framing

slide-42
SLIDE 42

Updated 4/9/2019

Elevator Pit

slide-43
SLIDE 43

Updated 4/9/2019

Interior Site Views

slide-44
SLIDE 44

image image image image image image image image image

  • DR. HOWARD ELEMENTARY

FALL CONSTRUCTION UPDATE

Updated 5/13/2019 9

  • Complete site utilities
  • Complete steel framing
  • Pouring interior concrete slabs and decking
  • Roofing

○ Target date for weather-tight building is end of November

  • Begin interior framing
  • Begin interior systems (mechanical, electrical, Plumbing) rough-in
slide-45
SLIDE 45

image image image image image image image image image

  • DR. HOWARD ELEMENTARY

UPCOMING PROJECT ACTIVITIES (not construction related)

  • Design of Furniture
  • Coordination of 3rd party inspections and testing
  • Playground design and equipment selection
slide-46
SLIDE 46
slide-47
SLIDE 47

SOUTH SIDE ELEMENTARY

slide-48
SLIDE 48

Interior Site - Inside New Gym

slide-49
SLIDE 49

Interior Site View

slide-50
SLIDE 50

Interior Renovated Areas

slide-51
SLIDE 51

SOUTH SIDE ELEMENTARY

SUMMER CONSTRUCTION PROGRESS

Interior Renovated Areas

slide-52
SLIDE 52

SOUTH SIDE ELEMENTARY

FALL CONSTRUCTION UPDATE

  • Complete steel framing
  • Complete pouring interior concrete slabs and decking
  • Roofing
  • Begin interior framing of addition
  • Begin interior systems (mechanical, electrical, plumbing) rough-in
  • Complete punch list items for summer interior renovations
  • Update on delays experienced over this summer and recovery plan
slide-53
SLIDE 53

SOUTH SIDE ELEMENTARY

PHASING PLAN - SPRING 2020

slide-54
SLIDE 54

SOUTH SIDE ELEMENTARY

PHASING PLAN - SUMMER 2020

slide-55
SLIDE 55

SOUTH SIDE ELEMENTARY

UPCOMING PROJECT ACTIVITIES (not construction related)

  • Purchase of furniture for addition
  • Coordination of 3rd party inspections and testing
  • Purchase of owner furnished materials for addition
  • Coordinate moves for occupancy of the addition in January 2020

Spring 2020 renovations in the existing school

  • Playground design and equipment selection
slide-56
SLIDE 56
slide-57
SLIDE 57

MCKINLEY FIELD

slide-58
SLIDE 58

View from the new track - facing North

slide-59
SLIDE 59

Future McKinley Fieldhouse

slide-60
SLIDE 60

View from new track - Facing North-West

slide-61
SLIDE 61

View from new track - facing South West

slide-62
SLIDE 62

MCKINLEY FIELD

FALL CONSTRUCTION ACTIVITIES

  • Complete site grading and paving for track and field events
  • Install of synthetic turf
  • Fieldhouse

○ Construction of CMU walls, exterior windows and doors ○ Roofing ○ Interior framing and install of MEP systems

slide-63
SLIDE 63

MCKINLEY FIELD

UPCOMING PROJECT ACTIVITIES (not construction related)

  • Coordination and purchase of Owner Furnished items, including

○ Scoreboard ○ Audio visual equipment ○ Furniture, signage, and equipment for Field House ○ Athletic equipment

  • Coordination of 3rd party inspection and testing
slide-64
SLIDE 64
slide-65
SLIDE 65

FINANCIAL UPDATE

slide-66
SLIDE 66
slide-67
SLIDE 67

FINANCIAL UPDATE

  • August 12, 2019 Board of Education authorized

establishing new standing Finance Committee. ○ Currently accepting applications for new members

slide-68
SLIDE 68

ENROLLMENT PROJECTIONS K-5

*Current K-5 Enrollment as of August 20, 2019 = 4,951

Source: Cooperative Strategies Development Report, October 2018

slide-69
SLIDE 69

ENROLLMENT PROJECTIONS MIDDLE SCHOOL

*Current M.S. Enrollment as of August 20, 2019 = 2,329

Source: Cooperative Strategies Development Report, October 2018

slide-70
SLIDE 70

PAST AND PRESENT 6-8 ENROLLMENT BY BUILDING

Total Students:

  • 2017 - 18 = 2,076
  • 2018 - 19 = 2,276
  • 2019 - 20 = 2,329

Increase in growth over two years = 253 students

slide-71
SLIDE 71

OPTIONS TO ADDRESS CAPACITY: PORTABLES

Location Portable(s) Annual Lease Franklin 3 $40,500 Jefferson 2 $27,000 IPA 1 $13,500 Stratton 1 $13,500 Barkstall 1 $13,250 YAP (@ Columbia) 1 $13,250 Annual Cost $121,000*

*Portables require delivery, install and removal costs. Typically $9K/portable.

slide-72
SLIDE 72
  • IPA 2-Story Addition with Renovation (Tier II Option B)

○ ~$22M* ○ 82K SF (currently 43K SF) ○ Capacity = 648 students (Adds ~200 seats from current design capacity of 474)

  • 4th Middle School

○ ~$42M* ○ 118K SF ○ Capacity = 600 students ○ Assumes built on land adjacent to Barkstall (for estimating purposes) ○ Soccer field, baseball and bleachers *Updated from 2016 with what we know now.

OPTIONS TO ADDRESS CAPACITY: BUILD

slide-73
SLIDE 73

REFERENDUM OVERSIGHT COMMITTEE

QUESTIONS

September 10, 2019

Next Meeting - December 2, 2019