REFERENDUM OVERSIGHT COMMITTEE
September 10, 2019
REFERENDUM OVERSIGHT COMMITTEE September 10, 2019 AGENDA image - - PowerPoint PPT Presentation
REFERENDUM OVERSIGHT COMMITTEE September 10, 2019 AGENDA image Approval of Minutes from June 3rd Meeting All Projects image - Budgets - Progress Review Active Projects image - Design/Bidding/Construction Updates -
September 10, 2019
image image image image image image image image image
image image image image image image image image image
$ 87.1M $ 63.3M $ 15.0M $ 16.1M $ 11.1M $ 6.0M $ 3.6M $ 6.2M $208.4M $ 9.2M $ 8.2M $ 10.1M $ 2.0M $ 1.0M $ - $ 0.3M $ 0.6M $31.4M
REFERENDUM INCREASE CURRENT
$ 96.3M $ 71.5M $ 25.1M $ 18.1M $ 12.1M $ 6.0M $ 3.9M $ 6.8M $239.8M
image image image image image image image image image
No Summer 2021 work Updated Substantial Completion Date - January 2020 TBD
New Gym Basement Foundations
New Gym Basement Foundations
Renovated Seely Hall
Third Floor Renovated Hallway
Third Floor Renovated Classroom
Third Floor Renovated Classroom
renovated spaces.
concrete walls will be installed this Fall.
electrical, and HVAC infrastructure rough-in work will begin.
Summer Breaks.
FALL CONSTRUCTION UPDATE
PHASING PLAN - SPRING 2020
PHASING PLAN - SUMMER 2020
FIRST FLOOR PHASING PLAN - SUMMER 2020
FIRST FLOOR PHASING PLAN - SUMMER 2020
UPCOMING PROJECT ACTIVITIES (not construction related)
procurement package.
abatement, and construction.
South Addition
North Addition - Storm Shelter
Centennial High School
CONSTRUCTION PROGRESS PHOTO – STOCKPILE FOR FUTURE FILL
CONSTRUCTION PROGRESS PHOTOS
North Addition - Storm Shelter
2nd Floor Renovated Corridor (painting of wall tile not yet completed)
Centennial High School
CONSTRUCTION PROGRESS PHOTO – STOCKPILE FOR FUTURE FILL
Scaffold structure built inside existing pool New interior partitions
CONSTRUCTION PROGRESS PHOTOS
Renovated Gym
FALL CONSTRUCTION UPDATE
renovated spaces.
Precast concrete walls will continue at both additions.
and HVAC infrastructure rough-in work will begin.
work over Winter Break.
FIRST FLOOR PHASING PLAN - SPRING 2020
SECOND FLOOR PHASING PLAN - SPRING 2020
FIRST FLOOR PHASING PLAN - SUMMER 2020
SECOND FLOOR PHASING PLAN - SUMMER 2020
UPCOMING PROJECT ACTIVITIES (not construction related)
procurement package.
abatement, and construction.
PHASING PLAN - SUMMER 2020
PHASING PLAN - SUMMER 2020
PHASING PLAN - SUMMER 2020
UPCOMING PROJECT ACTIVITIES
○ Community Meeting - September 18, 2019 ○ Design Development Approval - October 15, 2019 Board Meeting
○ Early 2020 ○ May have package in late 2019
○ June 2020 - August 2021 ○ Hazardous Material abatement may occur earlier
Updated 4/9/2019
Exterior Site View from James St.
Exterior Site View from New Entrance on University Ave.
Metal Framing
Updated 4/9/2019
Elevator Pit
Updated 4/9/2019
Interior Site Views
image image image image image image image image image
FALL CONSTRUCTION UPDATE
Updated 5/13/2019 9
○ Target date for weather-tight building is end of November
image image image image image image image image image
UPCOMING PROJECT ACTIVITIES (not construction related)
Interior Site - Inside New Gym
Interior Site View
Interior Renovated Areas
SUMMER CONSTRUCTION PROGRESS
Interior Renovated Areas
FALL CONSTRUCTION UPDATE
PHASING PLAN - SPRING 2020
PHASING PLAN - SUMMER 2020
UPCOMING PROJECT ACTIVITIES (not construction related)
Spring 2020 renovations in the existing school
View from the new track - facing North
Future McKinley Fieldhouse
View from new track - Facing North-West
View from new track - facing South West
FALL CONSTRUCTION ACTIVITIES
○ Construction of CMU walls, exterior windows and doors ○ Roofing ○ Interior framing and install of MEP systems
UPCOMING PROJECT ACTIVITIES (not construction related)
○ Scoreboard ○ Audio visual equipment ○ Furniture, signage, and equipment for Field House ○ Athletic equipment
establishing new standing Finance Committee. ○ Currently accepting applications for new members
*Current K-5 Enrollment as of August 20, 2019 = 4,951
Source: Cooperative Strategies Development Report, October 2018
*Current M.S. Enrollment as of August 20, 2019 = 2,329
Source: Cooperative Strategies Development Report, October 2018
Total Students:
Increase in growth over two years = 253 students
Location Portable(s) Annual Lease Franklin 3 $40,500 Jefferson 2 $27,000 IPA 1 $13,500 Stratton 1 $13,500 Barkstall 1 $13,250 YAP (@ Columbia) 1 $13,250 Annual Cost $121,000*
*Portables require delivery, install and removal costs. Typically $9K/portable.
○ ~$22M* ○ 82K SF (currently 43K SF) ○ Capacity = 648 students (Adds ~200 seats from current design capacity of 474)
○ ~$42M* ○ 118K SF ○ Capacity = 600 students ○ Assumes built on land adjacent to Barkstall (for estimating purposes) ○ Soccer field, baseball and bleachers *Updated from 2016 with what we know now.
September 10, 2019
Next Meeting - December 2, 2019