MEASURE B
PROGRAM UPDAT E
CITIZENS’ BOND OVERSIGHT COMMITTEE: AUGUST 22, 2017
MEASURE B PROGRAM UPDAT E CITIZENS BOND OVERSIGHT COMMITTEE: AUGUST - - PowerPoint PPT Presentation
MEASURE B PROGRAM UPDAT E CITIZENS BOND OVERSIGHT COMMITTEE: AUGUST 22, 2017 MEASURE B PROGRAM OVERVIEW Facilities Master Plans EXECUTIVE LEVEL SUMMARY Project Recap K03-35718: Performing Arts Project Summary: Small capital repairs.
CITIZENS’ BOND OVERSIGHT COMMITTEE: AUGUST 22, 2017
Project Summary: Small capital repairs. Status:
construction to begin after Memorial Day 2018.
Project Summary: New facility for M&O to replace existing structures, from both campuses, that are in disrepair; Storage facility/metal structure for District storage for surplus property, program storage, etc.; The following programs are also included: Police, Reprographics, Graphic Design, Shipping & Receiving. Status:
design/constructability review to begin
Project Summary: Replace existing natural grass field with synthetic turf fields with associated markings for various sports, restroom facility, addition to existing gym complex for storage or equipment, score boards, tennis courts, multi-purpose turf in PE complex, small capital repairs, perimeter fencing, laundry facilities, and FF&E. Status:
draft report due August 10, design footing and foundations per geohazard report, DSA submittal late August
Project Summary: Demolition of Maintenance Facilities along Kent Avenue, Gardening Shed in Lot 10, and Batting Cages. Status:
announcer’s booth due to migratory birds nesting on the structure.
Project Summary: New prefabricated, DSA pre-approved building for classroom and demonstrations for organic farm & associated programs. Status:
This project will be rebid in the late fall/winter.
scheduled for week of 9/18/17
Project Summary: Multi-purpose facility to seat at least 275-300 for seated dinner, commercial kitchen, stage, and Jonas Center staging, etc. Status:
Project Summary: Buildings 1-7, Envelope improvements, windows replacement, mechanical repairs, flooring, painting, small capital repairs. Status:
Project Summary: Buildings 8-12, Envelope improvements, roofing replacement, windows replacement, mechanical repairs, flooring, painting, small capital repairs. Status:
August 18, 2017
Project Summary: Buildings 13-16, All-new center for wellness, recreation, aquatics, athletics and kinesiology, designed for students and community access; The new Miwok Center will include a new gymnasium, Olympic size pool, warmup lap pool, and wellness center. Status:
Project Summary: To build outdoor amphitheater to seat 250 guests with outdoor stage, sound system, accessibility to existing sidewalks and pathway to existing parking lots. Status:
Outdoor Water Use Applications July 17, 2017
Project Summary: Demolition of existing Corp Yard Facility and Buildings 11, 18, 19, 20, 22, 23, and other facilities as needed. Status:
abatement 8/25/17
Highlights:
Phase 1: Exterior Modernization Update exterior with materials that are energy efficient and require less maintenance. Complete Fall 2019 Phase 2: Interior Modernization Update finishes and building systems to current standards and relocate walls to create more classrooms. Complete Fall 2019
COLLEGE OF MARIN - KENTFIELD M&O FACILITY
www.brick-inc.com SITE - AERIAL VIEW 08/01/2017
This image is a conceptual rendering and is not intended to be a final product of design. Final design shall be approved by the Board of Trustees.
COLLEGE OF MARIN - KENTFIELD M&O FACILITY
M+O WEST PERSPECTIVE /01/2017 0808/01/17 www.brick-inc.com
This image is a conceptual rendering and is not intended to be a final product of design. Final design shall be approved by the Board of Trustees.
COLLEGE OF MARIN - KENTFIELD M&O FACILITY
M+O FRONT ENTRY 08/01/2017 www.brick-inc.com
This image is a conceptual rendering and is not intended to be a final product of design. Final design shall be approved by the Board of Trustees.
COLLEGE OF MARIN - KENTFIELD M&O FACILITY
835 College Ave. Kentfield, CA 94904
CAMPUS POLICE ADMIN. BLDG. 08/01/2017 www.brick-inc.com
This image is a conceptual rendering and is not intended to be a final product of design. Final design shall be approved by the Board of Trustees.
COLLEGE OF MARIN - KENTFIELD M&O FACILITY
M+O LOADING DOCK AND SHOPS 08/01/2017 www.brick-inc.com
This image is a conceptual rendering and is not intended to be a final product of design. Final design shall be approved by the Board of Trustees.
COLLEGE OF MARIN - KENTFIELD M&O FACILITY
GROUNDS SHOP AND POLE BARN 08/01/2017 www.brick-inc.com
This image is a conceptual rendering and is not intended to be a final product of design. Final design shall be approved by the Board of Trustees.
This image is a conceptual rendering and is not intended to be a final product of design. Final design shall be approved by the Board of Trustees.
Floor Plan - M&O
This image is a conceptual rendering and is not intended to be a final product of design. Final design shall be approved by the Board of Trustees.
Floor Plan - CAMPUS POLICE/ADMIN. BLDG.
COLLEGE OF MARIN - KENTFIELD M&O FACILITY
www.brick-inc.com SITE - AERIAL VIEW 08/01/2017
This image is a conceptual rendering and is not intended to be a final product of design. Final design shall be approved by the Board of Trustees.
Budget: $32,313,553 Budget Source: Measure B Scope: Study/assessment
space to warrant renovation, demolition, or new construction based on needs, programs, and current code conditions
Budget: $51,395,750 Budget Source: Measure B Scope: Study/assessment
space to warrant renovation, demolition, or new construction based on needs, programs, and current code conditions
Combined Budget: $83,709,303 Initial Programming Thoughts:
Library Bookstore Student Accessibility Services (DSPS) Assessment Outreach Enrollment Services Office of Instructional Management (OIM) Internship Registration Cafeteria Foundation Counseling Student Activities and Advocacy Transfer Center EOPS/CARE & CalWORKs Tutoring and Learning Center Cashiering Veteran Resource Center Learning Communities (Puente, Umoja) Community Education William Keith Room Humiston Room Classrooms Computer Labs Health Services Mail Room Writing Lab Office Space CIS Lab Testing & Assessment Rooms for Student Groups Associated Student Groups Replacement of Village Square 6K Sq.ft.
Board Goals: What does the Board identify as its major goals and expectations for this project? Delivery Method: TBD Major Value Engineering Items: TBD
□ Programming
□ Value Engineering
□ Schematic Design
□ Value Engineering
□ Design Development
□ Value Engineering
□ Construction Documents
□ Value Engineering
Board Reviews Completed
Project Initiation
Board Reviews To Be Done
CITIZENS’ BOND OVERSIGHT COMMITTEE: AUGUST 22, 2017