1 7/1/2016
Implementation of Administrative Order
- n Consent between the Navy and
Red Hill Fuel Storage Facility Status Update for HBWS June 27, 2016 - - PowerPoint PPT Presentation
Red Hill Fuel Storage Facility Status Update for HBWS June 27, 2016 Implementation of Administrative Order on Consent between the Navy and Defense Logistics Agency with Hawaii Department of Health and the US EPA Region 9 7/1/2016 1
1 7/1/2016
2 7/1/2016
3 7/1/2016
4 7/1/2016
5 7/1/2016
6 7/1/2016
www.epa.gov/red-hill
health.hawaii.gov/shwb/ust-red-hill-project-main/
7
8 7/1/2016
Specific Task AOC Deadline Current Status Scoping Meetings (2.1) Start within 30 Days from effective date of AOC Scoping Completed TIRM Procedures Report (2.2) Within 120 days from final scoping meeting Revised Draft Outline for TIRM Procedures Report received from Navy March 23, 2016 Decision Meeting (2.3) Within 60 days of TIRM Procedures Report
9 7/1/2016
10 7/1/2016
Specific Task AOC Deadline Current Status Scoping Meeting (3.1) Start within 30 days from effective date of AOC Scoping Completed Scope of Work (3.2) Within 90 days from final Scoping Meeting Draft SOW Outline submitted Jan 29, 2016 TUA Report (3.3) Within 12 months of SOW Approval
11 7/1/2016
12 7/1/2016
13 7/1/2016
14
15 7/1/2016
16 7/1/2016
17 7/1/2016
18 7/1/2016
19 7/1/2016 Specific Task AOC Deadline Current Status Scoping Meeting for Groundwater Flow and Fate & Transport Model Report (7.1.1, 7.2.1) Within 30 days of effective date of AOC Complete Groundwater Flow and Fate & Transport Model SOW (7.1.2, 7.2.2) Within 90 days of Final Scoping Meeting Submitted May 4, 2016, Agencies’ Approval Pending Groundwater Flow Model Report (7.1.3) Within 24 months of Agencies’ Approval of SOW Fate & Transport Model Report (7.2.3) Within 6 months of Agencies’ Approval
Scoping Meeting for Groundwater Monitoring Well Network (7.3.1) Within 30 days of effective date of AOC Complete Groundwater Monitoring Well Network SOW (7.3.2) Within 90 days of Final Scoping Meeting Submitted May 4, 2016, Agencies’ Approval Pending/ Monitoring Well Installation Workplan submitted April 26, 2016/Agencies’ partial approval on June 17, 2016 Groundwater Monitoring Well Network (7,3.3) Within 12 months of Agencies’ Approval of Groundwater Flow Model Report
20 7/1/2016
Proposed Monitoring Well Location
RedHil UST Stream Topographic Contour (feet above mean sea level) Red Hill Installation Boundary
Notes
earthdata.hbnl (USGS 1.foot orthoimagery)
UST Underground Storage Tank 150 A 300
Figure 2
Feet
600 Proposed Monitoring Well Locations Monitoring Well Installation Work Plan Red Hill Bulk Fuel Storage Facility JBPHH, O'ahu, Hawai'i
21 7/1/2016
22 7/1/2016
23 7/1/2016
24 7/1/2016
25 7/1/2016
26 7/1/2016