public safety building
play

Public Safety Building Construction Contractors Outreach Town Hall - PDF document

Earthquake Safety and Emergency Public Safety Building Construction Contractors Outreach Town Hall d Response Bond B June 30, 2011 R De partment of f Public c Works Public Safety Building MEETING AGENDA MEETING AGENDA Welcome


  1. Earthquake Safety and Emergency Public Safety Building Construction Contractors’ Outreach Town Hall d Response Bond B June 30, 2011 R De partment of f Public c Works

  2. Public Safety Building MEETING AGENDA MEETING AGENDA Welcome Fuad Sweiss Deputy Director Dept of Public Works Fuad Sweiss, Deputy Director, Dept. of Public Works Introduction of Project Charles Higueras, Project Manager, Dept. of Public Works Steve Slosek Project Architect HOK/ Cavagnero Steve Slosek, Project Architect, HOK/ Cavagnero Main Presentation on Upcoming Work, Dates for Bidding Bret Firebaugh, Project Sponsor, Charles Pankow Builders Human Rights Commission and Small Business Participation Selormey, Dzikunu, Contract Compliance Officer, HRC Office of Economic & Workforce Development/ CityBuild Requirements p y q Ken Nim, Workforce Compliance Officer, OEWD/ CityBuild Prevailing Wage Requirements Ardis Graham, Contract Compliance Officer, OLSE , p , Questions & Answers

  3. Public Safety Building INTRODUCTION OF PROJECT INTRODUCTION OF PROJECT • Project Team • Project Team • Building Information • Project and Trade Package Bid Schedule • LBE Goals, Local Hiring, and Prevailing Wage Requirements

  4. Public Safety Building PROJECT TEAM PROJECT TEAM • Charles Higueras FAIA – DPW Project Manager • Charles Higueras, FAIA – DPW Project Manager • Steve Slosek - HOK/ Cavagnero Project Architect • Bret Firebaugh, Charles Pankow Builders, Ltd. • Capt. John Goldberg, SFPD Project Liaison • Capt. John Hanley, SFFD Project Liaison

  5. Public Safety Building SAN FRANCISCO DEPT OF PUBLIC WORKS SAN FRANCISCO DEPT. OF PUBLIC WORKS Charles Higueras FAIA, Project Manager P: 415/ 557- 4646 P: 415/ 557 4646 E: charles.higueras@sfdpw.org Samuel Chui, Project Manager Samuel Chui, Project Manager P: 415/ 558- 4082 E: samuel.chui@sfdpw.org

  6. Public Safety Building BUILDING INFORMATION BUILDING INFORMATION – FUNCTIONAL AREAS & BUDGETS FUNCTIONAL AREAS & BUDGETS PSB Functional Areas: Police Headquarters - 110,000 SF Police Station - 20,000 SF Fire Station - 17,000 SF Shared - 25,000 SF Sh d 25 000 SF Parking Structure - 128,000 SF TOTAL AREA: 300 000 SF TOTAL AREA: 300,000 SF Budgets: Art Enrichment: $3 3M Art Enrichment: $3.3M Construction Cost: $164M

  7. Public Safety Building BUILDING INFORMATION BUILDING INFORMATION - CHARACTERISTICS CHARACTERISTICS Safety: Controlled Access & Security S f t C t ll d A & S it Sustainability: LEED Gold - Integrated Hi- Perf./ Low Maint. Civic: Mission Bay Development Standards, Historic Building y p , g Rehabilitation Standards Essential Seismic Safety: 50% increase in structural strength 96 Hours Resiliency: 96 Hours Resiliency: • Emergency Generator capacity to provide for key operational areas of Police Head Quarter, Police and Fire Stations • Fire Water Storage S g • Potable Water • Sewage Storage • Surface Discharge of Storm Water

  8. Public Safety Building EXECUTIVE ARCHITECT EXECUTIVE ARCHITECT HOK/ Cavagnero contacts: HOK/ Cavagnero contacts: Laura Blake AIA, Project Manager P: 415/ 252- 2539 E: laura@cavagnero com E: laura@cavagnero.com Steve Slosek, Project Architect P: 415/ 356- 8581 P: 415/ 356- 8581 E: steve.slosek@hok.com

  9. Public Safety Building SITE PLAN SITE PLAN

  10. Public Safety Building TYPICAL TOWER PLAN (FLOORS 3- 6) TYPICAL TOWER PLAN (FLOORS 3 6)

  11. Public Safety Building COURTYARD AND ROOF PLAN COURTYARD AND ROOF PLAN

  12. Public Safety Building MISSION ROCK STREET MISSION ROCK STREET

  13. Public Safety Building THIRD STREET THIRD STREET

  14. Public Safety Building CHINA BASIN CHINA BASIN

  15. Public Safety Building PUBLIC ENTRY ON THIRD STREET PUBLIC ENTRY ON THIRD STREET

  16. Public Safety Building SOUTH PLAZA ON CHINA BASIN STREET SOUTH PLAZA ON CHINA BASIN STREET

  17. Public Safety Building CHARLES PANKOW BUILDERS LTD CHARLES PANKOW BUILDERS, LTD. Charles Pankow Builders, Ltd. Contact: Bret Firebaugh, DBIA, LEED AP - Project Sponsor P: 510- 379- 1509 E: bfirebaugh@pankow.com

  18. Public Safety Building CONSTRUCTION MANGER/ GENERAL CONTRACTOR - CM/ GC CONSTRUCTION MANGER/ GENERAL CONTRACTOR CM/ GC Role: Role: Selected through a competitive process and awarded contract September 2009 September 2009 Construction Manager • Constructability • Prequalification • Procurement G General Contractor l C • Construction

  19. Public Safety Building CONSTRUCTION MANGER/ GENERAL CONTRACTOR CONSTRUCTION MANGER/ GENERAL CONTRACTOR - CM/ GC CM/ GC Project Schedule Design 7/ 2010 – 8/ 2012 Site Work, Shoring, Exc. 11/ 2011 – 4/ 2012 Cons. Start 11/2011 Foundation/ Structure 4/ 2012 – 3/ 2013 Exterior Skin 9/ 2012 – 11/ 2013 / / Interiors 12/ 2012 – 11/ 2013 Commissioning 8/ 2013 – 2/ 2014 Cons. Comp 2/2014 19

  20. Public Safety Building PROJECT STATUS/ OPPORTUNITIES PROJECT STATUS/ OPPORTUNITIES Current Current • Design Development Phase completing • Test pile program under development • Site investigation and staging development Upcoming • • Vacate and secure site Vacate and secure site • Site utility investigation • Alternative pile testing • RFQ’s for piles, shoring Future • • Trade package bid schedule Trade package bid schedule – by CM/ GC by CM/ GC

  21. Public Safety Building TRADE PACKAGE BID SCHEDULE TRADE PACKAGE BID SCHEDULE Group # RFQ Start RFP Start Dollar Amount Potholing May 2011 May 2011 $40k 1 Fencing Shoring May 2011 J uly 2011 $2M 2 Surveying Alternative Pile Testing J une 2011 J uly 2011 $100k 3 Dewatering Curtain Wall/ Glazing Curtain Wall/ Glazing J J une2011 une2011 J J uly 2011 uly 2011 $23M $23M 4 4 Site Security System Construction Trailers Clear & Grub, Excavation J uly 2011 Sept. 2011 $4M 5 Window Washing Equipment Construction Site Signage Site Utilities – Safe Off Temp Electric/ water/ U.G. Electric p Fire Sprinkler DB Oct. 2011 Dec. 2011 $6M 6 Piles

  22. Public Safety Building TRADE PACKAGE BID SCHEDULE (CONTINUED) TRADE PACKAGE BID SCHEDULE (CONTINUED) Group # RFQ Start RFP Start Dollar Amount 7 Waterproofing Dec. 2011 J an. 2012 $29M Below Grade MEP Concrete Rebar Rebar Structural Steel Manhoist Elevator Fire Proofing Mar. 2012 April 2012 $13M 8 Framing / Drywall Misc. Metals/ Stairs Roofing Sheet Metal g

  23. Public Safety Building TRADE PACKAGE BID SCHEDULE (CONTINUED) TRADE PACKAGE BID SCHEDULE (CONTINUED) Group # RFQ Start RFP Start Dollar Amount 9 Tile J une 2012 Aug. 2012 $49M Flooring Millwork DF&H DF&H Window Coverings Access Floors Acoustical Ceilings H Hardscape d Asphalt Paving Painting Final Clean Fire Station #30 Fi S i #30 MEP Site Barriers Toilet Partitions and Accessories Signage

  24. Public Safety Building PROJECT STATUS/ OPPORTUNITIES PROJECT STATUS/ OPPORTUNITIES Bidding Process iddi Bidder Outreach Advertise Lists RFQ Distribute Distribute Analyze/ Short List Analyze/ Short List RFP Distribute Analyze/ Award 24

  25. Public Safety Building PREQUALIFICATION PROCESS PREQUALIFICATION PROCESS • Licensing Licensing • Bonding • Insurance Insurance • Environmental Matters • Disputes, Arbitration, Litigation & Claims p g • Financial Information • Safety • Prevailing Wage & Apprentice Compliance • LBE/ Local Hiring

  26. Public Safety Building HUMAN RIGHTS COMMISSION (HRC) HUMAN RIGHTS COMMISSION (HRC) Chapter 14B: Local Business Enterprise and Non- Discrimination p p Ordinance Requirements Selormey Dzikunu, Contract Compliance Officer P: 415/ 558 4059 P: 415/ 558- 4059 E: selormey.dzikunu@sfgov.org

  27. Public Safety Building HUMAN RIGHTS COMMISSION (HRC) HUMAN RIGHTS COMMISSION (HRC) LBE Subcontracting Requirements • The requirements of Chapter 14B (“LBE Ordinance”) shall apply. • Prime must comply with Chapter 14B and their implementing Rules and Regulations. • The Overall LBE Subcontracting goal: h ll b l • 10% of the total value of the entire contract. • LBE goal must be met by the cumulative participation by LBEs in the two phases for this project: • (1) the Pre- Construction Services phase (1) h P C i S i h • (2) the Construction Phase. •Prime will work with HRC on procurement plan to meet/ exceed the requisite LBE subcontracting goal. q g g •Trade Package LBE Subcontractor/ Subconsultant Participation Goal

  28. Public Safety Building OFFICE OF ECONOMIC AND WORKFORCE DEVELOPMENT (OEWD) OFFICE OF ECONOMIC AND WORKFORCE DEVELOPMENT (OEWD) San Francisco Local Hiring Policy for Construction y Ken Nim, Workforce Compliance Officer, CityBuild P: 415/ 581- 2303 E: ken.nim@sfgov.org E: ken.nim@sfgov.org

  29. Public Safety Building OFFICE OF ECONOMIC AND WORKFORCE DEVELOPMENT (OEWD) OFFICE OF ECONOMIC AND WORKFORCE DEVELOPMENT (OEWD) Summary of Local Hiring Policy y g y • Covering All Construction Public Works or Improvement Projects with Engineer Estimate in excess of $400k • Effective for Construction Bids First Advertised on or after Eff i f C i Bid Fi Ad i d f March 25, 2011 • Work Hours by Trade Performed by San Francisco residents with 10% f from Disadvantaged Workers Di d t d W k

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend