Project Update High School Additions & Remodeling School District of Holmen Holmen, Wisconsin 3.25.19 High School Additions & Remodeling Background Fall 2017 HHS Facility Committee met to determine need and shared with B & G


slide-1
SLIDE 1

High School Additions & Remodeling Project Update – High School Additions & Remodeling

School District of Holmen

Holmen, Wisconsin 3.25.19

slide-2
SLIDE 2

High School Additions & Remodeling

Background

Fall 2017 HHS Facility Committee met to determine need and shared with B & G July 2018 *Model 1.5 and 2.0 shared at July 9 Board Meeting *Model 1.75 shared at July 23 Board Meeting August 2018 Resolutions for Referendum approved at Board Meeting August 13 November 2018 Referendum passed Question #1 Shall the School District of Holmen, La Crosse County, Wisconsin be authorized to issue pursuant to Chapter 67 of the Wisconsin Statutes, general

  • bligation bonds in an amount not to

exceed $23,500,000 for the public purpose of paying the cost of an improvement project to the current Holmen High School building consisting

  • f: constructing, furnishing and equipping

additions for the fine arts center, gymnasium and related space, career technology education, music and other areas; remodeling, renovating and equipping the commons, kitchen, instructional and other space; and site improvements?

slide-3
SLIDE 3

High School Additions & Remodeling

Background

slide-4
SLIDE 4

High School Additions & Remodeling

Process

.

Design Development Construction Documents (plans, specifications) Bid Construction Schematic Design High School Design Team 1.4.19 1.9.19 2.12.19 3.13.19 Executive Design Team 12.19.18 1.17.19 2.14.19 3.14.19 3.18.19 3.20.19

slide-5
SLIDE 5

High School Additions & Remodeling

Design

Referendum Concept Diagram

slide-6
SLIDE 6

High School Additions & Remodeling

Design

Schematic Design Concept Diagram

slide-7
SLIDE 7

High School Additions & Remodeling

Design

Schematic Design Site Diagram

slide-8
SLIDE 8

High School Additions & Remodeling

Design

Schematic Design Concept Diagram

slide-9
SLIDE 9

High School Additions & Remodeling

Design

West Segment Concept Diagram

slide-10
SLIDE 10

High School Additions & Remodeling

Design

Middle Segment Concept Diagram

slide-11
SLIDE 11

High School Additions & Remodeling

Design

East Segment Concept Diagram

slide-12
SLIDE 12

High School Additions & Remodeling

Design

Aerial View from West Concept

slide-13
SLIDE 13

High School Additions & Remodeling

Design

Aerial View from North Concept

slide-14
SLIDE 14

High School Additions & Remodeling

Design

View from West of Athletic Entrance

slide-15
SLIDE 15

High School Additions & Remodeling

Design

View from North of Fine Arts Center Entrance

slide-16
SLIDE 16

High School Additions & Remodeling

Budget

  • Estimated cost
  • Cost more or less
  • Referendum $23,500,000, within budget.

REFERENDUM 2.25.19

slide-17
SLIDE 17

High School Additions & Remodeling

Timeline

slide-18
SLIDE 18

High School Additions & Remodeling

Timeline

Dec 2018/Jan 2019 Schematic Design - Addition Jan/Feb/March 2019: Design Development - Addition April/May/ June 2019: Development of Construction Documents (plans/ specifications) July 2019: Bidding Documents Released August 2019: Board Approve Bid

August 2019: Start Schematic/ Design Development

  • Remodel

August 2019: Project Begins August 2020: Projected Project Completion July 2019: State Approval