Honeoye Falls-Lima Central School District 2016 Additions and Alterations Phase 2 Project Update June 2020 2016 Additions and Alterations Phase 2 Referendum Value $29,986,084 Incidental Budget $ 4,632,681 Construction Contingency $
2016 Additions and Alterations Phase 2
Referendum Value $29,986,084 Incidental Budget $ 4,632,681 Construction Contingency $ 1,564,311 Contracts Awarded $22,848,873 State Contract $ 940,219
Construction Contingency Budget Update
- Construction Contingency Budget
$1,564,311
- Additional Co-Op Purchases
$ 195,594
- Additional Credit
$ 63,092
- Approved Change Orders
$1,404,734
- Remaining Construction Contingency
$ 35,571
- Construction Project is 94% Complete
- Contingency Budget is 98% spent
- Contract allowance approved totals $11,074
- Project Team is following approximately $84,500 in pending issues.
Financial Overview
- Voter Authorization
$29,986,084
- Contracts Issued at Bid
$23,789,092
- Authorized Change Orders
$ 1,404,734
- Pending Change Orders
$ 84,500
- District Purchase Orders
$ 132,502
- Incidental Budget
$ 4,297,109
- Incidental Purchases and Credits
$ 15,039
- Total Remaining Project Funds
$ 263,108
2016 Additions and Alterations Phase 2 Project Status/Schedule Update
Manor Intermediate
- Concrete risers in the Music Room have
been poured.
- MEP finishes are complete, and
casework has been installed in the Music Room.
- The serving line in the Kitchen has been
- removed. The bearing wall separating the
Kitchen from the Cafeteria has been temporarily shored and the opening for the new overhead door has been demo’d. Senior High School
- Lobby benches have been installed.
- The sliding glass door dividing the Kitchen
and Cafeteria has been installed.
- Start-up’s and training for the Food Service
equipment are complete.
- In the Robotics Lab, the casework and
countertops have been installed.
- In the IT Suite, MEP rough-in’s are complete
and framing is underway.
- At the Main Entrance, the concrete sidewalks
are nearly complete, the parking lot has received base, binder, and top. The Cougar wall has been painted and the illuminated sign has been installed.
2016 Additions and Alterations Phase 2 Project Status/Schedule Update
Lima Intermediate
- The casework for the Main
Office has been fabricated and
- delivered. The installation is
underway.
- Framing in Classroom 105, the
Discovery Lab, and the Nurses Suite is underway.
- The elevator has been inspected
and is fully operational. Transportation Building
- In the last phase, the structural steel has
been erected, the MEP rough-in’s are
- ngoing, the walls have been framed, and
the gyp. board is being installed.
- The new doors and hardware are being
installed throughout.
- The new overhead door in the key shop
has been installed.
2016 Additions and Alterations Phase 2 What to expect in the upcoming Month
Manor Intermediate
- Music Room will be complete and
turned over to the District.
- The new serving line will be installed
in the Kitchen and the connections for the MEP’s will be made.
- The Structural steel and overhead
door for the new opening between the Kitchen and Cafeteria will be installed.
- Wall and floor tile will be installed
where needed in the Cafeteria. Transportation Building
- In the last phase, the walls will be
finished and painted, the floor will be mitigated and leveled, and new VCT will be installed. MEP finishes will be ongoing.
- Casework will be delivered and installed
throughout.
- Door and hardware installation will
continue throughout.
2016 Additions and Alterations Phase 2 What to expect in the upcoming Month
Senior High School
- The fabrication of the movable furniture
for the Robotics lab will be ongoing.
- Doors and hardware will be installed
throughout.
- Framing will be completed in the IT
Suite, the walls will be boarded, casework will be fabricated, and MEP finishes will be ongoing.
- Parking lot will be striped, and the
remainder of the concrete sidewalks will be poured.
- Demo will begin in Central Kitchen.
Lima Elementary
- Casework for the Main Office will be
installed.
- The floors in Classroom 105, the
Discovery, and the Nurses Suite will be leveled, the walls will be finished, and MEP finishes will be ongoing.
- The fabrication of the new transaction
window in the Main Office will be ongoing.