honeoye falls lima central school district
play

Honeoye Falls-Lima Central School District 2016 Additions and - PowerPoint PPT Presentation

Honeoye Falls-Lima Central School District 2016 Additions and Alterations Phase 2 Project Update March 2020 2016 Additions and Alterations Phase 2 Referendum Value $29,986,084 Incidental Budget $ 4,632,681 Construction Contingency $


  1. Honeoye Falls-Lima Central School District 2016 Additions and Alterations Phase 2 Project Update March 2020

  2. 2016 Additions and Alterations Phase 2 Referendum Value $29,986,084 Incidental Budget $ 4,632,681 Construction Contingency $ 1,564,311 Contracts Awarded $22,848,873 State Contract $ 940,219

  3. Construction Contingency Budget Update • Construction Contingency Budget $1,564,311 • Additional Co-Op Purchases $ 187,098 • Additional Credit $ 63,092 • Approved Change Orders $1,098,108 • Remaining Construction Contingency $ 342,197 • Construction Project is 76% Complete • Contingency Budget is 78% spent • Contract allowance approved totals $0 • Project Team is following approximately $267,739 in pending issues.

  4. 2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate Senior High School • Rooms 303 and 305 have been • The Display Cases have been installed in the completed and turned over to the Lobby. District. • Wall tile and floor tile have been installed in • Construction in the Music Room has the Kitchen and Cafeteria. begun. • Ceiling grid is installed throughout the Cafeteria and Kitchen and ceiling tile is being Transportation Building dropped. • Concrete for the Mezzanine has been poured. • The Cougar Mural has been installed in the stairwell adjacent to the Cafeteria. • Overhead plumbing, ductwork and electrical conduit are ongoing. • Demolition has begun in the Robotics Lab. • Masonry block work is ongoing. • Demo of B&G has begun.

  5. 2016 Additions and Alterations Phase 2 Project Status/Schedule Update Lima Intermediate Middle School • The Main Office has undergone • The building has been switched over to the demolition, framing has begun and new Day Automation platform. MEP rough-ins are ongoing. • Rooms 107, 108, 109 and 110 have been abated and new flooring is going in.

  6. 2016 Additions and Alterations Phase 2 What to expect in the upcoming Month Manor Intermediate Senior High School • Heavy demo will continue in the • The Cafeteria will be turned over to the Music Room. District. Lima Elementary • Construction will continue in the Kitchen Area. • Construction in the Main Office will continue. • The Faculty Lounge will be completed and turned over to the District. Transportation Building • Construction in the Robotics Lab will continue. • Masonry work, drywall, floor leveling and MEP rough-ins will all continue. • Parking lot work and concrete sidewalks will continue.

  7. Honeoye Falls-Lima Central School District 2016 Additions and Alterations Phase 2 Progress Photos

  8. New Mezzanine – Transportation Center

  9. New Mezzanine – Transportation Center

  10. Office Space – Transportation Center

  11. Temporary Wall in Manor Cafeteria

  12. New Music Room - Manor

  13. New Music Room - Manor

  14. Cafeteria – High School

  15. Cafeteria – High School

  16. Cafeteria – High School Kitchen

  17. Flexible Learning Lab – High School

  18. Flexible Learning Lab – High School

  19. Robotics Lab – High School

  20. Main Entrance Lobby – High School

  21. Main Entrance Lobby – High School

  22. Main Entrance Lobby – High School

  23. B&G Building Demolition

  24. B&G Building Demolition

  25. B&G Building Demolition

  26. New Concrete Sidewalks – High School

  27. New Concrete Sidewalks – High School

  28. New Main Office – Lima

  29. Room 107 – Lima

  30. Room 108 – Lima

  31. Room 109 – Lima

  32. Room 110 – Lima

  33. Cougar Mural – High School

  34. Honeoye Falls-Lima Central School District Questions?

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend