Honeoye Falls-Lima Central School District 2016 Additions and Alterations Phase 2 Project Update March 2020 2016 Additions and Alterations Phase 2 Referendum Value $29,986,084 Incidental Budget $ 4,632,681 Construction Contingency $


slide-1
SLIDE 1

Honeoye Falls-Lima Central School District

2016 Additions and Alterations Phase 2 Project Update March 2020

slide-2
SLIDE 2

2016 Additions and Alterations Phase 2

Referendum Value $29,986,084 Incidental Budget $ 4,632,681 Construction Contingency $ 1,564,311 Contracts Awarded $22,848,873 State Contract $ 940,219

slide-3
SLIDE 3

Construction Contingency Budget Update

  • Construction Contingency Budget

$1,564,311

  • Additional Co-Op Purchases

$ 187,098

  • Additional Credit

$ 63,092

  • Approved Change Orders

$1,098,108

  • Remaining Construction Contingency

$ 342,197

  • Construction Project is 76% Complete
  • Contingency Budget is 78% spent
  • Contract allowance approved totals $0
  • Project Team is following approximately $267,739 in pending issues.
slide-4
SLIDE 4

2016 Additions and Alterations Phase 2 Project Status/Schedule Update

Manor Intermediate

  • Rooms 303 and 305 have been

completed and turned over to the District.

  • Construction in the Music Room has

begun. Transportation Building

  • Concrete for the Mezzanine has

been poured.

  • Overhead plumbing, ductwork and

electrical conduit are ongoing.

  • Masonry block work is ongoing.

Senior High School

  • The Display Cases have been installed in the

Lobby.

  • Wall tile and floor tile have been installed in

the Kitchen and Cafeteria.

  • Ceiling grid is installed throughout the

Cafeteria and Kitchen and ceiling tile is being dropped.

  • The Cougar Mural has been installed in the

stairwell adjacent to the Cafeteria.

  • Demolition has begun in the Robotics Lab.
  • Demo of B&G has begun.
slide-5
SLIDE 5

2016 Additions and Alterations Phase 2 Project Status/Schedule Update

Lima Intermediate

  • The Main Office has undergone

demolition, framing has begun and MEP rough-ins are ongoing.

  • Rooms 107, 108, 109 and 110 have

been abated and new flooring is going in. Middle School

  • The building has been switched over to the

new Day Automation platform.

slide-6
SLIDE 6

2016 Additions and Alterations Phase 2 What to expect in the upcoming Month

Manor Intermediate

  • Heavy demo will continue in the

Music Room. Senior High School

  • The Cafeteria will be turned over to the

District.

  • Construction will continue in the Kitchen

Area.

  • The Faculty Lounge will be completed

and turned over to the District.

  • Construction in the Robotics Lab will

continue.

  • Parking lot work and concrete sidewalks

will continue. Lima Elementary

  • Construction in the Main Office will

continue. Transportation Building

  • Masonry work, drywall, floor leveling

and MEP rough-ins will all continue.

slide-7
SLIDE 7

Honeoye Falls-Lima Central School District

2016 Additions and Alterations Phase 2 Progress Photos

slide-8
SLIDE 8

New Mezzanine – Transportation Center

slide-9
SLIDE 9

New Mezzanine – Transportation Center

slide-10
SLIDE 10

Office Space – Transportation Center

slide-11
SLIDE 11

Temporary Wall in Manor Cafeteria

slide-12
SLIDE 12

New Music Room - Manor

slide-13
SLIDE 13

New Music Room - Manor

slide-14
SLIDE 14

Cafeteria – High School

slide-15
SLIDE 15

Cafeteria – High School

slide-16
SLIDE 16

Cafeteria – High School Kitchen

slide-17
SLIDE 17

Flexible Learning Lab – High School

slide-18
SLIDE 18

Flexible Learning Lab – High School

slide-19
SLIDE 19

Robotics Lab – High School

slide-20
SLIDE 20

Main Entrance Lobby – High School

slide-21
SLIDE 21

Main Entrance Lobby – High School

slide-22
SLIDE 22

Main Entrance Lobby – High School

slide-23
SLIDE 23

B&G Building Demolition

slide-24
SLIDE 24

B&G Building Demolition

slide-25
SLIDE 25

B&G Building Demolition

slide-26
SLIDE 26

New Concrete Sidewalks – High School

slide-27
SLIDE 27

New Concrete Sidewalks – High School

slide-28
SLIDE 28

New Main Office – Lima

slide-29
SLIDE 29

Room 107 – Lima

slide-30
SLIDE 30

Room 108 – Lima

slide-31
SLIDE 31

Room 109 – Lima

slide-32
SLIDE 32

Room 110 – Lima

slide-33
SLIDE 33

Cougar Mural – High School

slide-34
SLIDE 34

Honeoye Falls-Lima Central School District

Questions?