Honeoye Falls-Lima Central School District 2016 Additions and Alterations Phase 2 Project Update December 2018 2016 Additions and Alterations Phase 2 Referendum Value $29,986,084 Incidental Budget $ 4,632,681 Construction Contingency $


  1. Honeoye Falls-Lima Central School District 2016 Additions and Alterations Phase 2 Project Update December 2018

  2. 2016 Additions and Alterations Phase 2 Referendum Value $29,986,084 Incidental Budget $ 4,632,681 Construction Contingency $ 1,564,311 Contracts Awarded $22,848,873 State Contract $ 940,219

  3. Construction Contingency Budget Update • Construction Contingency Budget $1,564,311 • There are no approved Change Orders at this time • Contingency Budget is 0% spent • Contract allowance approved totals $0 • Project Team is following approximately $213,700 in pending issues

  4. 2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate (Rooms 207, 209, Senior High School 211 and 213) • Excavation along with foundation work for the • Temporary wall has been installed. Main Entrance is underway. • The plumbing fixtures have been • Abatement and Demo of the Art Room and disconnected and removed. New Nurses Office started over Christmas Break and continues. • Demolition and abatement are Papermill Storage complete. • The concrete flooring inside of the South Storage Building has been installed. Transportation Building • Bearing plates for structural steel have been installed. • Structural steel has been ordered. .

  5. 2016 Additions and Alterations Phase 2 What to expect in the upcoming Month Manor Intermediate (Room 207, 209, Senior High School 211 and 213) • Foundation work for the Main Entrance • Construction in Manor will continue is scheduled to be completed by mid with the installation of case work, wire January. Once complete the building pad molding, flooring, paint and finishes. will be backfilled with stone and compacted. Transportation Building • Structural steel is to be delivered and • Construction in the Art Room and New installation is to begin. Nurses Office will continue throughout the month of January.

  6. Honeoye Falls-Lima Central School District 2016 Additions and Alterations Phase 2 Progress Photos

  7. Concrete prep – Papermill

  8. Installed Concrete – Papermill

  9. Demo/Abatement – High School Art Room

  10. Demo – High School Art Room

  11. Demo – New High School Nurses Office

  12. Demo – New High School Nurses Office

  13. Foundation Work – High School Main Entrance

  14. Foundation Work – High School Main Entrance

  15. Foundation Work – High School Main Entrance

  16. Forming Foundation Walls – High School Main Entrance

  17. Foundation Work – High School Main Entrance

  18. Mastic to be Abated – High School

  19. Demo – Manor Intermediate

  20. Demo – Manor Intermediate

  21. Mastic Abatement – Manor Intermediate

  22. Abatement – Manor Intermediate

  23. Honeoye Falls-Lima Central School District Questions?

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.