Honeoye Falls-Lima Central School District 2016 Additions and Alterations Phase 2 Project Update December 2018 2016 Additions and Alterations Phase 2 Referendum Value $29,986,084 Incidental Budget $ 4,632,681 Construction Contingency $
2016 Additions and Alterations Phase 2
Referendum Value $29,986,084 Incidental Budget $ 4,632,681 Construction Contingency $ 1,564,311 Contracts Awarded $22,848,873 State Contract $ 940,219
Construction Contingency Budget Update
- Construction Contingency Budget
$1,564,311
- There are no approved Change Orders at this time
- Contingency Budget is 0% spent
- Contract allowance approved totals $0
- Project Team is following approximately $213,700 in pending issues
2016 Additions and Alterations Phase 2 Project Status/Schedule Update
Manor Intermediate (Rooms 207, 209, 211 and 213)
- Temporary wall has been installed.
- The plumbing fixtures have been
disconnected and removed.
- Demolition and abatement are
complete. Transportation Building
- Bearing plates for structural steel
have been installed.
- Structural steel has been ordered.
. Senior High School
- Excavation along with foundation work for the
Main Entrance is underway.
- Abatement and Demo of the Art Room and
New Nurses Office started over Christmas Break and continues. Papermill Storage
- The concrete flooring inside of the South
Storage Building has been installed.
2016 Additions and Alterations Phase 2 What to expect in the upcoming Month
Manor Intermediate (Room 207, 209, 211 and 213)
- Construction in Manor will continue
with the installation of case work, wire molding, flooring, paint and finishes. Transportation Building
- Structural steel is to be delivered and
installation is to begin. Senior High School
- Foundation work for the Main Entrance
is scheduled to be completed by mid
- January. Once complete the building pad
will be backfilled with stone and compacted.
- Construction in the Art Room and New
Nurses Office will continue throughout the month of January.