PROJECT OJECT UP UPDA DATE TE Ca Calexic xico o West La - - PowerPoint PPT Presentation

project oject up upda date te
SMART_READER_LITE
LIVE PREVIEW

PROJECT OJECT UP UPDA DATE TE Ca Calexic xico o West La - - PowerPoint PPT Presentation

PROJECT OJECT UP UPDA DATE TE Ca Calexic xico o West La Land nd Port of En Entry y Ex Expansion ansion and Reco confi nfigur gurat ation ion U.S. Genera neral Serv rvice ices s Admini minist strat ation ion March 16,


slide-1
SLIDE 1

PROJECT OJECT UP UPDA DATE TE Ca Calexic xico

  • West La

Land nd Port of En Entry y Ex Expansion ansion and Reco confi nfigur gurat ation ion

U.S. Genera neral Serv rvice ices s Admini minist strat ation ion

March 16, 2017

slide-2
SLIDE 2

Exi xisti sting ng Calexi xico co LPO POE SI SITE

Aerial view of existing site as of September 2015

slide-3
SLIDE 3

Calexi xico co LPO POE (Ph Phase se 1 & 2 & 2)

Phase 1: 10 NB POV lanes w/ primary & secondary canopies, new headhouse, 5 SB POV lanes October 2015 – March 2018 Phase 2: Demo exist Port building, build temp ped processing facility, new ped building, new admin building, 6 additional NB POV lanes, SB POV w/ canopies & booths October 2017 – October 2020

slide-4
SLIDE 4

Calexi xico co LPO POE FLY-OV OVER ER (Ph Phase se 1 & 2) & 2)

slide-5
SLIDE 5

Nor

  • rthbo

bound nd PO POV V / / Admin Building ing

5

Looking north – approach from Mexico

slide-6
SLIDE 6

Pre Pre-Pr Primary ry Canop

  • py

6

Looking north – pre primary canopy and primary canopy beyond

slide-7
SLIDE 7

Pe Pedest stri rian an Pa Pavilio ion Entra rance nce

7

Looking north – approach (pedestrian) from Mexico

slide-8
SLIDE 8

Pe Pedest stri rian an Pa Pavilio ion fro rom 1st

st St.

8

Looking west – pedestrians exiting to 1st St.

slide-9
SLIDE 9

Ph Phase se 1 C Con

  • nst

stru ructio ction n Pr Prog

  • gre

ress ss

Aerial View as of January 24, 2017

slide-10
SLIDE 10

10

Ph Phase se 1 Con

  • nst

stru ructio ction n Pr Prog

  • gre

ress ss

Looking north – Shell Space structure

slide-11
SLIDE 11

11

Ph Phase se 1 Con

  • nst

stru ructio ction n Pr Prog

  • gre

ress ss

Looking south – concrete pour of Shell Space slab

slide-12
SLIDE 12

12

Ph Phase se 1 Con

  • nst

stru ructio ction n Pr Prog

  • gre

ress ss

Looking north – concrete pour of Northbound POV lanes

slide-13
SLIDE 13

13

Ph Phase se 1 C Con

  • nst

stru ructio ction n Pr Prog

  • gre

ress ss

Looking north – northbound POV inspection

slide-14
SLIDE 14

14

Ph Phase se 1 C Con

  • nst

stru ructio ction n Pr Prog

  • gre

ress ss

Looking north – new Headhouse

slide-15
SLIDE 15

15

Ph Phase se 1 C Con

  • nst

stru ructio ction n Pr Prog

  • gre

ress ss

Looking south towards Mexico – Southbound POV across new bridge

slide-16
SLIDE 16

16

Ph Phase se 1 C Con

  • nst

stru ructio ction n Pr Prog

  • gre

ress ss

60” Storm Drain Line Installation

slide-17
SLIDE 17

Upc pcom

  • ming

g Activitie ities

Sewer line work across 2nd St (off hours) March-April 2017 2nd St sidewalk June –Aug 2017 Cesar Chavez/2nd St. traffic signal (City) July 2017 (estimated) Temp ped processing facility & Demolition of existing Port building Oct 2017 - March 2018 Phase 1 completion resulting in closure of existing Northbound / Southbound POV lanes March 2018

slide-18
SLIDE 18

Calexi xico co LPO POE Temp p Pe Ped Pr Proc

  • cess

ssing ng

(exp xpected ected complet mpletion

  • n March

arch 2018) 18)

slide-19
SLIDE 19

Calex lexic ico

  • Phase

ase 2

New Temp Ped NB

slide-20
SLIDE 20

Calexi xico co LPO POE Temp p Pe Ped Pr Proc

  • cess

ssing ng

(exp xpected ected complet mpletion

  • n March

arch 2018) 18)

slide-21
SLIDE 21
slide-22
SLIDE 22

Calexi xico co LPO POE Temp p Pe Ped Pr Proc

  • cess

ssing ng

(exp xpected ected complet mpletion

  • n March

arch 2018) 18)

slide-23
SLIDE 23