Project Authorization for North Harbor Surplus Crane Dispositions - - PowerPoint PPT Presentation

project authorization for
SMART_READER_LITE
LIVE PREVIEW

Project Authorization for North Harbor Surplus Crane Dispositions - - PowerPoint PPT Presentation

Item No.: 5C Supp Date of Meeting: June 5, 2018 Project Authorization for North Harbor Surplus Crane Dispositions 5/22/2018 1 Project Authorization North Harbor Surplus Crane Dispositions 1 i 8. z 1 Request project author ation to remove


slide-1
SLIDE 1

Project Authorization for

5/22/2018 1

North Harbor Surplus Crane Dispositions

Item No.: 5C Supp Date of Meeting: June 5, 2018

slide-2
SLIDE 2

Project Authorization North Harbor Surplus Crane Dispositions

5/22/2018 2

26.2 53.7 21.4

Request project author

1i 8.

z1 ation to remove four surplus ship to shore (STS) container cranes from the North Harbor terminals in an amount not to exceed $4,000,000 for work associated with the North Harbor Surplus Crane Dispositions, Master Identification No. U00293.

slide-3
SLIDE 3

Background North Harbor Surplus Crane Dispositions

  • 10 North Harbor Cranes have been Declared Surplus
  • One Crane on Terminal 46 in 2009
  • Three Cranes on Terminal 18 in 2012
  • Six Cranes on Terminal 5 in 2014
  • T-5 Crane disposition to occur in a future action item

5/22/2018 3

slide-4
SLIDE 4

Locations North Harbor Surplus Crane Dispositions

5/22/2018 4

slide-5
SLIDE 5

Project Objectives and Schedule North Harbor Crane Dispositions

  • Objectives
  • Remove four cranes from Terminals 18 & 46
  • Efficiently as possible
  • Adherence to labor to labor jurisdictions
  • Drivers
  • Meets Lease obligation
  • Allows full commercial use of Terminal 46 dock
  • Schedule
  • Four cranes removed by the end of 2018

5/22/2018 5

slide-6
SLIDE 6

Source of Funds North Harbor Surplus Crane Dispositions

  • The current five year capital investment plan includes over $10

million for the removal of ten cranes in the North Harbor

  • The five year forecast anticipated that these costs would be

expensed beginning in 2019

  • Based on the current 2018 financial forecast, it is recommended

that the three cranes at Terminal 18 and possibly the crane at Terminal 46 be removed in 2018

  • The estimated cost for the removal is not to exceed $4,000,000

5/22/2018 6

slide-7
SLIDE 7

Conclusion North Harbor Surplus Crane Dispositions

Request project authorization in an amount not to exceed $4,000,000 for work associated with the North Harbor Surplus Crane Dispositions, Master Identification No. U00293

5/22/2018 7