Post Auth riz ti n Authorization Changes F b February 2, 2011 2 - - PowerPoint PPT Presentation
Post Auth riz ti n Authorization Changes F b February 2, 2011 2 - - PowerPoint PPT Presentation
MATILIJA DAM ECOSYSTEM RESTORATION PROJECT RESTORATION PROJECT Post Auth riz ti n Authorization Changes F b February 2, 2011 2 2011 Common Decision Documents for P Post-Authorization Changes h i i Ch Minor Updates from
Common Decision Documents for P h i i Ch Post-Authorization Changes
Mi U d t f F ibilit R t
- Minor Updates from Feasibility Report
- Economic updates, typically approved by the Corps,
District Commander
- Limited Changes from Feasibility Report
- Within the South Pacific Division (SPD) Commander’s
uth rit authority
- Project Exceeds Maximum Cost Limit
- Requires Congressional reauthorization
Requires Congressional reauthorization
- Significant Changes from Feasibility Report
- Post Authorization Decision Document (PADD)
- Requires SPD or HQ/ASA/Congressional approval
Authority for Changes h d to an authorized project
The discretionary authority to make post-authorization y y p changes without seeking further Congressional authority is restricted to circumstances where the scope, area to be served purpose function or plan of improvement of the served, purpose, function or plan of improvement of the project is not materially altered (within a specified range/scope). Changes in authorized projects may be made without Congressional permission if the changes are required either by engineering necessity or are needed to either by engineering necessity or are needed to accommodate changed economic and/or physical conditions. The approval authority depends on the type and The approval authority depends on the type and magnitude (scope/metrics) of a change….. magnitude (scope/metrics) of a change…..
Approval Authority for Changes
The approval
Reauthorization by Congress
The approval authority is at
- ne of five
Secretary of the Army
- ne of five
levels:
Chief of Engineers Division Commander Division Commander District Commander
Approval Authority of h d the District Commander
Some limited changes may be approved
D m nt ti n f D si n R fin m nts
Some limited changes may be approved by the District Commander:
- Documentation of Design Refinements.
- Minor cost updates and scope changes
associated with design associated with design refinements….i.e., less than 20%.
- Insignificant changes in environmental
i t (t i ll S l t l EA)
Reauthorization by Congress
impacts (typically Supplemental EA).
Secretary of the Army Chief of Engineers Division Commander District Commander
Approval Authority of th Di i i C d the Division Commander
Typical Criteria:
- Within the Chief of Engineer’s delegated
th it
Typical Criteria:
authority:
- Does not require action by Assistant
Secretary of the Army for Civil Works y y (ASA (CW)) or authorization by Congress
- Required Documentation
Generally a Limited Reevaluation Report
Reauthorization by Congress
- Generally, a Limited Reevaluation Report
(LRR)
- NEPA Document is required (Likely EA)
Secretary of the Army Chief of Engineers Division Commander District Commander
Approval Authority by d Corps Headquarters
T i l C it i
Within the Chief of Engineer’s h
Typical Criteria:
g authority Requires coordination with, but no authorization by ASA(CW) u z y ( W) Does not require authorization by Congress Required Documentation
Reauthorization by Congress
Required Documentation
- General Reevaluation Report
(GRR)
Secretary of the Army Chief of Engineers
- NEPA Document (SEIS)
Division Commander District Commander
Approval Authority by h ( ) the ASA(CW)
Change does not require authorization
Typical Criteria:
Change does not require authorization by Congress. Congressional discretion: delegated g g authority to the ASA(CW) ASA(CW) does not delegate the authority to the USACE
Reauthorization by Congress
authority to the USACE NEPA Document is required
Secretary of the Army Chief of Engineers Division Commander District Commander
Changes Requiring h b Authorization by Congress
T i l C it i
Addition or deletion of a project purpose.
Typical Criteria:
p j p p Change in local cooperation requirements specifically referenced in authorizing language. Cost increase greater than 20% (Section 902 Limit). g ( ) Significant change in project scope. Required Documentation General Reevaluation Report (GRR)
Reauthorization by Congress
- General Reevaluation Report (GRR)
- NEPA Document (SEIS)
Other?......
Secretary of the Army Chief of Engineers Division Commander District Commander
Fines Disposal Options
Design Phase Decision Tree for Disposal of
Reauthor ization by Congres s Secretary of the Army Chief of Engineers
Sequester Fines
Fines
Division Commander District Commander
Prior Objective: Retain Approval Authority
Sequester Fines
pp y within the 1st Tier
BRDA O ti MODA Options: Upstream (USA) Other? Options:
- BRDA 1-4 (136 Ac)
- BRDA 1-2 only (89 Ac)
- Feas (94 Ac)
- East/West Split (72
Ac)
- MODA East (46 Ac)
Options:
- 2 sites (USA 1&2)
BRDA 1-4 Issues:
- Cost Increase of approx
BRDA 1-2 Issues
- Cost Increase of
Issues:
- Property
Issues:
- Approx 37 Ac of addt’l impacts
- utside of Feas stockpile footprint
(225 Ac Feas vs 262 Ac USA & Stockpiles) Cost Increase of approx $34+ Million over Feas Cost Increase of approx $20+ Million over Feas p y Owner/Community Concerns
- Cost Increase of approx
$14+ Million over Feas
- Concerns regarding concept
design: little/no erosion potential
- Cost Increase of approx
$15+Million over Feas
Fines Disposal Options
Design Phase Fines Disposal: Cost &
Sequester Fines Natural Transport of
Schedule Impacts
BRDA Other Sites Upstream
- f BRDA
Transport of Fines Upstream of Downstream of H 150 Sites 1-4:
- Supplemental EA
Sites 1-2:
- Supplemental
EA
- At minimum,
Supplemental EA / Robles
- Likely requires EIS
due to change in water Hwy 150
- Likely requires EIS
- PADD required
- Requires 902
Congressional Reauthorization due to cost increase
- Concurrent action
with ongoing design: 2- EA
- Requires 902
Reauthorization
- 2-3 month
impact for 902
- Costs approx
Supplemental EA / Possible EIS
- Possible PADD
Required
- Assume no
significant change in due to change in water supply impacts
- PADD required
- If significant change in
timeframe for project ecorest benefits,
- If significant change in
timeframe for project ecorest benefits, Congressional Reauthorization likely
- 7-10 year impact due
g g g 3 months impact likely for 902 approval
- Costs approx $150k
Costs approx $150k g g scope or timeframe for ecorest (HEP) benefits
- 6-18 month impact
- Costs approx
$400k $1 2M Congressional Reauthorization likely
- 7-10 year impact due
to PADD (new Feas study) & Congress Reauth 7 10 year impact due to PADD (new Feas study) & Congress Reauth
- Costs approx $5-7M
$400k-$1.2M
- Costs approx $5-7M
First Milestone Second Chief of Engineers Report
Decision Document (PADD) Tasks
Initiate PADD Milestone Review of Tentatively Recommend ed Plan
- Hold Public
Second Milestone Review/ Public Draft
- Detailed
Analysis of
Public Meeting p
- Complete IEPR
- Respond to
comments
- Finalize Report
Documentation C l t Di t i t
Initiate PADD Study
- Prepare PMP
- Review &
Approval
- Negotiate &
Hold Public Workshop
- Analyze Alts,
Env Impacts, Costs, Real Estate Requirements Analysis of Recommende d Plan
- Prepare
Public Draft Report (EIS/EIR)
Meeting
- Respond to
Review Comments/ Finalize
- Complete District
Report
- Transmit to MSC
& Corps HQ
- Prepare for 30-
day Washington-
Reinitiate Design
- Administration
Review g Sign Design Agreement Mod
- 75%/25%
Cost Share Splie Requirements (includes model cert)
- Select
Tentative Plan
- Prepare
Interim Draft (EIS/EIR)
- Initiate
Independent External Peer Review (IEPR)
- Agency
Finalize Public Draft Report
- Complete
additional ATR & Policy Review Level State & Agency Review
- Testify at Civil
Works Review Board
- Initiate
Review
- Record of
Decision
- WRDA
Authorization p
- Approx 6 mo-
1 yr Interim Draft Report
- Agency
Technical Review
- Policy Review
- Agency
Technical Review
- Policy
Review A 1 5 2
- Initiate 45-day
Public Review
- Approx 6-9
mo Washington Level Review
- Prepare Chief Of
Engineer’s Report
- Unknown
Timeframe
- Approx 1.5-2
yrs
- Approx 1.5-2
yrs
- Approx 1 yr
References
- ER 200-2-2: Procedures for Implementing NEPA, March
1988
- ER 1105-2-100: Planning Guidance Notebook, Appendix G
(PAC reports) & Appendix H (Review & Approval of Decision Documents) November 2007 Documents), November 2007
- ER 1165-2-502: Delegation of Review and Approval
Authority for Post-Authorization Decision Documents, March 2007
- ER 1110-2-1150: Engineering and Design for Civil Works
Projects, August 1999 Projects, August 1999
- CESPD-ET-P Memorandum: Guidance for Post-Authorization
Decision Documents, April 1999 ER 1130 2 530 Fl d C t l O ti d M i t
- ER 1130-2-530: Flood Control Operations and Maintenance
Policies , November 1996
Upstream Storage of Fines p g
Slurry Disposal Sites
MODA East MODA West BRDA 1 BRDA 2 BRDA 3 BRDA 4