Work Authorization Documents Work Authorization Document Control - - PDF document

work authorization documents
SMART_READER_LITE
LIVE PREVIEW

Work Authorization Documents Work Authorization Document Control - - PDF document

Work Authorization Documents https://cametoolbox.fnal.gov/Project/WADReports?ProjectName=HL-L... Work Authorization Documents Work Authorization Document Control Account Information Control Account Manager: 10629N Nobrega, Fred Control


slide-1
SLIDE 1

Work Authorization Documents

Work Authorization Document

Control Account Information Control Account Manager: 10629N Nobrega, Fred Control Account Number: 302.2.05 Control Account Description: Coil Fabrication at FNAL Period of Performance Start: 8/1/2016 Finish: 9/29/2023 WAD Scope Fabricate 3 pre-series QXF coils and 46 production QXF coils at Fermilab. Fabrication steps include Winding and Curing, Reaction, and

  • Impregnation. Includes shipping of accepted coil to LBNL for magnet assembly.

BCR Changes (Latest on Top) < No notes stored > Budget HOURS DIRECT BAC DOE.HEP .MIE DOE-High Energy Physics-funded Major Item of Equipment fun 85,813.1 $3,518,591.86 $10,382,461.11 L Labor 85,813.1 $3,293,091.86 $10,084,543.92 M Material 0.0 $225,500.00 $297,917.19 DOE.HEP .OPC DOE-High Energy Physics-funded Other Project Costs funding 4,129.1 $412,913.19 $412,913.19 L Labor 4,129.1 $412,913.19 $412,913.19 Total 89,942.2 $3,931,505.05 $10,795,374.30

Go back

Work Authorization Documents https://cametoolbox.fnal.gov/Project/WADReports?ProjectName=HL-L... 1 of 1 6/25/2018, 8:53 AM

slide-2
SLIDE 2

Activity ID Activity Name Start Finish Cobra PMT Code Planned Material Cost Planned Labor Units Planned NonFermi labor Units

Control Accou Control Account Manager: 10629N Nobrega, Fred

02-Oct-2017 29-Sep-2023 $225,500 89942.23h 0.00h

Control Accoun Control Account: 302.2.05 Coil Fabrication at FNAL

02-Oct-2017 29-Sep-2023 $225,500 89942.23h 0.00h

DOE.HEP.OPC DO DOE.HEP.OPC DOE-High Energy Physics-funded Other Project Costs fund

02-Oct-2017 30-Mar-2018 $0 4129.13h 0.00h C02051010LOP CTC:L3 Management of Coil Fabrication at FNAL-LABOR OP 02-Oct-2017* 30-Mar-2018 C $0 1419.40h 0.00h C02051020PLOP CTC:Pre-Series Coil Fabrication-LABOR OP 02-Oct-2017* 30-Mar-2018 C $0 2709.73h 0.00h

DOE.HEP.MIE DOE DOE.HEP.MIE DOE-High Energy Physics-funded Major Item of Equipment f

02-Apr-2018 29-Sep-2023 $225,500 85813.10h 0.00h A202676 L3 Mgmt of Coil Fab at FNAL (L) (Q3) FY18 02-Apr-2018 29-Jun-2018 A $0 352.00h 0.00h A21695 Coil QXFA-108 Fab (LARP Cable) (L) 02-Apr-2018 09-May-2018 C $0 996.10h 0.00h A21699 Coil QXFA-109 Fab (LARP Cable) (L) 02-Apr-2018 20-Jun-2018 C $0 1659.80h 0.00h A207070 L3 Mgmt of Coil Fab at FNAL (M&S) (Q3) FY18 02-Apr-2018 29-Jun-2018 A $2,500 0.00h 0.00h A21702 Coil QXFA-110 Fab (LARP Cable) (L) 16-Apr-2018 23-Aug-2018 C $0 2214.00h 0.00h A21694 Coil QXFA-108 Ship (LARP Cable) (M&S) 10-May-2018 10-May-2018 C $4,500 0.00h 0.00h A21698 Coil QXFA-109 Ship (LARP Cable) (M&S) 21-Jun-2018 21-Jun-2018 C $4,500 0.00h 0.00h A21707 Coil QXFA-111 Fab (L) 26-Jun-2018 24-Oct-2018 C $0 1543.70h 0.00h A202686 L3 Mgmt of Coil Fab at FNAL (L) (Q4) FY18 02-Jul-2018 28-Sep-2018 A $0 352.00h 0.00h A21703 Coil QXFA-110 Ship (LARP Cable) (M&S) 24-Aug-2018 24-Aug-2018 C $4,500 0.00h 0.00h A21712 Coil QXFA-112 Fab (L) 06-Sep-2018 10-Jan-2019 C $0 1543.70h 0.00h A20844 L3 Mgmt of Coil Fab at FNAL (L) (Q1) FY19 01-Oct-2018 28-Dec-2018 A $0 352.00h 0.00h A20621 Training 2nd Crew Technicans (L) FY19 01-Oct-2018* 18-Jul-2019 C $0 3247.00h 0.00h A207080 L3 Mgmt of Coil Fab at FNAL (M&S) (Q1) FY19 01-Oct-2018 28-Dec-2018 A $2,500 0.00h 0.00h A21708 Coil QXFA-111 Ship (M&S) 25-Oct-2018 25-Oct-2018 C $4,500 0.00h 0.00h A21717 Coil QXFA-113 Fab (L) 15-Nov-2018 22-Mar-2019 C $0 1543.70h 0.00h A202876 L3 Mgmt of Coil Fab at FNAL (L) (Q2) FY19 02-Jan-2019 29-Mar-2019 A $0 352.00h 0.00h A21713 Coil QXFA-112 Ship (M&S) 11-Jan-2019 11-Jan-2019 C $4,500 0.00h 0.00h A21722 Coil QXFA-114 Fab (L) 04-Feb-2019 03-Jun-2019 C $0 1543.70h 0.00h A21718 Coil QXFA-113 Ship (M&S) 25-Mar-2019 25-Mar-2019 C $4,500 0.00h 0.00h A202886 L3 Mgmt of Coil Fab at FNAL (L) (Q3) FY19 01-Apr-2019 28-Jun-2019 A $0 352.00h 0.00h A21727 Coil QXFA-115 Fab (L) 15-Apr-2019 13-Aug-2019 C $0 1543.70h 0.00h A21723 Coil QXFA-114 Ship (M&S) 04-Jun-2019 04-Jun-2019 C $4,500 0.00h 0.00h A21732 Coil QXFA-116 Fab (L) 04-Jun-2019 02-Oct-2019 C $0 1543.70h 0.00h A202896 L3 Mgmt of Coil Fab at FNAL (L) (Q4) FY19 01-Jul-2019 30-Sep-2019 A $0 352.00h 0.00h A21737 Coil QXFA-117 Fab (L) 24-Jul-2019 20-Nov-2019 C $0 1543.70h 0.00h A21728 Coil QXFA-115 Ship (M&S) 14-Aug-2019 14-Aug-2019 C $4,500 0.00h 0.00h A21742 Coil QXFA-118 Fab (L) 12-Sep-2019 16-Jan-2020 C $0 1543.70h 0.00h A20845 L3 Mgmt of Coil Fab at FNAL (L) FY20 01-Oct-2019 30-Sep-2020 A $0 1408.00h 0.00h A21733 Coil QXFA-116 Ship (M&S) 03-Oct-2019 03-Oct-2019 C $4,500 0.00h 0.00h A21747 Coil QXFA-119 Fab (L) 31-Oct-2019 06-Mar-2020 C $0 1543.70h 0.00h A21738 Coil QXFA-117 Ship (M&S) 21-Nov-2019 21-Nov-2019 C $4,500 0.00h 0.00h A21752 Coil QXFA-120 Fab (L) 23-Dec-2019 24-Apr-2020 C $0 1543.70h 0.00h A21743 Coil QXFA-118 Ship (M&S) 17-Jan-2020 17-Jan-2020 C $4,500 0.00h 0.00h A21757 Coil QXFA-121 Fab (L) 17-Feb-2020 15-Jun-2020 C $0 1543.70h 0.00h A21748 Coil QXFA-119 Ship (M&S) 09-Mar-2020 09-Mar-2020 C $4,500 0.00h 0.00h A21762 Coil QXFA-122 Fab (L) 16-Mar-2020 14-Jul-2020 C $0 1543.70h 0.00h A21767 Coil QXFA-123 Fab (L) 13-Apr-2020 11-Aug-2020 C $0 1543.70h 0.00h A21753 Coil QXFA-120 Ship (M&S) 27-Apr-2020 27-Apr-2020 C $4,500 0.00h 0.00h A21772 Coil QXFA-124 Fab (L) 11-May-2020 09-Sep-2020 C $0 1543.70h 0.00h

Cobra PMT Code Legend

A = Level of Effort C = Physical Percent Complete F = 0-100 O = Earned as Spent

Print Date: 25-Jun-2018 - 10:41

Page 1 of 3

US HL-LHC Accelerator Upgrade Project

Work Authorization Document Activities

Project ID: 302-BLBCR006 Project Name: US HL-LHC ACCELERATOR UPGRADE PROJECT: BCR005 Baseline with BCR006 with contingency change Layout: WAD Activities Filter: TASK filters: Control Account, Cost Class 1 is not "OB".

slide-3
SLIDE 3

Activity ID Activity Name Start Finish Cobra PMT Code Planned Material Cost Planned Labor Units Planned NonFermi labor Units A21777 Coil QXFA-125 Fab (L) 09-Jun-2020 07-Oct-2020 C $0 1543.70h 0.00h A21758 Coil QXFA-121 Ship (M&S) 16-Jun-2020 16-Jun-2020 C $4,500 0.00h 0.00h A21782 Coil QXFA-126 Fab (L) 08-Jul-2020 04-Nov-2020 C $0 1543.70h 0.00h A21763 Coil QXFA-122 Ship (M&S) 15-Jul-2020 15-Jul-2020 C $4,500 0.00h 0.00h A21787 Coil QXFA-127 Fab (L) 05-Aug-2020 04-Dec-2020 C $0 1543.70h 0.00h A21768 Coil QXFA-123 Ship (M&S) 12-Aug-2020 12-Aug-2020 C $4,500 0.00h 0.00h A21792 Coil QXFA-128 Fab (L) 02-Sep-2020 07-Jan-2021 C $0 1543.70h 0.00h A21773 Coil QXFA-124 Ship (M&S) 10-Sep-2020 10-Sep-2020 C $4,500 0.00h 0.00h A20846 L3 Mgmt of Coil Fab at FNAL (L) FY21 01-Oct-2020 30-Sep-2021 A $0 1408.00h 0.00h A21797 Coil QXFA-129 Fab (L) 01-Oct-2020 05-Feb-2021 C $0 1543.70h 0.00h A21778 Coil QXFA-125 Ship (M&S) 08-Oct-2020 08-Oct-2020 C $4,500 0.00h 0.00h A21802 Coil QXFA-130 Fab (L) 27-Oct-2020 03-Mar-2021 C $0 1543.70h 0.00h A21783 Coil QXFA-126 Ship (M&S) 05-Nov-2020 05-Nov-2020 C $4,500 0.00h 0.00h A21807 Coil QXFA-131 Fab (L) 20-Nov-2020 29-Mar-2021 C $0 1543.70h 0.00h A21788 Coil QXFA-127 Ship (M&S) 07-Dec-2020 07-Dec-2020 C $4,500 0.00h 0.00h A21812 Coil QXFA-132 Fab (L) 18-Dec-2020 22-Apr-2021 C $0 1543.70h 0.00h A21793 Coil QXFA-128 Ship (M&S) 08-Jan-2021 08-Jan-2021 C $4,500 0.00h 0.00h A21817 Coil QXFA-133 Fab (L) 20-Jan-2021 18-May-2021 C $0 1543.70h 0.00h A21798 Coil QXFA-129 Ship (M&S) 08-Feb-2021 08-Feb-2021 C $4,500 0.00h 0.00h A21822 Coil QXFA-134 Fab (L) 15-Feb-2021 14-Jun-2021 C $0 1543.70h 0.00h A21803 Coil QXFA-130 Ship (M&S) 04-Mar-2021 04-Mar-2021 C $4,500 0.00h 0.00h A21827 Coil QXFA-135 Fab (L) 11-Mar-2021 09-Jul-2021 C $0 1543.70h 0.00h A21808 Coil QXFA-131 Ship (M&S) 30-Mar-2021 30-Mar-2021 C $4,500 0.00h 0.00h A21832 Coil QXFA-136 Fab (L) 06-Apr-2021 04-Aug-2021 C $0 1543.70h 0.00h A21813 Coil QXFA-132 Ship (M&S) 23-Apr-2021 23-Apr-2021 C $4,500 0.00h 0.00h A21837 Coil QXFA-137 Fab (L) 30-Apr-2021 30-Aug-2021 C $0 1543.70h 0.00h A21818 Coil QXFA-133 Ship (M&S) 19-May-2021 19-May-2021 C $4,500 0.00h 0.00h A21842 Coil QXFA-138 Fab (L) 26-May-2021 24-Sep-2021 C $0 1543.70h 0.00h A21823 Coil QXFA-134 Ship (M&S) 15-Jun-2021 15-Jun-2021 C $4,500 0.00h 0.00h A21847 Coil QXFA-139 Fab (L) 22-Jun-2021 20-Oct-2021 C $0 1543.70h 0.00h A21828 Coil QXFA-135 Ship (M&S) 12-Jul-2021 12-Jul-2021 C $4,500 0.00h 0.00h A21852 Coil QXFA-140 Fab (L) 19-Jul-2021 15-Nov-2021 C $0 1543.70h 0.00h A21833 Coil QXFA-136 Ship (M&S) 05-Aug-2021 05-Aug-2021 C $4,500 0.00h 0.00h A21857 Coil QXFA-141 Fab (L) 12-Aug-2021 13-Dec-2021 C $0 1543.70h 0.00h A21838 Coil QXFA-137 Ship (M&S) 31-Aug-2021 31-Aug-2021 C $4,500 0.00h 0.00h A21862 Coil QXFA-142 Fab (L) 08-Sep-2021 12-Jan-2022 C $0 1543.70h 0.00h A21843 Coil QXFA-138 Ship (M&S) 27-Sep-2021 27-Sep-2021 C $4,500 0.00h 0.00h A20847 L3 Mgmt of Coil Fab at FNAL (L) FY22 01-Oct-2021 30-Sep-2022 A $0 1408.00h 0.00h A21867 Coil QXFA-143 Fab (L) 04-Oct-2021 08-Feb-2022 C $0 1543.70h 0.00h A21848 Coil QXFA-139 Ship (M&S) 21-Oct-2021 21-Oct-2021 C $4,500 0.00h 0.00h A21872 Coil QXFA-144 Fab (L) 28-Oct-2021 04-Mar-2022 C $0 1543.70h 0.00h A21853 Coil QXFA-140 Ship (M&S) 16-Nov-2021 16-Nov-2021 C $4,500 0.00h 0.00h A21877 Coil QXFA-145 Fab (L) 23-Nov-2021 30-Mar-2022 C $0 1543.70h 0.00h A21858 Coil QXFA-141 Ship (M&S) 14-Dec-2021 14-Dec-2021 C $4,500 0.00h 0.00h A21882 Coil QXFA-146 Fab (L) 21-Dec-2021 25-Apr-2022 C $0 1543.70h 0.00h

Cobra PMT Code Legend

A = Level of Effort C = Physical Percent Complete F = 0-100 O = Earned as Spent

Print Date: 25-Jun-2018 - 10:41

Page 2 of 3

US HL-LHC Accelerator Upgrade Project

Work Authorization Document Activities

Project ID: 302-BLBCR006 Project Name: US HL-LHC ACCELERATOR UPGRADE PROJECT: BCR005 Baseline with BCR006 with contingency change Layout: WAD Activities Filter: TASK filters: Control Account, Cost Class 1 is not "OB".

slide-4
SLIDE 4

Activity ID Activity Name Start Finish Cobra PMT Code Planned Material Cost Planned Labor Units Planned NonFermi labor Units A21863 Coil QXFA-142 Ship (M&S) 13-Jan-2022 13-Jan-2022 C $4,500 0.00h 0.00h A21887 Coil QXFA-147 Fab (L) 21-Jan-2022 19-May-2022 C $0 1543.70h 0.00h A21868 Coil QXFA-143 Ship (M&S) 09-Feb-2022 09-Feb-2022 C $4,500 0.00h 0.00h A21892 Coil QXFA-148 Fab (L) 16-Feb-2022 15-Jun-2022 C $0 1543.70h 0.00h A21873 Coil QXFA-144 Ship (M&S) 07-Mar-2022 07-Mar-2022 C $4,500 0.00h 0.00h A21897 Coil QXFA-149 Fab (L) 14-Mar-2022 12-Jul-2022 C $0 1543.70h 0.00h A21878 Coil QXFA-145 Ship (M&S) 31-Mar-2022 31-Mar-2022 C $4,500 0.00h 0.00h A21902 Coil QXFA-150 Fab (L) 07-Apr-2022 05-Aug-2022 C $0 1543.70h 0.00h A21883 Coil QXFA-146 Ship (M&S) 26-Apr-2022 26-Apr-2022 C $4,500 0.00h 0.00h A21907 Coil QXFA-151 Fab (L) 03-May-2022 31-Aug-2022 C $0 1543.70h 0.00h A21888 Coil QXFA-147 Ship (M&S) 20-May-2022 20-May-2022 C $4,500 0.00h 0.00h A21912 Coil QXFA-152 Fab (L) 27-May-2022 27-Sep-2022 C $0 1543.70h 0.00h A21893 Coil QXFA-148 Ship (M&S) 16-Jun-2022 16-Jun-2022 C $4,500 0.00h 0.00h A21917 Coil QXFA-153 Fab (L) 23-Jun-2022 21-Oct-2022 C $0 1543.70h 0.00h A21918 Coil QXFA-153 Ship (M&S) 23-Jun-2022 23-Jun-2022 C $4,500 0.00h 0.00h A21898 Coil QXFA-149 Ship (M&S) 13-Jul-2022 13-Jul-2022 C $4,500 0.00h 0.00h A21923 Coil QXFA-154 Ship (M&S) 20-Jul-2022 20-Jul-2022 C $4,500 0.00h 0.00h A21922 Coil QXFA-154 Fab (L) 20-Jul-2022 16-Nov-2022 C $0 1543.70h 0.00h A21903 Coil QXFA-150 Ship (M&S) 08-Aug-2022 08-Aug-2022 C $4,500 0.00h 0.00h A21927 Coil QXFA-155 Fab (L) 15-Aug-2022 14-Dec-2022 C $0 1543.70h 0.00h A21908 Coil QXFA-151 Ship (M&S) 01-Sep-2022 01-Sep-2022 C $4,500 0.00h 0.00h A205790 Coil QXFA-156 Fab (L) 09-Sep-2022 13-Jan-2023 C $0 1543.70h 0.00h A21913 Coil QXFA-152 Ship (M&S) 28-Sep-2022 28-Sep-2022 C $4,500 0.00h 0.00h A204830 L3 Mgmt of Coil Fab at FNAL (L) FY23 03-Oct-2022 29-Sep-2023 A $0 350.00h 0.00h A21928 Coil QXFA-155 Ship (M&S) 15-Dec-2022 15-Dec-2022 C $4,500 0.00h 0.00h A205800 Coil QXFA-156 Ship (M&S) 17-Jan-2023 17-Jan-2023 C $4,500 0.00h 0.00h

Cobra PMT Code Legend

A = Level of Effort C = Physical Percent Complete F = 0-100 O = Earned as Spent

Print Date: 25-Jun-2018 - 10:41

Page 3 of 3

US HL-LHC Accelerator Upgrade Project

Work Authorization Document Activities

Project ID: 302-BLBCR006 Project Name: US HL-LHC ACCELERATOR UPGRADE PROJECT: BCR005 Baseline with BCR006 with contingency change Layout: WAD Activities Filter: TASK filters: Control Account, Cost Class 1 is not "OB".

slide-5
SLIDE 5

Control Account Plan

Pick one or more Control Accounts or pick a CAM. Pick a time-range or leave blank for auto-calculation. Click Show. Click on the icon for expanding a time range. Click / unclick the Fiscal box to flip between Fiscal / Calendar years. Control Account: Cost Set: Results: CAM: From: To: Fiscal: Control Account CAM Fund Type CA Start CA Finish CTC Resource_TYPE FY_2018_oct_dec FY_2018_jan_mar apr/18 may/18 jun/18 jul/18 aug/18 sep/18

  • ct/18

nov/18 dec/18 jan/19 feb/19 mar/19 FY_2019_apr_jun FY_2019_jul_sep FY_2020 FY_2021 FY_2022 FY_2023 Total 302.2.05 Coil Fabrication at FNAL 10629N Nobrega, Fred DOE.HEP.MIE 8/1/2016 9/29/2023 302.205L0001 L3 Management of Coil Fabrication at FNAL LABOR EQ L Labor $19,826 $20,770 $19,826 $20,140 $22,058 $18,222 $23,511 $20,444 $18,400 $21,120 $20,114 $21,120 $62,354 $62,354 $370,259 Subtotal $19,826 $20,770 $19,826 $20,140 $22,058 $18,222 $23,511 $20,444 $18,400 $21,120 $20,114 $21,120 $62,354 $62,354 $370,259 8/1/2016 9/29/2023 302.205L0002 Coil Fabrication LABOR EQ L Labor $177,499 $155,171 $107,339 $94,642 $87,865 $67,503 $79,338 $58,052 $69,663 $54,182 $75,468 $71,598 $228,339 $301,872 $1,639,538 $2,400,688 $2,517,564 $367,675 $8,553,995 Subtotal $177,499 $155,171 $107,339 $94,642 $87,865 $67,503 $79,338 $58,052 $69,663 $54,182 $75,468 $71,598 $228,339 $301,872 $1,639,538 $2,400,688 $2,517,564 $367,675 $8,553,995 8/1/2016 9/29/2023 302.205L0003 Technician Training LABOR EQ L Labor $33,785 $29,378 $26,440 $30,847 $29,378 $30,847 $94,010 $19,096 $293,780 Subtotal $33,785 $29,378 $26,440 $30,847 $29,378 $30,847 $94,010 $19,096 $293,780 8/1/2016 9/29/2023 302.205M0001 L3 Management of Coil Fabrication at FNAL M&S EQ M Material $965 $1,011 $965 $1,131 $983 $885 $5,940 Subtotal $965 $1,011 $965 $1,131 $983 $885 $5,940 8/1/2016 9/29/2023 302.205M0002 Coil Fabrication M&S EQ M Material $5,631 $5,631 $5,631 $5,744 $5,744 $5,744 $5,744 $5,744 $52,731 $83,666 $97,531 $12,435 $291,977 Subtotal $5,631 $5,631 $5,631 $5,744 $5,744 $5,744 $5,744 $5,744 $52,731 $83,666 $97,531 $12,435 $291,977 8/1/2016 9/29/2023 No CTC L Labor $257,398 $265,378 $273,604 $70,129 $866,510 Subtotal $257,398 $265,378 $273,604 $70,129 $866,510 Subtotal $198,289 $182,583 $133,761 $114,782 $115,555 $85,725 $143,509 $108,858 $115,388 $111,893 $124,960 $129,309 $390,447 $389,066 $1,949,667 $2,749,732 $2,888,699 $450,239 $10,382,461 DOE.HEP.OPC 8/1/2016 9/29/2023 302.02.05.1010L.OP L3 Management of Coil Fabrication at FNAL-LABOR OP L Labor $69,239 $72,701 $141,940 Subtotal $69,239 $72,701 $141,940 8/1/2016 9/29/2023 302.02.05.1020PL.OP Pre-Series Coil Fabrication-LABOR OP L Labor $132,182 $138,791 $270,973 Subtotal $132,182 $138,791 $270,973 Subtotal $201,421 $211,492 $412,913 Subtotal $201,421 $211,492 $198,289 $182,583 $133,761 $114,782 $115,555 $85,725 $143,509 $108,858 $115,388 $111,893 $124,960 $129,309 $390,447 $389,066 $1,949,667 $2,749,732 $2,888,699 $450,239 $10,795,374 Total $201,421 $211,492 $198,289 $182,583 $133,761 $114,782 $115,555 $85,725 $143,509 $108,858 $115,388 $111,893 $124,960 $129,309 $390,447 $389,066 $1,949,667 $2,749,732 $2,888,699 $450,239 $10,795,374 Go back

302.2.05 Coil Fabrication at FNAL None selected

Control Account Plan https://cametoolbox.fnal.gov/DataSet/CAPPivot?DataSetId=45&ControlAccount=302.2.05+Co... 1 of 1 6/25/2018, 8:50 AM