Presentation to Lee County Zoning Board of Appeals On Behalf of - - PowerPoint PPT Presentation
Presentation to Lee County Zoning Board of Appeals On Behalf of - - PowerPoint PPT Presentation
Presentation to Lee County Zoning Board of Appeals On Behalf of Local Landowners and Hamilton Township Tom Hewson John Stamberg P.E. Principal Energy Ventures Analysis Inc Arlington Virginia 703-276-8900 November 27, 2011 Decommissioning
Decommissioning Costs and Risks
Why should Lee County care?
Paul Gipe estimated that there over 14,000 wind turbines in California alone that were abandoned by 1997. Abandoned wind turbines have/will continue to adversely affect local property values and character.
Caithness Windfarm Information Forum (www.caithnesswindfarms.co.uk) tracks wind turbine accident data that can be confirmed through press reports or official releases. They have documented (through 9/2012) 249 turbine blade failure incidents, 195 turbine fires and 130 structural failures– that can lead to premature unit decommissioning.
Wind facilities are often developed as limited liability corporations. At the end of the project life, the LLC may have no equity remaining to fund decommissioning cost.
Pre-funding future decommissioning costs has become a common requirement for wind project permitting.
Intent to have cost paid by wind developer who financially benefits from wind project operation
Different approaches available to assign decommissioning cost and risk between wind project
- perators and local community
Decommissioning Risk
Abandoned Wind Turbines at Kamora Wind Farm (HI)
Decommissioning Risk
130 documented cases of structural failure such this January 2008 accident in Cumbria UK
Decommissioning Risk
Wind turbine foundation failure
Decommissioning Risk
195 Documented Wind turbine fires such as this turbine in
- Germany. Can be caused by equipment failure or lightning.
Decommission Planning
Decommissioning Plan Components
Defining Scope of Work:
Dismantling wind turbines and met towers
Removing turbine foundations (to what depth?) and land reclamation
Removing crane pads
Substation removal (transformers, equipment, foundations, etc..)
O&M building removal
Access Roads- Retain or remove?
Collection system electrical system- Abandon underground lines or remove?
Trigger decommissioning as individual turbines cease operation or wait until entire project is shutdown
Decommission Financing
Financing cost approaches
Project performance bond for a defined scope of work with an approved
highly rated bonding company--- Assigns 100% of project risk to project bonding agency
Financial bond at a preset amount to be sufficient to cover anticipated
decommissioning costs– Leaves future cost escalation and scrap value risks to local community and property owners
Other financial assurance – Assigns full financial risks to local community
and property owners if financial assurance entity fails
Decommissioning Costs
Decommissioning Costs
Table 1. Decommissioning Cost Known To Wind Turbine Contractors and Items with Insufficient Details to Make Independent Demolition Estimates
Decommissioning Costs
Scrap Amounts Dixon Iron and Metal 7/20/12 Verbal Quote
(4)
Per Turbine Received Scrap Value Truck Delivery Cost
(5)
Cost to Disassemble
- r Torch
(6)
Cost to Load at Wind Farm Crew B-12N
(7)
Net Scrap Value
- I. Turbine Metal
- A. Rotor 60 Tons
(1),(3)
- 1. Hub Iron/Steel
40 tons $165/ton $6,600 $400 (2 trips) $1,000 $2,305 $2,895
- 2. Blades
20 tons
- B. Nacelle 82 Tons
(1),(2)
- 1. Gear Box, Transmission,
Brakes 35 tons $165/ton $5,775 $400 (2 trips) Nil $2,305 $3,070
- 2. Generator
35 tons $7,500/each $7,500 $200 (1 trip) Nil $1,153 $6,147
- 3. Non-Metal
12 tons
- C. Tower/Bolts
(2)
- 1. Tower
205 tons $165/ton $33,825 $4,000 (10 trips) $5,000 $11,525 $13,300
- D. Subtotal per Turbine
280 tons $53,700 ($5,000) ($6,000) ($17,288) $25,412
- E. Subtotal per 87 Turbines
24,360 tons $4,671,900 ($435,000) ($522,000) ($1,504,056) $2,210,844
- II. Transformers/Miscellaneous
- A. Turbine Transformer
7.48 tons
- 1. Sheet Steel
3.1 tons
- 2. Core Steel
1.6 tons 6.3 tons $3,276 at $66 Nil $768 $2,442
- 3. Core Copper
1.6 tons $0.26/#
(9)
(3 trips)
- 4. Oil
1.15 tons
- B. Subtotal per 87 Turbines
$285,012 ($5,742) Nil ($66,816) $212,454
- C. Master Primary Transformer
(MPT) 120 tons $62,400
(10)
$0.26/# $800 (4 trips) Nil ($2,305) $59,294
- D. Miscellaneous (in above
Section I)
- E. Subtotal per 87 Turbines
$347,412 ($6,542) Nil ($69,121) $271,748
- III. Total Salvage Value
$5,019,312 ($441,542) ($522,000) ($1,573,177) $2,482,592
Table 2 Net Scrap Salvage Value
Decommissioning Costs
Table 3 Non-Metal Disposal Costs
Item Amount Site Process Cost Trucking Cost To Load Landfill Dumping Cost Total Cost
- 1. Blades
20 tons $4,371.50/3 blades $200 (1 trip) $51.00 3/day $900
(
$5,542.50 (Crew B-7) (Crew B-10-U)
- 2. Nacelle Non-Metal
12 tons $1,452.60 $200 (1 trip) $51.00 3/day $450 $2,153.60 (Crew Q-20) (Crew B-10-U)
- 3. Transformer and Transmission
500 gal $1,200 = 12 barrels $50.00 Nil $450 $1,700.00 Oils @ $100/barrel
- 4. Cost per Turbine
$7,024.10 $450 $102 $1,800 $9,376.10
- 5. Cost for 87 Turbines
$611,097 $39,150 $8,874 $156,600 $815,721
Lee County landfill charge at $900 per 20 ton load
Decommissioning Costs
Table 4- Foundation Removal and Land Reclamation
Decommissioning Costs
Table 5 --Road Removal Costs