make to innovate
play

MAKE TO INNOVATE Mid-Term Review Spring 2019 Micro-g Project - PowerPoint PPT Presentation

MAKE TO INNOVATE Mid-Term Review Spring 2019 Micro-g Project Overview Activity Report Design Review Design Constraints Current Design AGENDA Proposed Changes Design Risks Budget Status Conclusion Spring 2019 Make to


  1. MAKE TO INNOVATE Mid-Term Review – Spring 2019 Micro-g

  2. Project Overview Activity Report Design Review • Design Constraints • Current Design AGENDA • Proposed Changes • Design Risks Budget Status Conclusion Spring 2019 Make to Innovate (M:2:I)

  3. PROJECT OVERVIEW Project Executive Summary

  4. PROJECT OVERVIEW • Micro-g NExT • Challenge for undergraduate students to design tools in partnership with National Aeronautics and Space Administration (NASA) • M:2:I Micro-g • Manufacture and test an Extravehicular Activity (EVA) Camera Mount Neutral Buoyancy Laboratory Spring 2019 Make to Innovate (M:2:I) EVA Camera Mount

  5. PROJECT OVERVIEW Pictured (Left to Right, Top to Bottom): Justin Stein, Ty Sandene, Jeremy Hayhurst, Tyler Hoppe, Daniel Partida-Wittman, Dakota Fouts, Bryce Miles, Katerina Connelly, James LaPorta, Trevor Lyon, Jacob Thompson Make to Innovate (M:2:I) Spring 2019

  6. Project Faculty Tomas Gonzalez-Torres – Aerospace Engineering Adviser Project Dr. Cullinan – Material Science and Engineering Technical Jessica Tramaglini – NASA Mentor Advisers PROJECT OVERVIEW Project Team Ty Sandene – Aerospace Engineering Lead Project Micro-g NExT University – NASA Stake Space Grant Consortium – NASA Holders Make to Innovate – Iowa State University Make to Innovate (M:2:I) Spring 2019

  7. PROJECT OVERVIEW Project Lead Ty Sandene Design and Test and Manufacturing Prototype Team Team Lead Lead Trevor Lyon Justin Stein Design and Test and Manufacturing Prototype Team Team Dakota Fouts Bryce Miles Jeremy Hayhurst Daniel Partida-Wittman Katerina Connelly Jacob Thompson Tyler Hoppe James LaPorta Make to Innovate (M:2:I) Spring 2019

  8. PROJECT OVERVIEW • Project Mission Statement: Micro- g’s mission is to develop tools for NASA which will be used in a micro-gravity environment. The end goal is to generate new technology that will be used in future spaceflight missions, having a significant impact on the world of manned spaceflight. • Project Objectives: The objective of Micro-g is to design, manufacture, and test an Extravehicular Camera Mount to be used by NASA. For this semester, the team will submit a Test Equipment Data Package, Proof of Concept Video, and Test Readiness Review prior to traveling to Houston for the final test week in the Neutral Buoyancy Laboratory (NBL). Make to Innovate (M:2:I) Spring 2019

  9. PROJECT OVERVIEW Semester Goals: • Manufacture a test-ready EVA Camera Mount for NASA • Submit a Proof of Concept Video, Test Equipment Data Package, and Test Readiness Review • Successfully test Micro- g’s EVA Camera Mount design in the Neutral Buoyancy Laboratory. Deliverables: • Micro- g’s deliverables include a test -ready EVA camera mount, comprehensive Test Equipment Data Package (TEDP), Proof of Concept Video, and Test Readiness Review (TRR). Make to Innovate (M:2:I) Spring 2019

  10. PROJECT PLAN High Level Plan: • Manufacture EVA Camera Mount • Successfully test in the NBL Make to Innovate (M:2:I) Spring 2019

  11. ACTIVITY REPORT Milestones, Tasks, and Health Report

  12. MILESTONES Design and Manufacturing: • Milestone 1 Deliverables: • ANSYS analysis on the camera mount design. • Test and Equipment Data Package • Proof of Concept Video • Hardware Design • Milestone 2 Deliverables: • Test Readiness Review • Device Overview • Component Review Make to Innovate (M:2:I) Spring 2019

  13. TASK BREAKDOWN Design team Make to Innovate (M:2:I) Spring 2019

  14. MILESTONES Test and Prototype Team • Milestone 1 Deliverables: • Completion of the Testing • Test Equipment Data Package: • Operations • Hazard Analysis • Milestone 2 Deliverables: • Completion of the Operation • Test Readiness Review: • Technical Requirements • Hazard Analysis Make to Innovate (M:2:I) Spring 2019

  15. TASK BREAKDOWN Test team Make to Innovate (M:2:I) Spring 2019

  16. PROJECT HEALTH REPORT • Project is currently on Accelerated schedule Task: Status: Due Date: Date: Notes: • Delays in outsourced parts Manufacturing of final camera mount In progress 3/25/2019 3/12/2019 Purchased from Re3dtech may delay manufacturing of TEDP: In progress 3/25/2019 3/15/2019 Micro-g accelerated date: 3/15/2019 final camera mounts Hardware Design In progress 3/25/2019 3/15/2019 Requires photos of the final camera mount • Prototype built will be used Analysis and Testing In progress 3/25/2019 3/15/2019 Requires the final camera mount for the TEDP Operations Plan In progress 3/25/2019 3/15/2019 Does not require physical camera mount Hazard Analysis In progress 3/25/2019 3/15/2019 Does not require physical camera mount Forward Plan Not Started 3/25/2019 3/15/2019 Back up section addressing any issues Proof of Concept Video Not Started 3/25/2019 3/23/2019 Micro-g accelerated date: 3/23/2019 Test Readiness Review Not Started 5/13/2019 5/1/2019 2 months out Make to Innovate (M:2:I) Spring 2019

  17. DESIGN REVIEW Overview

  18. DESIGN OVERVIEW Prototype V2 Prototype V3 Make to Innovate (M:2:I) Spring 2019

  19. PROTOTYPE V2 • Two switches engage/disengage the pawl • Springs provide the tension to create the moment to hold the switch in locked/ unlocked position • If one switch fails, the other can still lock the mechanism Make to Innovate (M:2:I) Spring 2019

  20. PROTOTYPE V3 • One switch to engage/disengage the pawl • Constant force spring on the other side of the double gear • If the one fails the other is able to keep the clamps shut Make to Innovate (M:2:I) Spring 2019

  21. DESIGN REVIEW Constraints

  22. DESIGN CONSTRAINTS • With Micro- g’s budget, the EVA camera Micro-g NExT Requirements mount will be manufactured from The device shall attach to at least two of three interfaces 1 cheaper test-ready materials 2 The device shall include a 1-fault tolerant attach method 3 The device shall use only manual power • To be consider for flight, the camera The device shall allow for camera pitch and yaw mount was designed to fit all three adjustability of ± 45˚ 4 interfaces The device shall be able to pack within 12" x 16" x 18" 5 6 The total must be less than 15 lbs. 7 Device shall be made from NBL approved materials 8 Device shall allow a GoPro to mount to it 9 Pinch points should be minimized Make to Innovate (M:2:I) Spring 2019

  23. DESIGN REVIEW Current Design

  24. CURRENT DESIGN • Decided to continue with prototype V2 due to constant spring causing issues • Reduces pinch hazard caused by constant spring • Simpler to assemble Make to Innovate (M:2:I) Spring 2019

  25. CURRENT DESIGN • Current design uses a double gear • Larger gear moves both sliding arms the same length and in the same direction • Pawl engages smaller gear to lock the sliding arms from opening while attached Make to Innovate (M:2:I) Spring 2019

  26. DESIGN REVIEW Proposed Changes

  27. PROPOSED CHANGES • Removed away from pin design • Added switch system instead of traditional ratcheting system • Removed end of the sliding arm to ease manufacturing/assembly Make to Innovate (M:2:I) Spring 2019

  28. DESIGN REVIEW Design Risks

  29. DESIGN RISKS • Risk 1: Missing NASA deadlines for Micro-g NExT • Mitigation 1: The Micro-g timeline has been advanced • Risk 2: Key component failing during testing at the NBL • Mitigation 2: Conduct comprehensive testing and analysis prior to May • Risk 3: Design flaw resulting in failure to meet requirements • Mitigation 3: 3D print and test prototype version prior to final build Make to Innovate (M:2:I) Spring 2019

  30. BUDGET Status and requests

  31. BUDGET STATUS Requested Approved Est. March Budget Spent Remaining Budget Budget Expenditures • In total, Micro-g received $6,250 in funding: $5,000 from the Iowa Raw Space Grant Consortium and $2,000 $2,000 $225.47 $1,775 $1,250 Supplies $1,250 from the Department of Aerospace Engineering Equipment $2,000 $2,000 $0 $2,000 $1,250 • Micro-g has consumed $225 or 3.6% of the budget as of March. Travel $2,250 $2,250 $0 $2,000 $0 Remaining: Total $6,250 $6,250 $225.47 $6,024.53 $3,524.53 Make to Innovate (M:2:I) Spring 2019

  32. BUDGET STATUS • Expected additional $1000 stipend from NASA for meeting milestones • $200 – Team Roster/organization chart • $200 – Gantt Chart/timeline • $400 – TEDP $400 – Proof of Concept Video • No additional funding is being pursued for Micro-g

  33. CONCLUSION

  34. CLOSING • Micro-g will manufacture the final camera mount this March • Project is on schedule to meet required deadlines • No major risks or scheduling threats requiring additional mitigation at this time

  35. EXTRA SLIDES

  36. ISS INTERFACES:

  37. SWITCH (SIDE VIEW) Make to Innovate (M:2:I) Spring 2019

  38. SWITCH (FRONT) Make to Innovate (M:2:I) Spring 2019

  39. SWITCH & DOUBLE PAWL Make to Innovate (M:2:I) Spring 2019

  40. SWITCH & DOUBLE PAWL Make to Innovate (M:2:I) Spring 2019

  41. INTERFACE ATTACHMENT Make to Innovate (M:2:I) Spring 2019

  42. INTERFACE ATTACHMENT

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend