MAKE TO INNOVATE
Final Review – Spring 2019 Micro-G
MAKE TO INNOVATE Final Review Spring 2019 Micro-G Project Overview - - PowerPoint PPT Presentation
MAKE TO INNOVATE Final Review Spring 2019 Micro-G Project Overview Activity Report Project Review Design Constraints Final Design AGENDA Future Plans Risks Budget Status Conclusion Spring 2019 Make to Innovate (M:2:I)
Final Review – Spring 2019 Micro-G
Project Overview Activity Report
Project Review Budget Status Conclusion
Spring 2019 Make to Innovate (M:2:I)
Project Executive Summary
Aeronautics and Space Administration (NASA)
EVA Camera Mount Neutral Buoyancy Laboratory
Make to Innovate (M:2:I) Spring 2019
Pictured (Left to Right, Top to Bottom): Justin Stein, Ty Sandene, Jeremy Hayhurst, Tyler Hoppe, Daniel Partida-Wittman, Dakota Fouts, Bryce Miles, Katerina Connelly, James LaPorta, Trevor Lyon, Jacob Thompson
Make to Innovate (M:2:I) Spring 2019
SPRING 2019 Make to Innovate (M:2:I)
Project Stake Holders
Micro-g NExT University – NASA Space Grant Consortium – NASA Department of Aerospace Engineering– Iowa State University
Project Team Lead
Ty Sandene – Aerospace Engineering
Project Technical Advisers
Jessica Tramaglini – NASA Mentor
Project Faculty Adviser
Tomas Gonzalez-Torres – Aerospace Engineering
PROJECT OVERVIEW
Project Lead
Ty Sandene
Design and Manufacturing Team Lead
Trevor Lyon
Design and Manufacturing Team
Dakota Fouts Jeremy Hayhurst Katerina Connelly Tyler Hoppe
Test and Prototype Team Lead
Justin Stein
Test and Prototype Team
Bryce Miles Daniel Partida-Wittman Jacob Thompson James LaPorta
Make to Innovate (M:2:I) Spring 2019
Project Mission Statement: Micro-g’s mission is to develop tools for NASA which will be used in a micro-gravity environment. The end goal is to generate new technology that will be used in future spaceflight missions and Extravehicular Activity (EVA) walks, having a significant impact on the world of manned spaceflight. Achieved Project Goals:
Package (TEDP)
Remaining Goals:
Make to Innovate (M:2:I) Spring 2019
Deliverables: Achieved:
(TEDP)
Planned:
Make to Innovate (M:2:I) Spring 2019
Milestones, Tasks, and Health Report
Design and Manufacturing:
Spring 2019
Make to Innovate (M:2:I)
Test and Prototype Team
Spring 2019
Make to Innovate (M:2:I)
Spring 2019
manufactured in case of failure while testing
Make to Innovate (M:2:I)
Task Status Due Date Accelerated Date Manufacture Final Camera Mount Complete 3/25/2019 3/12/2019 TEDP Complete 3/25/2019 3/12/2019 Proof of Concept Video Complete 3/25/2019 3/12/2019 Micro-g Poster Complete 4/29/2019 4/26/2019 Diver Briefing Package Complete 5/10/2019 4/29/2019 Cribsheet Complete 5/17/2019 4/29/2019 Test Readiness Review In Progress 5/13/2019 5/3/2019
Spring 2019
Overview
Top Level Overview
when stowed (without camera arm)
fully extended
Make to Innovate (M:2:I) Spring 2019
Top Level Overview
to lock/unlock clamp
inside lever box
Make to Innovate (M:2:I) Spring 2019
Top Level Overview Operation:
showing
desired size
green is showing
desired surface
be adjusted
Make to Innovate (M:2:I) Spring 2019
Constraints
Make to Innovate (M:2:I) Spring 2019
Final Design
Interface Camera Effector (ICE) can attach to all 3 International Space Station interfaces
Make to Innovate (M:2:I)
Make to Innovate (M:2:I) Spring 2019
Make to Innovate (M:2:I) Spring 2019
Gear Box
Make to Innovate (M:2:I) Spring 2019
Sliding Arm
Make to Innovate (M:2:I) Spring 2019
Camera Arm
Future Work
Switch System Removable Clamp
Make to Innovate (M:2:I) Spring 2019
Key Risks:
Make to Innovate (M:2:I) Spring 2019
Status and requests
Estimated Spent Remaining Raw Supplies $2,000.00 $494.33 Equipment $2,000.00 $1,760.29 Travel $2,250.00 $3,839.50 Total: $6,250.00 $6,094.12 $155.88
$6,250 in funding and has spent $6,094.12.
not be allocated; however, may be used for minor repairs or testing
Make to Innovate (M:2:I) Spring 2019