SLIDE 1
PRE-BOILER SYSTEM OBJECTIVES To remove dirt ,oil ,grease etc., from - - PowerPoint PPT Presentation
PRE-BOILER SYSTEM OBJECTIVES To remove dirt ,oil ,grease etc., from - - PowerPoint PPT Presentation
CHEMICAL CLEANING OF PRE-BOILER SYSTEM OBJECTIVES To remove dirt ,oil ,grease etc., from Condensate ,Feed water, Drip and Extraction steam lines of HP and LP heaters prior to putting these systems in regular service. This is to ensure flow of
SLIDE 2
SLIDE 3
STATE OF THE PLANT
- Hydro-test of the entire system to be flushed declared
completed.
- All the regenerative equipments are installed in position and
temporary pipeline connection as per scheme is complete.
- The bore of the temporary pipelines should preferably be the
same as that used in permanent system.
- All permanent support are provided for all the pipelines before
flushing.
- Plugs to be provided in the safety valves of LPHs,water seal
inlets in flash tanks and LPH 1 and in C&I tapping.
- Screens to be provided on booster pump suction line and acid
cleaning pump suction line
SLIDE 4
- Availability of auxiliary steam.
- Reagent preparation plant.
- Sampling points for each circuit.
- Level gauge on tank, pressure gauges and temperature
indicators wherever required.
- All the cutting and welding work on instrument tapping points
are complete upto isolating root valves.
- All the orifices,flow nozzles, control valves and NRV internals
are removed and a checklist is prepared. Spool pieces are provided wherever required.
- Installation of temporary chemical cleaning pumps(2 nos.) and
connected piping along with required instrumentation is complete.
- During post mounting cleaning it is proposed to use chemically
clean water from condensate storage tank.
SLIDE 5
- Readiness of process water supply system,condenser
circulating water system with pump house.
- Availability of compressed air.
- Proximate analysis laboratory facility.
- Power supply to acid cleaning pumps,CEPs,condensate
emergency make up pumps, condensate normal make up pumps, motor operated valves and lighting.
SLIDE 6
EQUIPMENTS AND RESOURCES FOR WATER WASHING
- Condensate storage tanks.
- Condenser of volume 1000m3 as a reservoir for storing the
dematerialized water.
- Turbine condensate pumps (3 nos.).
- Chemical cleaning pumps (q=300t/h,h=80mwg,n=1500rpm)-
2nos.
- Compressor plant and pipeline Dn100 to supply air into the
washing circuit with the parameters not less than q=20m3/min,p=0.6MPa
- Pipelines and valves Dn 20-300,Pn 1.6MPa
SLIDE 7
EQUIPMENT AND RESOURCES FOR CHEMICAL CLEANING AND PASSIVATION
- Deaerator and Feed Water Storage Tank.
- Chemical cleaning pumps (q=300t/h,h=80mwg,n=1500rpm)-
2nos.
- Pipelines and valves Dn 20-300,Pn 1.6MPa
- SG Package neutralizing basin for collecting the spent
solutions.
- Reagent Preparation Plant designed for storage, preparation
and supply of chemical reagents.
- Chemical reagents.
- Washing process controlling instruments (flow elements,
pressure gauges, level gauges, temperature elements)
SLIDE 8
The pre-boiler system consists of
- Condensate system
- Drip system
- Feed water system
- Extraction steam lines to Regenerative Heaters
SLIDE 9
→ Condensate system comprises of 3 nos. of Condensate Extraction Pumps,Low Pressure Heaters, Gland Steam Cooler,Deaerator,connecting pipelines including excess condensate line upto Condensate storage tank.
SLIDE 10
→Feed water system comprises 2 nos. of motor driven boiler feed pumps,2 nos. of Turbine driven boiler feed pumps ,their booster pumps and recirculation lines, high pressure heaters, their connecting pipelines upto econimiser inlet.Reheater and Superheater spray line are also included for the purpose of flushing.
SLIDE 11
→ Drip system comprises of the shell side of all LP and HP heaters and their normal and emergency drip lines.
SLIDE 12
→Extraction steam system consists of bled steam lines from different stages of Turbines (HPT,IPT and LPT) to LP and HP heaters,Deaerator and TDBFPs.
SLIDE 13
CLEANING METHOD
- Pre- mounting cleaning.
- Extraction steam lines to regenerative heaters
- Post-mounting cleaning.
- Feed water line,Condendate line and heater drip lines.
- Steam blowing.
- MS line,CRH line , HRH line ,steam line to TDBFPs etc.
SLIDE 14
METHODS AND SCOPE OF CLEANING Post Mounting Cleaning
- Main Turbine and BFP Drive Turbine Condenser Cleaning.
- Hydro-pneumatic Washing with Demineralized Water of Unit
Circulating System.
- Chemical Cleaning of Water–Steam path of Heater and
Pipeline with hydrofluoric Acid solution.
- Chemical Passivation of Water-Steam path of Heater and
Pipeline with Hydrogen Peroxide solution added with Ammonia.
SLIDE 15
Pre-Mounting Cleaning
- Chemical Cleaning of Pipelines in a bath of Hydrofluoric Acid
solution.
- Spent solution displacement.
- Chemical Passivation of Pipelines with Hydrogen Peroxide
solution added with ammonia.
- Air Blowing of Passivated pipelines for drying.
SLIDE 16
Main Turbine and BFP Drive Turbine Condenser Cleaning or Condenser Degreasing. STEP- I
- The demineralized water is heated upto 700c in the De-aerator
FST.
- The Chemical solution prepared in reagent preparation plant is
mixed with the hot water in the De-aerator FST.
SLIDE 17
- The hot solution is transferred to Condenser with the help of
temporary chemical cleaning pump through temporary pipelines connecting pump discharge header to the CEP discharge header and the cooling device sprayers of Condenser.
- Circulation is completed by bringing this solution from
condenser to Chemical Cleaning pump suction header through CEP suction header and temporary pipeline connection.
- Circulation is continued for 4 hrs.
- System is isolated after closing one temporary gate valve
provided in the circuit (refer to scheme.)
SLIDE 18
FST DEAERATOR AUX.STEAM CHEMICAL BP BP BP BP ACID CLEANING PUMPS CONDENSERS CEPS
SLIDE 19
STEP –II
- CEPs are charged from water side by opening suction valve
and through proper venting, keeping discharge valve in closed condition and suction strainer in position.
- Flushing started by alternately starting and stopping CEPs and
completing the circulation from CEP discharge to CEP suction line through recirculation line and condenser.
SLIDE 20
- Circulation is continued for 4 hrs.
- After cleaning the spent solution is pumped from condenser to
neutralizing basin.
- Water washing of Condenser started and continued for 4 hrs.
using the two circuits already described..
SLIDE 21
DEAERATOR FST AUX.STEAM CHEMICAL BP BP BP BP ACID CLEANING PUMPS CONDENSERS CEPS
SLIDE 22
Hydro-pneumatic Washing of Unit Circulating System with Demineralized Water and air. → Hydro-pneumatic washing of unit circulating system is carried
- ut step by step with simultaneous water and air supply.
→Demineralized water for washing is stored in the De-aerator FST and Condenser. →Hydropneumatic washing is declared completed if suspended matter content of the washing water reaches no more than 100mg/kg. →Hydro-pneumatic washing of unit circulating system is done using following four circuits.
SLIDE 23
CIRCUIT 1:
Circuit 1A De-aerator FST – TDBFP A booster pump suction line – BP strainers – Temporary header connecting the BP suction lines downstream of the strainers – Acid cleaning pumps – Temporary discharge header – Temporary lines to the discharge gate valves of four feed pumps – Feed lines to HPH – Bypass line of all HPH – HPH bypass lines – Water path of HPH 6,7,8 – Feed water line upto boiler feed control unit – Temporary discharge line to the circulating water line - De-aerator FST.
SLIDE 24
Circuit 1B De-aerator FST – TDBFP B booster pump suction line – BP strainers – Temporary header connecting the BP suction lines downstream of the strainers – Acid cleaning pumps – Temporary discharge header – Temporary lines to the discharge gate valves of four feed pumps – Feed lines to HPH – Bypass line of all HPH – HPH bypass lines – Water path of HPH 6,7,8 – Feed water line upto boiler feed control unit – Temporary discharge line to the circulating water line - De-aerator FST.
SLIDE 25
Circuit 1C De-aerator FST – MDBFP booster pump suction line – BP strainers – Temporary header connecting the BP suction lines downstream of the strainers – Acid cleaning pumps – Temporary discharge header – Temporary lines to the discharge gate valves of four feed pumps – Feed lines to HPH – Bypass line of all HPH – HPH bypass lines – Water path of HPH 6,7,8 – Feed water line upto boiler feed control unit – Temporary discharge line to the circulating water line - De-aerator FST.
SLIDE 26
Circuit 1D De-aerator FST – Booster pump suction line – BP strainers – Temporary header connecting the BP suction lines downstream of the strainers – Acid cleaning pumps – Temporary discharge header – Temporary lines to the discharge gate valves of TDBFP A – Feed lines to HPH – Bypass line of all HPH – HPH bypass lines – Water path
- f HPH 6,7,8 – Feed water line upto boiler feed control
unit – Temporary discharge line to the circulating water line - De-aerator FST.
SLIDE 27
Circuit 1E De-aerator FST – Booster pump suction line – BP strainers – Temporary header connecting the BP suction lines downstream of the strainers – Acid cleaning pumps – Temporary discharge header – Temporary lines to the discharge gate valves of TDBFP B – Feed lines to HPH – Bypass line of all HPH – HPH bypass lines – Water path of HPH 6,7,8 – Feed water line upto boiler feed control unit – Temporary discharge line to the circulating water line - De-aerator FST.
SLIDE 28
Circuit 1F De-aerator FST – Booster pump suction line – BP strainers – Temporary header connecting the BP suction lines downstream of the strainers – Acid cleaning pumps – Temporary discharge header – Temporary lines to the discharge gate valves of MDBFP A – Feed lines to HPH – Bypass line of all HPH – HPH bypass lines – Water path of HPH 6,7,8 – Feed water line upto boiler feed control unit – Temporary discharge line to the circulating water line - De-aerator FST.
SLIDE 29
Circuit 1G De-aerator FST – Booster pump suction line – BP strainers – Temporary header connecting the BP suction lines downstream of the strainers – Acid cleaning pumps – Temporary discharge header – Temporary lines to the discharge gate valves of MDBFP B – Feed lines to HPH – Bypass line of all HPH – HPH bypass lines – Water path of HPH 6,7,8 – Feed water line upto boiler feed control unit – Temporary discharge line to the circulating water line - De-aerator FST.
SLIDE 30
Circuit 1H De-aerator FST – Booster pump suction line – BP strainers – Temporary header connecting the BP suction lines downstream of the strainers – Acid cleaning pumps – Temporary discharge header – Temporary lines to the discharge gate valves of four feed pumps – Feed lines to HPH – 50 % bypass line of all HPH– Feed water line upto boiler feed control unit – Temporary discharge line to the circulating water line - De-aerator FST.
SLIDE 31
Circuit 1I De-aerator FST –Booster pump suction line – BP strainers – Temporary header connecting the BP suction lines downstream of the strainers – Acid cleaning pumps – Temporary discharge header – Temporary lines to the discharge gate valves of four feed pumps – Feed lines to HPH – 100 % bypass line of all HPH – Feed water line upto boiler feed control unit – Temporary discharge line to the circulating water line - De-aerator FST.
SLIDE 32
Circuit 1J De-aerator FST –Booster pump suction line – BP strainers – Temporary header connecting the BP suction lines downstream of the strainers – Acid cleaning pumps – Temporary discharge header – Temporary lines to the discharge gate valves of four feed pumps – Feed lines to HPH bypass line for 6A,7A,8A – Feed water line upto boiler feed control unit – Temporary discharge line to the circulating water line – De-aerator FST.
SLIDE 33
Circuit 1K De-aerator FST –Booster pump suction line – BP strainers – Temporary header connecting the BP suction lines downstream of the strainers – Acid cleaning pumps – Temporary discharge header – Temporary lines to the discharge gate valves of four feed pumps – Feed lines to HPH bypass line for 6B,7B,8B – Feed water line upto boiler feed control unit – Temporary discharge line to the circulating water line – De-aerator FST.
SLIDE 34
Circuit 1E De-aerator FST –Booster pump suction line – BP strainers – Temporary header connecting the BP suction lines downstream of the strainers – Acid cleaning pumps – Temporary discharge header – Temporary lines to the discharge gate valves of four feed pumps – Feed lines to HPH – Water path of HPH 6A,7A,8A – Feed water line upto boiler feed control unit – Temporary discharge line to the circulating water line – De-aerator FST.
SLIDE 35
Circuit 1L De-aerator FST –Booster pump suction line – BP strainers – Temporary header connecting the BP suction lines downstream of the strainers – Acid cleaning pumps – Temporary discharge header – Temporary lines to the discharge gate valves of four feed pumps – Feed lines to HPH – Water path of HPH 6B,7B,8B – Feed water line upto boiler feed control unit – Temporary discharge line to the circulating water line – De-aerator FST.
SLIDE 36
CIRCUIT 2: Circuit 2A Condenser – CEP suction lines – Acid cleaning pumps – CEP discharge header – Condensate line bypassing LPHs – line down stream of LPHs – Temporary discharge line to the circulating water system – De- aerator FST Circuit 2B Condenser – CEP suction lines – Acid cleaning pumps – CEP discharge header – Water side of LPHs – Line down stream of LPHs – Temporary discharge line to the circulating water system – De-aerator FST
SLIDE 37
CIRCUIT 3:
Circuit 3A Condenser – CEP suction lines – Acid cleaning pumps – CEP discharge header – Condensate line bypassing LPHs – Temporary header for water supply to the HPH steam space – Steam side of HPH 6A – HPH discharge line – Temporary discharge line to the circulating water system – De-aerator FST
SLIDE 38
Circuit 3B Condenser – CEP suction lines – Acid cleaning pumps – CEP discharge header – Condensate line bypassing LPHs – Temporary header for water supply to the HPH steam space – Steam side of HPH 6B – HPH discharge line – Temporary discharge line to the circulating water system – De-aerator FST
SLIDE 39
Circuit 3C Condenser – CEP suction lines – Acid cleaning pumps – CEP discharge header – Condensate line bypassing LPHs – Temporary header for water supply to the HPH steam space – Steam side of HPH 7A – HPH discharge line – Temporary discharge line to the circulating water system – De-aerator FST
SLIDE 40
Circuit 3D Condenser – CEP suction lines – Acid cleaning pumps – CEP discharge header – Condensate line bypassing LPHs – Temporary header for water supply to the HPH steam space – Steam side of HPH 7B – HPH discharge line – Temporary discharge line to the circulating water system – De-aerator FST
SLIDE 41
Circuit 3E Condenser – CEP suction lines – Acid cleaning pumps – CEP discharge header – Condensate line bypassing LPHs – Temporary header for water supply to the HPH steam space – Steam side of HPH 8A – HPH discharge line – Temporary discharge line to the circulating water system – De-aerator FST
SLIDE 42
Circuit 3F Condenser – CEP suction lines – Acid cleaning pumps – CEP discharge header – Condensate line bypassing LPHs – Temporary header for water supply to the HPH steam space – Steam side of HPH 8B – HPH discharge line – Temporary discharge line to the circulating water system – De-aerator FST
SLIDE 43
CIRCUIT 4:
Circuit 4A Condenser – CEP suction lines – Acid cleaning pumps – CEP discharge header – Condensate line bypassing LPHs – Temporary header for water supply to the LPH steam space – Steam side of LPH 1A – LPH discharge line – Temporary discharge line to the circulating water system – De-aerator FST
SLIDE 44
Circuit 4B Condenser – CEP suction lines – Acid cleaning pumps – CEP discharge header – Condensate line bypassing LPHs – Temporary header for water supply to the LPH steam space – Steam side of LPH 1B – LPH discharge line – Temporary discharge line to the circulating water system – De-aerator FST
SLIDE 45
Circuit 4C Condenser – CEP suction lines – Acid cleaning pumps – CEP discharge header – Condensate line bypassing LPHs – Temporary header for water supply to the LPH steam space – Steam side of LPH 2 – LPH discharge line – Temporary discharge line to the circulating water system – De-aerator FST
SLIDE 46
Circuit 4D Condenser – CEP suction lines – Acid cleaning pumps – CEP discharge header – Condensate line bypassing LPHs – Temporary header for water supply to the LPH steam space – Steam side of LPH 3 – LPH discharge line – Temporary discharge line to the circulating water system – De-aerator FST
SLIDE 47
Circuit 4E Condenser – CEP suction lines – Acid cleaning pumps – CEP discharge header – Condensate line bypassing LPHs – Temporary header for water supply to the LPH steam space – Steam side of LPH 4 – LPH discharge line – Temporary discharge line to the circulating water system – De-aerator FST
SLIDE 48 M M M M M
M
M
M M M
M
M
M
M M
M
M M
LPH-1A LPH-1B LPH-2 LPH-3 LPH-4
M M M
DRIP /P-A DRIP /P-B
M M M M
BP
MBP
M M M M M M M M M M M MAIN CONDENSER - 1 MAIN CONDENSER - 2 M M M M M MGSC CPU
M CEP-3 CEP-2 CEP-1 M HPH-6A HPH-7A HPH-8A M M M M M M M M M HPH-6B HPH-7B HPH-8B M M M M M M M M M M M M M M M M M TO ECO I/L SLIDE 49
BP
MBP
M M M M M M M M M M M MAIN CONDENSER - 1 MAIN CONDENSER - 2 M M M M M MGSC CPU
M CEP-3 CEP-2 CEP-1 M HPH-6A HPH-7A HPH-8A M M M M M M M M M HPH-6B HPH-7B HPH-8B M M M M M M M M M M MTO ECO I/L
SLIDE 50 M M
M
M
M M M
M
M
M
M M
M
M M
LPH-1A LPH-1B LPH-2 LPH-3 LPH-4
M M
BP
MBP
M M M M M M M M M MAIN CONDENSER - 1 MAIN CONDENSER - 2 M M M M M MCPU
M CEP-3 CEP-2 CEP-1 M M M M M M M M M M MGSC
M M M SLIDE 51 M M M M
BP
MBP
M M M M M M M M M M M MAIN CONDENSER - 1 MAIN CONDENSER - 2 M M M M M MGSC CPU
M CEP-3 CEP-2 CEP-1 M HPH-6A HPH-7A HPH-8A M M M M M M HPH-6B HPH-7B HPH-8B M M M M M M M M M M M M M M M TO ECO I/L SLIDE 52 M M M M
M
M
LPH-1A LPH-1B LPH-2 LPH-3 LPH-4
M M M
DRIP /P-A DRIP /P-B
M M
BP
MBP
M M M M M M M M M M M MAIN CONDENSER - 1 MAIN CONDENSER - 2 M M M M M MGSC CPU
M CEP-3 CEP-2 CEP-1 M M M M M M M M M SLIDE 53
ACID CLEANING: →Acid cleaning is made using the same four circuits on which water washing is made. To make closed circuit the de-aerator is included into the scheme, in which cleaning solution can be heated if required. →Reagents in liquid form, each by separate pipeline, are supplied from reagent preparation plant into suction pipeline
- f acid cleaning pump.
→Minimum Hydrofluoric acid solution temperature is 200C and
- ptimum temperature is 400 C
→Acid cleaning phase duration is 4-8 hours at temperature up to 400C →Hydrofluoric acid cleaning solution concentration is selected depending on ferric oxide quantity in the circuit to be washed.
SLIDE 54
CLEANING SOLUTION DISPLACEMENT: →Primary displacement of spent cleaning solution is carried out by compressed air from the compressor-house ; this allows saving of water for washing. →The final removal of solution is carried out with standard speed ; in drainable section – not less than 1m/s and in non- drainable section not less than 2m/s. Solution is removed from the circuits by hydraulic pneumatic method with water supply from condensers by acid cleaning pumps. →Acid cleaning is declared finished if discharge water conductivity reaches 20µs/cm.
SLIDE 55
PASSIVATION: →Passivation of acid cleaned surface is carried out with Hydrogen Peroxide solution added with ammonia. →Before passivation the acid cleaned surface is neutralized with the circulation of ammonia solution. →Passivation is carried out with demineralized water under the following conditions:
- Hydrogen Peroxide concentration is 0.02%.
- Ammonia Concentration is upto 0.8%.
- Solution temperature is 400C.
- Duration 4-6 hours.
- Solution flow velocity is 0.3 to 0.5 m/s
SLIDE 56