Port of Davisville Infrastructure Rehabilitation/Replacement Program February 2016 Port of Davisville RIs only Public Port One of the Top 10 auto import locations in North America 2015 sixth consecutive record breaking year A


  1. Port of Davisville Infrastructure Rehabilitation/Replacement Program February 2016

  2. Port of Davisville RI’s only Public Port • One of the Top 10 auto import locations in North America • 2015 sixth consecutive record breaking year • A record 193 ship calls in 2015 • 227,021 autos imported in 2015 • Additional 42,150 auto by rail and truck • The Port of Davisville now handles more than six times the volume of automobiles shipped there in 1996, a 547% increase 2015 NARRAGANSETT BAY • Port of Davisville represents nearly half of IMPORT VESSEL ARRIVALS Port of Davisville import vessel calls into Narragansett Bay Other RI Terminals and Ports 45% 55% 1

  3. Port of Davisville Economic Impact R/ECON Input-Output Model analysis of 2014 cargo activity: ● $333 million in business output ● Over 1,500 direct, indirect and induced jobs ● $97 million in household earnings ● $17 million in state taxes ● $10 million in local taxes SOURCE: Economic and Tax Effects on the Rhode Island Economy of Major Business Activity at the Port of Davisville in 2014, FXM Associates, November 4, 2015 2

  4. Port of Davisville – Pier 2 Pier 2 ● Constructed: 1956/1957 ● Type: Earth Filled Marginal Wharf ● Use: Public Port ● Design Life: 50 years PIER 2 ● Age: 60 years 3

  5. Port of Davisville Pier 2 – Rehabilitation Cost Pier 2: Rehabilitation $82 million (2015 $’s) 975 construction jobs resulting from this investment 4

  6. Port of Davisville - Pier 2 Rehabilitation • Phase 1: Engineering and Permitting $ 4,000,000 • Phase 2: Dredge East Berth $ 3,800,000 • Phase 3: Construct East Berth $16,100,000 5

  7. Port of Davisville - Pier 2 Rehabilitation Phase 4: Install New Sheet Pile South Side $37,800,000 Phase 5: Install New Sheet Pile East Side $20,300,000 Construction East Berth South Berth Construction 6

  8. Port of Davisville - Pier 2 Rehabilitation Estimated impact of Annual Inflation of 2.00% 2.00% 4.0400% 6.1208% 8.2432% 10.4081% 2016 2017 2018 2019 2020 2021 Total Design & Permitting of Pier 2 $4,000,000 $4,080,000 $4,080,000 Pier 2 Improvements Dredging $3,800,000 $4,032,590 $4,032,590 Pier 2 Extension $16,100,000 $17,085,449 $17,085,449 New Anchored HZ-M Bulkhead Pier 2 South Face $37,800,000 $40,915,936 $40,915,936 New Anchored HZ-M Bulkhead Pier 2 East Face $20,300,000 $22,412,840 $22,412,840 Total $82,000,000 $4,080,000 $0 $21,118,039 $40,915,936 $22,412,840 $88,526,815 7

  9. Port of Davisville - Pier 2 Rehabilitation Total Project Cost: ($90,000,000) Source of Funds: Proposed General Obligation Bond $70,000,000 *Kushner Approved Revenue Bond $20,000,000 * The revenue bond will be repaid exclusively by the QDC and port users. It will fund a portion of the port improvement initiative at no cost to state taxpayers. 8

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.