Planning Stage
1 of 39
Planning Stage 1 of 39 Project Life Cycle - Planning Stage - - PowerPoint PPT Presentation
Planning Stage 1 of 39 Project Life Cycle - Planning Stage Conceptualisation Planning Implementation Completion 2 Planning Stage Inputs Why plan? The planning process Objectives Work Breakdown Structure
1 of 39
2
Inputs Why plan? The planning process Objectives Work Breakdown Structure Estimating Scheduling Outputs
3
Project objectives & scope Stakeholders & requirements Constraints Success criteria Feasibility analysis & risk level Initial plans Scope of the planning stage
4
Signatures from senior management in project and
client organisations
Project manager also signs to confirm acceptance of
the next stage
5
6
Good planning will benefit the project Bad planning can add to cost of failure
7
8
Planning
an on-going process, not a stage iterative
Project plans are working documents Planning must be combined with
9
Plans demonstrate feasibility Identify general risks & constraints
Baseline plan
what, when and how things should be done what resources are required
10
Progress monitored against plans
Plans contain detail for future work
Plans provide a basis for final evaluation
11
12
13
Increase UK sales volume of ring binders by 5% by 30 June 2013
the objective is: specific and written down measurable “increase UK sales volume of ring binders by 5%” achievable by the staff concerned, agreed by those involved, aligned to the requirements of the organisation relevant to organisation’s sales targets, realistic in terms of outlets time-framed “by 30 June 2013”
14
the objective is: specific and written down measurable “reduce staff absenteeism in SE dept by 30%” achievable by the staff concerned, with health awareness courses, agreed by those involved, aligned to the requirements of the organisation relevant to the work of the organisation, realistic in terms of health care provision time-framed “by 31 December 2013”
15
the objective is: specific and written down measurable “hand in CC2005 assignment to UG Office” achievable by students concerned, with lectures and seminars, agreed by academic & admin staff, aligned to the requirements of the module relevant to the work of the module, realistic in terms of lecture schedule time-framed “by 10 May 2013”
16
ALL
17
Each work package broken down into a detailed list of
activities
Each activity broken down into individual tasks
18
19
20
Activity 1.1 Breakdown Task 1.1.1 Task 1.1.2 Task 1.1.3 Task 1.1.4 Activity 1.1
21
Project Breakdown: complete structure
Task 1.1.1 Task 1.1.2 Task 1.1.3 Task 1.1.4 Activity 1.1 Task 1.2.1 Task 1.2.2 Task 1.2.3 Activity 1.2 Task 1.3.1 Task 1.3.2 Activity 1.3 WP 1 WP 2 WP 3 Task 4.1.1 Task 4.1.2 Task 4.1.3 Activity 4.1 Task 4.2.1 Task 4.2.2 Task 4.2.3 Task 4.2.4 Task 4.2.5 Activity 4.2 WP 4 Complete Project
22
Functional grounds Responsibility Project phase Geographic location
23
Budget control Team management Skills 3rd party organisations
Reporting requirements
24
Civil
Plumbing Electrical
(Example from Burke, 1999, p.106)
25
Design Preparation of site and foundations Building Finishing and decorating
26
Be well defined Have a specification including:
Be agreed
27
An alternative starting point to WBS Identifies project products (deliverables) Details what must be produced
Products include:
technical management quality
Philosophy behind PRINCE
28
29
Quality of information available How far into the future... How well-defined is the work Experience of the estimator Time available to produce estimates Other (project specific) ‘risk’ factors
30
Requirements change over time
needs managing estimate revisions must follow immediately
Complete tasks/activities left out of plan
31
32
half the time needed by one person…
longer than 10 days
Important factors: communication and divisibility of work
(see Brooks, 1995)
33
Planning meals: people/resources/time
if there is enough food for 12 lunches
this would last one person every day for 12 days
(providing the food doesn’t go off!)
or two people every day for 6 days or four people every day for 3 days or 12 people for one day (a party!) but there is not enough for 14 people on one day,
and there is not enough for one person for 14 days this hasn’t included costs for storage, preparation, time for
preparation, freezing/thawing/cooking, effort in preparation (does it take 12 times longer to cook 12 meals than 1?), washing up, etc...
34
35
36
37
38
Burke, R (2003) Project Management: Planning and Control
Techniques, Wiley
Bentley C.(1997) PRINCE 2: A Practical Handbook, Butterworth-
Heinemann
Central Computer & Telecommunications Agency (1997) PRINCE 2:
An Outline, London: The Stationery Office
Field M & Keller L (1998) Project Management, International
Thomson Business Press
Brooks F. (1995) The Mythical Man-Month (Anniversary Edition),
Addison-Wesley
39