Performance Review July 2018 Safety Overview As of July 31, 2018 - - PowerPoint PPT Presentation
Performance Review July 2018 Safety Overview As of July 31, 2018 - - PowerPoint PPT Presentation
Performance Review July 2018 Safety Overview As of July 31, 2018 WRPS Tank Operations Contract has worked 7,630,194 hours One Recordable case in July: (539 days) without a Lost Time Workday Injury While loading equipment in the back of
2
Safety Overview
11 First Aid cases in July:
- Employee snagged thumb on a uni-
strut while working by farm causing a minor laceration
- While performing laundry duties,
employee felt pain in shoulder.
- Employee fell down and hit hand on
the fence causing abrasion.
- While transporting equipment by
handcart on uneven surfaces employee twisted knee causing strain.
- Employee lifted laundry bag causing
strain to lower back.
- Employee reported bite/sting on neck
causing irritation.
- Employee lifted boxes off of handcart
causing strain to abdomen.
- While walking employee felt an insect
bite on the neck causing irritation.
- Employee was adjusting chair and fell
to the floor causing pain to elbow, hip, knee and shoulder.
- Employee was wearing SCBA walking
down a hill on uneven terrain causing strain to knee.
- While walking employee felt an insect
bite on the neck causing irritation.
As of July 31, 2018 WRPS Tank Operations Contract has worked 7,630,194 hours (539 days) without a Lost Time Workday Injury and 197,133 hours (14 days) since the last Recordable case.
Total Recordable FY 2018 Cumulative Summary
October 1, 2017 through September 30, 2018
Days Away, Restricted Workdays
- r Transferred (DART)
FY 2018 Cumulative Summary
October 1, 2017 through September 30, 2018
0.09
12-month rolling rate: 0.11
DOE/EM Goal – 1.10
0.00
12-month rolling rate: 0.00
DOE/EM Goal – 0.60
One Recordable case in July:
- While loading equipment in the back
- f the van employee hit head on edge
- f hatchback causing laceration.
July 2018
Effective Corrective Action Tracking FY18 Status SV Improvement Focus
- Comprehensive schedule opportunity scope
list being monitored and tracked
- Overtime for High Priority Work
Non-labor effectiveness evaluations
- Critical Procurement Focus
- Implementation & Acceleration of FY19 Award
Resource availability
- Reprioritization of Critical Resources
- Posting of Critical Field Craft
Vapor REA for $20M
- Contract Mod Rec’d – PMB Target Aug-18
Management Topics
3
- Evolution and Transition of Waste Feed Delivery
- Capital disposition and alignment
- FY19 Plan Implemented this period
- PEMP renegotiation modification received this period
July 2018
Key Milestones
Complete To Go Will Miss Total MS % Complete % To Go
93 68 1 162 57.40% 42.60%
Current Month Change Control
4 July 2018
Performance Overview Current Month / Fiscal Year
5 July 2018 *OBS focus areas – detailed in subsequent slides
Performance Overview Cumulative / At Complete
6 July 2018 *OBS focus areas – detailed in subsequent slides
Management Forecast of Cost Performance
Schedule and Cost Performance Forecast
7 July 2018
CV declines by -$1,609k by FY End (from CTD)
____________________________________________________________________________________________________,______________________________________2L Production Ops -$2,102k 2T Chief Technology Office -$1,345k 2M Tank Farm Projects $1,562k
Forecast July BCWP vs. Actual July BCWP Missed by -$5,982k
_________________________________________________________________________________________________________________________________________2M Tank Farm Projects -$2,841k 2L Production Ops -$1,125k 2T CTO/Closure -$899k
CM Schedule Accuracy
72%
Discrete work only
Management Forecast of Schedule Performance
Carryover Funds Support 20 Operational Days
$50-$60M $43,625k
July 2018
Opportunities for Schedule Recovery
8
Expected Recovery $6-$16 M Opportunity $18 M
1 - most likely to recover 5 - least likely to recover
WBS L5 Title 5.01.04.01.64 - DST Transfer Pump Replacements OP 2-3 2,249 1 5.01.02.06.08 - ETF/LERF/TEDF Operations & Maintenance - OP 2-3 946 1 5.01.02.06.13 - Replace ETF Basin Covers 804 1 5.01.04.01.18 - DST In-Pit Heating 787 1 5.01.01.15.29 - AY-102 Rinse & Transfer - Phase III 654 1 5.01.04.01.91 - 242-A Evaporator Fire Alarm Panel Upgrades 594 1 5.03.02.06.10 - AP-105 Tank Farm Upgrades to Support DFLAW 581 1 Total 6,615 5.02.06.02.01 - A-Farm Infrastructure - Ventilation 1,247 2 Total 1,247 5.01.05.11.56 - Vapor Monitoring & Detection System Upgrades 2,839 3 5.02.08.04.04 - A/AX Infrastructure Installation 2,363 3 5.02.01.04.13 - Interim SX Barrier - South Construction 2,340 3 5.01.05.11.57 - Industrial Hygiene Trailer 799 3 Total 8,341 5.02.01.04.12 - Interim SX Barrier - North Construction 1,894 5 Total 1,894
Grand Total 18,097
Grand Total in $k 1-5 Ranking Top SV Recovery scopes in the remainder of FY18
Risk Program Health (July)
- Risk Management is averaging under 28 days for all 34+
register updates (time between register updates) (Figure 1)
- WRPS has maintained less than 21% total high risks
throughout FY18. Risk Management monitors the overall TOC risk profile to determine if risk mitigation strategies are effectively being developed for the highest level risks as a key component of improving the probability of mission success (figure 2) Current new registers being developed;
- TSCR (Tank Side Cesium Removal)
- Test Bed Initiative
- APO2A Jumper Repair
- Tank Farm Upgrades
- 2704 Fire Alarm Systems upgrades
- Maintenance Program Register
Current Risk Management program priorities;
- During the month of July, Risk Management assisted in
questions of DOE independent auditor team (CohnReznick) regarding the FY19 proposal.
- TBI register is being developed and going through a deep dive.
- Schedule Risk Analysis has started for Waste Feed Delivery
- Risk Management continues to hold smaller group training
classes for the EROMS database to assist and train risk
- wners, project managers, subject matter experts and project
controls members on the use and application of the system. Risks of Near Term Concern:
- P-B-1 might require replacement instead of repair (if repair
doesn’t work, possible 14 months to manufacture replacement)
- DST Transfers - Four DST transfers which were previously
scheduled in FY19 to support EC-11 and EC-12, will be rescheduled pending resolution of schedule dates for TBI and P-B-1 pump repair (or replacement).
- 222-S – Contract Transition Delays Upgrades
- 222-S – Lab Rad analysis resource availability
WRPS Risk Management
9 July 2018
Figure 2 Figure 1
Objective Measure
90 90 90 90 90 90 90 90 90 90 90 90 90 60 60 60 60 60 60 60 60 60 60 60 60 60
Performance Thresholds
45 45 45 45 45 45 45 45 45 45 45 45 45 25 15 15 45 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Goal 29 28 36 29 32 37 28 29 28 29 28 28 Declining Meets Exceeds To demonstrate the health of the risk program, the average age of project and program level risk registers are monitored as a guage of overall risk program activity and effectiveness. This metric helps ensure that the Risk Registers for TOC managed projects and programs are up-to-date. The Enterprise Risk and Opportunity Management procedure, TFC-PRJ-PC-C-13, requires that Program and Project Risk and Opportunity Registers be updated at least every 90 days. The average age in days of risk register from last update to the current date (end of calendar month) >90 Adverse ≤45
Performance Data
- Avg. Age in Days of Risk Register
>45 and ≤60 >60 and ≤90 10 20 30 40 50 60 70 80 90 100 Average Age in Days
- Avg. Age in Days of Risk Register
Objective Measure
0.45 0.45 0.45 0.45 0.45 0.45 0.45 0.45 0.45 0.45 0.45 0.45 0.45 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35
Performance Thresholds
0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.45 0.1 0.05 0.3 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Goal 130 124 126 133 138 130 139 146 148 152 150 148 703 680 688 689 726 734 743 756 745 778 729 721 18% 18% 18% 19% 19% 18% 19% 19% 20% 20% 21% 21% Declining Meets Exceeds Percentage of High Risks (Month) Number of Open Risks To monitor the overall TOC risk profile to determine if risk mitigation strategies are effectively being developed for the highest level risks as a key component of improving the probability of mission success. The percentage of currently characterized High Risks
- Vs. the Total number of Risks as a percentage.
>45% Adverse ≤30%
Performance Data
Number of High Risks >30 and ≤35% >35 and ≤45% 0% 10% 20% 30% 40% 50% 60% 70% 80% Percentage of High Risks Percentage of High Risks (Month)
Plant Status –PMs & CMs
10 July 2018
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Field Work Complete - CMs 40 43 32 46 39 60 48 39 31 31 Field Work Complete - PMs 589 628 473 554 653 645 566 511 426 516
100 200 300 400 500 600 700
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
FY18 Monthly Completed CMs & PMs
Indirect Pools
July 2018 11
(Over)/Under Summary: $6.9M Under July / $6.5M Under June
Fringe Rate (ABS & COS) ($1.7M) Over ABS (applied to Labor) $0.1M Under COS (applied to Labor) ($1.8M) Over COP Rate (applied to Labor) $2.3M Under G&A Rate (applied to Labor/Non-Labor) $6.3M Under
Total Net Debit to PMB $6.9M Under
FY18 (Over)/Under Forecast
(Over) = Credit to the Direct Field Work / Under = Cost Charge/Allocation to the Direct Field Work
Current Month Impacts:
- Reduction in labor base due to an increase in time taken off by employees.
- Reduction in base scope ~$12.1m offset by reduction in Indirect Pool.
Critical Needs List
12 July 2018
Waste Feed Delivery Summary
13 July 2018
Waste Feed Delivery Focus
Incorporating TSCR and Tank Farm Upgrade scope into the LAWPS Line Item project
- LAWPS Project scope will include
- Ramp down of the permanent cesium removal capability
- TSCR and associated infrastructure
- Waste feed transfer system to deliver feed to WTP
- Developing an integrated schedule to include 413.3B CD strategy
- Developing erratas to prior proposals, due in November align scope and finalize new baseline
- Revising the TSCR SDS to reflect incorporation into the LAWPS Line Item project
Accomplishments
LAWPS SDS endorsement by ORP TSCR SDS endorsement by ORP TBI – Draft Waste Incidental to Reprocessing (WIR) evaluation completed for ORP review
Challenges
- Resolution to Ecology’s position to regulate TSCR and LAWPS ventilation under RCRA
- Ecology’s willingness to grant temporary authorization to enable early start
- $393
- $7,815
- $118
- $1,736
0.94 0.95 1.02 0.99 1.11 0.80
July 2018
LA LAWPS Performance Revie iew
(WBS 5. 5.5)
Schedule Cost
14 Dollars Represented in Thousands
FY TCPI FYTD CPI CTD SPI CTD CPI FYTD SPI CM SPI
CTD Schedule Variance Total: -$1,618 P - LAWPS-S - Design Project Support
- $915
P - LAWPS-S South - Design
- $556
P - LAWPS-S - Technology Maturation
- $96
Cost Variance FYTD: $646 CTD: -$7,422 P - LAWPS - Design
- $992
- $6,728
P - LAWPS - Design Project Support $362
- $2,337
P - LAWPS-S South - Design $1,183 $1,183
EOY Forecast SV
Delta From Today
EOY Forecast CV
Delta From Today
Key Points
Biggest Threats/Risks Keys to Success
WDOE Desire to include HVAC System in RCRA Permit. Continue to support ORP in discussions/negotiations. Spent IX Column interim storage package requirements. Continue evaluation of requirements and alternatives. Permitting strategy for interim storage pad. Continue evaluation of requirements and alternatives.
- Completed 5th and final 45% Over-the-shoulder design reviews
- Continued progress towards conducting Formal 45% Design Review September 5th
& 6th
- Received approval of SDS from ORP
- Commenced proposal errata / addendum preparation to align LAWPS scope with
ORP Letter of Direction
- BCR-18-157 for LAWPS Expense to Capital Transition to be implemented for
August 2018 reporting
Biggest Threats/Risks Keys to Success
GFE doesn’t meet functional requirements CEES to perform simulant testing utilizing Laboratory validated simulant APT/WRPS/DOE integrated QA process and oversight during fabrication and FAT WIR Authorization is delayed HQ to remove public comment period from WIR reviews – or early public comment based on calculated DF values RCRA permit modification delay Temporary Authorization for early work
Test Bed Initiative
15 July 2018
Key Points: Schedule Recovery:
- GFE will include the waste processing equipment, i.e. filtration and IX.
- DOE is the DA for the GFE with WRPS support to the DA (Kris Thomas)
- WRPS has taken the lead in coordinating and organizing the multi-
performer / multi-contract project team through external IPT meetings and War Room efforts
- WRPS has completed numerous tasks including the following:
- Developed Tank Selection Report and received
- Completed Functions and Requirements and revision to F&R
- Drafted 1st WIR evaluation
- Developed schedule and optimized schedule
- Progressing on drafting necessary permits
- 30% Design Review
- Initial PrHA
- Proposal submitted to ORP 7/31/2018
- Project critical path is typical through design, fabrication, installation,
- perations with permitting and NEPA actions on critical path as well.
- Aggressive but realistic schedule in place, which does not meet
12/31/2018 desired date.
- Working opportunities to gain schedule acceleration.
2,000 Gallon Test Bed Initiative Gatepost Milestone Chart
2,000 Gallon Test Bed Initiative Milestones Responsible Party Forecast Finish WIR Evaluation Updated Based on AW-102 Sample Analytical Results WRPS 8/30/2018 Final Design Complete APT 10/25/2018 Temporary Authorization Approved DOE 11/13/2018 WIR Evaluation Approved DOE 12/4/2018 WIR Determination Approved DOE 12/20/2019 Fabrication and Factory Acceptance Testing Complete APT 12/27/2018 Equipment Delivered to Evaporator APT 1/2/2019 Equipment Installation Complete WRPS 2/7/2019 NEPA Documentation Approved DOE 2/11/2019 Testing Complete WRPS 2/11/2019 Declaration of Readiness to Operate WRPS 2/19/2019 Start of Waste Processing WRPS 2/20/2019 End of Waste Processing WRPS 2/26/2019 Totes Shipped to PFNW WRPS 3/15/2019 Complete Treatment of Mixed Low Level Waste APT 3/28/2019 WCS Provides Waste Profile Approval APT 4/29/2019 Treated MLLW Arrives at WSC APT 5/6/2019 Waste Disposed at WSC APT 5/9/2019
Extracted from TBI Working Schedule (8/13/2018)
$1,370
July 2018
$14,389
- $3,781
CT CTO/Closure an and In Interim Meas asures Performance Revie iew
Schedule Cost
16 Dollars Represented in Thousands
FY TCPI FYTD CPI CTD SPI CTD CPI FYTD SPI CM SPI
CTD Schedule Variance Total: -$5,151 Direct Push Characterization & Sampling
- $1,577
Waste Mgt Area C Performance Assessments
- $692
RCRA Closure Plan Updates
- $615
Cost Variance FYTD: $2,057 CTD: $15,448 Technology Development $0 $3,177 Technology Maturation & Analysis $1,313 $2,837 IDF Glass Testing $259 $2,254
EOY Forecast SV
Delta From Today
EOY Forecast CV
Delta From Today -$1,059
Key Points Schedule Recovery
- Complete WRPS and ORP legal reviews and incorporated comments; begin preparations to finalize
Technology & Innovation Roadmap; PBI 42.0.4 to be submitted in August upon finalizing roadmap.
- Issued TSCR technology maturation/testing plan ahead of schedule and submitted completion paperwork
for PBI 47.0.3.
- Completed Phase II testing associated with Mechanical Waste Gathering System alternate retrieval
technology and drafted, reviewed, and incorporated comments into the test report; PBI 42.0.9 to be submitted in August upon finalizing report.
- Complete review of the 100% design on the new sampling technique and incorporated comment on the
final design; PBI 42.0.5 to be submitted in August upon finalizing design.
- Design of the first of three panels for the TX Farm interim surface barrier is proceeding.
- Work is proceeding on Grout Testing and other WMA C closure activities.
- Developing responses to Ecology comments on the RCRA Tiers 2 and 3 Closure Plans.
- DOE O 435.1 WMA C WIR and PA public/NRC reviews are in progress.
- Regulatory Documentation schedule variance is due to Ecology comments that are
past due. Have started receiving and dispositioning the comments. Due to the significant number of comments, recovery is not expected this FY.
- ILAW Glass Testing is expected to recover a portion of lost schedule in the current
fiscal year, the remaining scope (Lysimeter studies) is expected to carryover to Q1
- f FY 2019.
Note: CTO related schedule is recovering as anticipated for the month and is expected to continue to recover most of the SV by the end of the FY18 Q4.
Biggest Threats / Risks Keys to Success
Path forward for Ecology review and finalization of WMA C closure documents is
- needed. A mutually acceptable regulatory
approach must be developed among Ecology, DOE, and WRPS to move forward with incremental closure of WMA C. Working with DOE and Ecology to develop acceptable path forward.
0.95 1.12 1.08 0.84 1.07 0.98
$512
- $13,006
$9,730
- $7,958
0.90 0.96 0.77 0.97 0.93 0.95
July 2018
Tan ank Far arms Projects Performance Revie iew
Schedule Cost
17 Dollars Represented in Thousands
FY TCPI FYTD CPI CTD SPI CTD CPI FYTD SPI CM SPI
CTD Schedule Variance Total: -$17,688 Tank Chemistry & Integrity
- $4,158
Tank Farm Upgrade Projects
- $7,177
Vadose Zone/ Interim Measures – SX Barrier
- $4,251
Cost Variance FYTD: -$9,051 CTD: -$13,518 Tank Chemistry & Integrity
- $623
$4,003 Tank Farm Upgrade Projects
- $2,378
- $7,414
Vadose Zone/Interim Measures – SX Barrier
- $6,740
- $6,609
EOY Forecast SV
Delta From Today
EOY Forecast CV
Delta From Today
Key Points
ISSUES
- Critical resources support to projects
- ARPA for execution of SX Barrier placement
ACCOMPLISHMENTS
- Completed AW-102 grab sampling to support Test Bed Initiative
- Received final shipment of removal equipment for AW-103 pump replacement
- Completed AZ-101 UT.
- Completed AZ-102 UT floor and vertical strip scans – Riser 89
- Completed In-Pit heater installation AN01A and AN06A
- Completed SS flow instruments electrical installations AY/AZ Farm
- Continued LERF Basin cover removal
Biggest Threats / Risks Keys to Success
Construction and plant forces resource availability Weekly critical resource allocation reviews and prioritization. Impact of change in mission to include Tank Side Cesium Removal and Test Bed Initiative Integration and prioritization for allocation of key resources.
CVAP Performance Revie iew
(WBS BS 5.1.5.2.11 & 5.1.5.11)
Schedule Cost
18 Dollars Represented in Thousands
FY TCPI FYTD CPI CTD SPI CTD CPI FYTD SPI CM SPI
CTD Schedule Variance Total: -$5,375 Vapor Monitoring & Detection System Upgrades
- $3,983
Industrial Hygiene Trailer
- $799
Chemical Vapor Engineered Control Upgrades
- $598
Cost Variance FYTD: -$319 CTD: $70 New Vapor Detection Technologies
- $756
- $1,912
Vapor Monitoring & Detection System Upgrades
- $630
- $1,578
Strobic Air Upgrade $1,068 $1,118
EOY Forecast SV
Delta From Today
EOY Forecast CV
Delta From Today
Key Points
- PA System Field Work – U complex completed & kicked off B
complex
- Completed first Strobic Air equipment mockup test
- Received short-lead calibration gases for AP stack monitor
- 10-wide IH Trailer site prep completed
- Released AX-farm Stack Monitor Final Design
- Completed 222-S 4S Renovation
Biggest Threats / Risks Keys to Success
Critical Resource Availability (Plant & Construction Forces) Integration & prioritization for allocation of key resources Consistent vendor support for vapor monitoring procurements Timely delivery of stack monitors & calibration gases AW Stack Permitting Ecology Approval for Authorization Results of QRA may change boundaries Vapor Monitoring & Detection System equipment turnover to
- perations
July 2018
$1,051
$1,121
$3,089
- $2,286
0.99 1.11 1.00 0.95 0.96 1.19
CVAP Da Dashboard
19
Biggest Threats / Risks Keys to Success
Schedule impacts due to several factors have resulted in retrieval legal milestones being in jeopardy: CD D-16B-2 (Complete 9 tanks by 31 March 2024) and TPA M-045-15 (Complete A-103 by 30 Sept. 2022)
- DOE notified the State of Washington that CD-D-16B-2 is in jeopardy due to
vapor impacts
- Funding priority placed on A/AX construction
- Retaining core operations team proficiency for AX retrieval readiness
- Implementation of APR use in AX farm will significantly improve
efficiency/schedule performance Washington Department of Ecology’s recent interpretation on tank ventilation air permitting requirements cannot be met with the current generation of tank exhauster systems
- Request to revise the AX Farm air permit needed to support retrieval was
submitted to ECY February 23, 2016
- ECY’s position is closely associated with the tank vapor litigation
- Work closely with WRPS and DOE legal to negotiate solution
Costs of A/AX retrieval system construction have increased due to several factors
- Implementation of APR use in AX farm will significantly improve efficiency/cost
performance
- Redesign of waste retrieval systems to simplify construction and reduce costs
- Complete a cost growth drivers analysis
There is a shortage of key field labor (NCOs, HPTs, IHTs, construction crafts) due to attrition, site-wide bump-and-roll, regional competition for skilled labor
- Coordination with CHPRC to pick up labor from any future RIF
- Early forecasting of construction labor needs to support contractor recruiting
efforts
- Expedited worker training for field deployment
Deployment of new retrieval technologies to improve efficiency and strengthen DOE support for retrieval
- Coordination with CTO
- Tech transfer from SRR (crawlers, sampling systems, mixer pumps)
- Tech transfer from heavy construction/mining industry (dome coring,
mechanical waste gathering)
$529
- $31,088
$3,599
- $2,153
0.97 1.02 0.99 0.99 0.90 1.06
July 2018
SST Retrie ievals ls Performance Review
Schedule Cost
20 Dollars Represented in Thousands
FY TCPI FYTD CPI CTD SPI CTD CPI FYTD SPI CM SPI
CTD Schedule Variance Total: -$5,752 C-Farm Retrievals $225 A/AX Retrievals
- $5,323
AY-102 Retrievals
- $654
Cost Variance FYTD: -$903 CTD: -$31,617 C-Farm Retrievals $6,103
- $5,052
A/AX Retrievals
- $8,405
- $33,900
AY-102 Retrievals $1,375 $7,311
EOY Forecast SV
Delta From Today
EOY Forecast CV
Delta From Today
Key Points
- Completed AX-101 & AX-103 equipment removal pit cleanout – AX03A
- Completed riser investigations for A-103 & A-104
- Completed install of water/chemical piping – all sections complete
- Completed isolation & layup of POR107 exhauster and POR357 raw
water skid
- Completed 1st half of shielding install along HIHTL route between POR
497 & POR412
- Completed removal and disposition of 12 interim stabilization
HIHTLs
- Completed disconnects HIHTL/cap HIHTL ends for C-105 to
POR104
- $2,102
$6,230
$1,841
- $1,660
0.81 1.01 0.95 1.00 0.97 1.42
July 2018
Production Operations Performance Review
Schedule Cost
21 Dollars Represented in Thousands
FY TCPI FYTD CPI CTD SPI CTD CPI FYTD SPI CM SPI
CTD Schedule Variance Total: -$3,501 ETF/LERF/TEDF Operations & Maintenance - OP 2-3
- $2,022
222-S HVAC - Vent Supply & Exhaust Fan Rplmnt
- $429
UX-302A Catch Tank Pumping FY18
- $259
Cost Variance FYTD: -$6,797 CTD: $8,332 Production Operations Support Services $0
- $11,807
Production Operations Farms AN/AP/B/BX/BY/C
$0 $6,852 Production Operations Central Shift Office $0
- $6,206
EOY Forecast SV
Delta From Today
EOY Forecast CV
Delta From Today
Key Points
- PB-1 Pump Failure – Realized Risk “242AE-0034-R” impacted achieving the full
WVR of 130,000 required to meet PBI 37.0.1.2 “242-A Evaporator Campaign WVR 130,000”.
Biggest Threats / Risks Keys to Success
Aging Equipment: ETF Systems, 242-A Systems, Transfer Pumps Adequate Spares, PMs, and Planned Upgrades PM/CM Backlog Reduction Adequate resource availability Adequate PMs, Spare Parts Inventory Critical Resource Review FY19/20 Planning Integration & prioritization for allocation of key resources Assess Skill Mix to FY19/FY20 Scope HAMTC MOA - Downgrade Respiratory Equip Requirement Field implementation of cartridges following 3rd Party Review PFP D&D boundary controls impact TOC execution Close coordination with CHPRC/DOE on response actions at PFP to minimize impacts 222-S and ETF Readiness to support DFLAW FY19/FY20 Proposal
- July Significant Accomplishments:
Completed the second Liquid Effluent Retention Facility (LERF) Campaign of FY18 reducing the LERF inventory by 1,000,000 Gallons in support of PBI-37.0.3.2. Completed the disposition of the remaining 6 RCE items for a total of 10 in support
- f PBI-40.0.3.
Completed installation of the Gas Chromatograph/Mass Spectrometer in support of PBI-38.0.2.3.