Paldiski nuclear site past, present and future Ivo Tatrik - - PowerPoint PPT Presentation

paldiski nuclear site past present and future
SMART_READER_LITE
LIVE PREVIEW

Paldiski nuclear site past, present and future Ivo Tatrik - - PowerPoint PPT Presentation

Paldiski nuclear site past, present and future Ivo Tatrik ivo.tatrik@alara.ee Status of A.L.A.R.A. Estonian state owned radioactive waste management agency Established 1995 for decommission and clean up of Former Nuclear Submarine


slide-1
SLIDE 1

Paldiski nuclear site – past, present and future

Ivo Tatrik

ivo.tatrik@alara.ee

slide-2
SLIDE 2

Status of A.L.A.R.A.

  • Estonian state owned radioactive waste

management agency

  • Established 1995 for decommission and clean

up of Former Nuclear Submarine Training centre in Paldiski

  • Operates Interim Storage in Paldiski and is

involved with decommissioning of Tammiku near surface disposal facility

  • Emergency response for orphan sources
slide-3
SLIDE 3

Paldiski site Tammiku disposal site

Radioactive waste storage facilities in Estonia

slide-4
SLIDE 4

Paldiski - history

slide-5
SLIDE 5

Paldiski site – history

Main Technological Building was erected 1960-1963

Unit 1 Unit 2 Thermal power 70 MW 90 MW Reactor type PWR Enrichment of fuel (in 235U) 20 % First criticality 1968 1983 Shut down 1989 Refuelling 1980 never Operating time 20 821 h5 333 h Fuel removed and sent back to Russia 1995

slide-6
SLIDE 6

Paldiski site – history (2)

 The

reactors are defueled, all the systems components, pipelines and tanks has been drained;

 High-pressure gas and air has been removed from

cylinders and systems of the reactor compartments;

 Reactor compartments are welded and there is no

access.

slide-7
SLIDE 7

Paldiski site – history (3)

 About 70 m3 concrete was poured inside RC;  Concrete sarcophagus around reactor compartments

were erected;

Air drying and monitoring system were installed.

slide-8
SLIDE 8

Paldiski site – history (4)

  • Decision about deferred decommissioning for 50 years

was made 2001 in order to wait until main dose contributors decay;

  • Extensive

works were held between 1995-2008 to prepare site for safe storage until 2039 including:

  • decommissioning of solid and liquid waste storages;
  • removal of auxiliary systems of reactors;
  • removal of underground contaminated piping's (3 km);
  • decontamination and demolition of auxiliary buildings.
  • Radioactive waste raised from decommissioning process

were packed and stored in interim storage.

slide-9
SLIDE 9

Paldiski site – history (5)

slide-10
SLIDE 10

Paldsiki site - today

slide-11
SLIDE 11

Paldiski site – today (2)

  • Reactors are stored safely;
  • Both

reactors and environment monitoring programs are active;

  • Reactors

program:

  • n-line

alpha and beta aerosols, gamma dose rate;

  • Environmental

program: water, grass and ground – 3H, 137Cs, 60Co, 90Sr

slide-12
SLIDE 12

Paldiski site – today (3)

slide-13
SLIDE 13

Paldiski site – future

  • Reactors will be dismantled after 50 years decay
  • f main dose contributors (Co-60);
  • Decommissioning will start 2039;
  • Before

decommissioning final disposal for radioactive waste will be built;

  • Preliminary

studies for decommissioning

  • f

reactors and establishing

  • f

repository for radioactive waste were conducted 2014-2015.

slide-14
SLIDE 14

Paldiski site – future (2)

Decommissioning outcomes:

  • Reactor compartments will be cut in small pieces

to fit in standard containers;

  • Reactors vessels will be disposed as whole,

without cutting, in special containers;

  • There will be 3 types of waste:

a) low level radioactive waste (LLW); b) Intermediate level waste (ILW); c) free released waste.

slide-15
SLIDE 15

Paldiski site - future (3)

Final disposal outcomes:

  • Disposal volumes: LLW – 2100 m3;

ILW – 900 m3.

  • 89% of waste is legacy waste
  • There will be need for 2 type of disposal

facilities: A) near surface facility; B) shaft type facility.

slide-16
SLIDE 16

Surface repository concept (1)

  • Ferro-concrete vault with wall thickness 40 cm;
  • Dimensions: length 14 m, width 12,5 m and height 6 m;
  • 2 sections side by side;
  • After filling each layer, all voids between packages will be

backfilled with concrete;

  • Similar repositories existing in France, Spain etc.
slide-17
SLIDE 17

Surface repository concept (2)

Disposal packages (existing):

  • concrete containers (fits also for intermediate depth repository);
  • ISO containers;
  • 200 l drums;
  • control rod containers.
slide-18
SLIDE 18

Intermediate depth repository concept (1)

  • Shaft outer diameter 10,4 m.
  • Depth 50 m, waste emplacement

depth 30-50 m (1400 m3).

  • Shaft is lined with pre-fabricated

ferro-concrete elements.

  • Wall thickness 50 cm.
  • Waste

types: LL-LLW and ILW (sealed sources,

226Ra

contaminated materials, reactor vessels as whole, biological shield tanks).

  • Backfilled with concrete.
  • Similar pilot repositories existing or

planned to build in Finland, Sweden, South Korea, Slovenia and Russia.

slide-19
SLIDE 19

Preliminary site selection (1)

  • This was only first step in site selection process and aim was to

map possible suitable areas. Site has to accommodate both type of repositories.

  • Based on existing geological, hydrogeological and social data

and international experience 3 sites/areas were selected.

  • From experts point of view current Paldiski site or it’s vicinity is

the most suitable area for final disposal. Geological and hydro geological conditions of Paldiskis are equal to other sites but waste transportation, infrastructure and social aspects are by far the best ones.

slide-20
SLIDE 20

Preliminary site selection (2)

slide-21
SLIDE 21

Costs and political decisions

  • Whole program cost (decommissioning + final disposal) about 90

million euro.

  • Site selection, design and construction, management of existing

waste and licensing process cost about 45 million euro (~50%).

  • “0 option” cost may rise up to 50 million euro in the future.
  • Specific studies as part of Environmental Impact Assessment for the

establishment of a radioactive waste repository will start at 2018.

  • Decision by Government was made April 28, 2016 that Ministry of

Economic Affairs and Communications will be the responsible authority who arrange radioactive waste storage and disposal activities in Estonia. It was fixed in new Radiation Act adopted by the Parliament on 8 of June 2016.

slide-22
SLIDE 22

Thank You for attention!