overview of the sps llrf upgrade
play

Overview of the SPS LLRF upgrade Gregoire Hagmann (CERN) Mattia - PowerPoint PPT Presentation

Overview of the SPS LLRF upgrade Gregoire Hagmann (CERN) Mattia Rizzi (CERN) Philippe Baudrenghien (CERN) Javier Serrano (CERN) Javier Galindo (CERN, UPC) Lorenz Schmid (CERN) Wolgang Hofle (CERN) Arthur Spierer (CERN) Gerd Kotzian (CERN)


  1. Overview of the SPS LLRF upgrade Gregoire Hagmann (CERN) Mattia Rizzi (CERN) Philippe Baudrenghien (CERN) Javier Serrano (CERN) Javier Galindo (CERN, UPC) Lorenz Schmid (CERN) Wolgang Hofle (CERN) Arthur Spierer (CERN) Gerd Kotzian (CERN) Tomasz Wlostowski (CERN) Fermilab - slip-stacking 2 April 2018

  2. CERN Accelerators Complex Fig1 - CERN Accelerators Complex Fermilab - slip-stacking 3 April 2018

  3. SPS RF Upgrade 2019-2020 (LS2) High Lumi LHC Beam requirements • Proton [1] : Doubling intensity → 2.5·10 11 p+/bunch • • Ions [2] : 50ns bunch spacing → slip stacking • long injection plateau (~40s) → low noise • 100ns Courtesy T. Argyropoulos 100ns Main limitations • Beam-loading V RF =1MV, ~2MV beam induced • • Longitudinal instabilities (impedance) 50ns Fig2 – Ions Slip-stacking [3] Fermilab - slip-stacking 4 April 2018

  4. SPS RF Upgrade 2019-2020 (LS2) RF systems : • 4x 200MHz cavity → 6 cavities • 2x 800MHz cavity LS2 Fig2 - SPS RF systems Fig3 – SPS Power upgrade Fermilab - slip-stacking 5 April 2018

  5. SPS 200MHz Cavities 4 Travelling wave cavities (TWC200) → Splitted into 6 cavities after LS2 (Better compromise with beam loading & Cavity Voltage) Drift tubes structure Fig4 – SPS TWC200 Fermilab - slip-stacking 6 April 2018

  6. SPS 800MHz Cavities 2x 800 MHz Travelling wave cavities (Tunnel) 4x 60kW IOT amplifiers per cavity (Surface) Center freq 800.888MHz Phase advance per cell π /2 Group velocity v g /c +0.035 Cell length 93.5 mm Total length L (37 cells) 3.460 m Series impedance R 2 0.647 M Ω /m 2 Disc-loaded structure "## ≅ 𝑊 %## 𝑊 10 Fig5 – SPS TWC800 LHC proton beam (2-3·10 10 protons/bunch) unstable without 800MHz system Fermilab - slip-stacking 7 April 2018

  7. SPS 800MHz Cavity Voltage Voltage created by the generator Voltage created by the beam Zeros at ±3.15MHz Fig6 – SPS TWC800 Impedance 2 ⎡ ⎤ τ τ ⎛ ⎞ ⎛ ⎞ sin sin ⎢ ⎥ 2 Z R L R sin ⎜ ⎟ ⎜ ⎟ τ − τ 2 2 V : Cavity voltage 0 2 2 V L I 2 j I = − ⎢ − ⎥ ⎜ ⎟ ⎜ ⎟ RF b 2 2 8 τ τ τ ⎢ ⎥ ⎜ ⎟ ⎜ ⎟ 2 ⎢ 2 ⎥ ⎝ ⎠ ⎝ ⎠ ⎣ ⎦ v L ⎛ ⎞ 𝜐 : Total phase slip for ultra relativistic p+ g 1 τ = − Δ ω ⎜ ⎟ v v ⎝ ⎠ g Fermilab - slip-stacking 8 April 2018

  8. SPS 800MHz Vector Sum NWA Artefact! 2 MHz Mag [10dB/div] Fig7 – RF Combiner Freq [Hz] Fig8 – Vector Sum response Fermilab - slip-stacking 9 April 2018

  9. SPS LLRF Upgrade Fig9 - Current SPS BeamControl Systems Fermilab - slip-stacking 10 April 2018

  10. SPS LLRF Upgrade Current system : NIM, Custom 6U Europa crate, VME • Mostly analog • Some designs from 1970s • Only electronics for 4 cavities at 200MHz • • (6 cavities installed after LS2) Lack of control • • No cycle-cycle settings (PPM) • No remote control, no built-in diagnostic • Very time-consuming setting-up Fig10 - Current SPS 200MHz RF feedbacks Upgrade foreseen in LS2 (2019-2020) Beam loading compensation MUST be improved to cope with 2x I BEAM (HiLumi LHC) • Bunch per Bunch Beam Phase & Radial position measurement → 5-10GSPS • Fixed-frequency acceleration (FFA) for ion acceleration → FPGA • Fixed-frequency sampling clock (lower noise) → COTS • Deterministic serial link for RF frequency distribution → White-Rabbit • Momentum slip-stacking for 50ns ion bunch spacing, → SoC (FPGA+ARM, eg: ZYNQ) • Fermilab - slip-stacking 11 April 2018

  11. SPS LLRF Architecture MTCA VME MTCA MTCA Fig11 – SPS LLRF Architecture Fermilab - slip-stacking 12 April 2018

  12. SPS LLRF 200MHz cavity Controller DS8VM1 (Desy/Struck) CERN design Fclk=125/250 MHz SIS8300-KU Fig12 – SPS 200MHz Cavity Controller (Direct sampling) (Desy/Struck) Fermilab - slip-stacking 13 April 2018

  13. SPS LLRF 200MHz cavity Controller Polar loop: • TX noise • Open loop phase • Gain linearity DS8VM1 (Desy/Struck) CERN design Fclk=125/250 MHz SIS8300-KU Fig13 – SPS 200MHz Cavity Controller (Direct sampling) (Desy/Struck) Fermilab - slip-stacking 14 April 2018

  14. SPS LLRF 200MHz cavity Controller RF Feedback • IQ feedback • Transient beam loading (Frev) • Impedance reduction at synchrotron sidebands (fs, 2·fs) DS8VM1 (Desy/Struck) CERN design Fclk=125/250 MHz SIS8300-KU Fig14 – SPS 200MHz Cavity Controller (Direct sampling) (Desy/Struck) Fermilab - slip-stacking 15 April 2018

  15. SPS LLRF Clock Generation/Distribution Fixed-frequency sampling Big paradigm change for CERN • synchrotrons Simplify clocking scheme • Better noise performance (clock) • Higher complexity in signal • processing for bunch synchronous processing White-rabbit support Reconstruction of sampling clock • from White-Rabbit Aim for <130dBc/Hz • (from 100Hz offset range) Scalable system • LLRF Backplane (Desy) compatible Fig15: eRTM for SPS LLRF (Courtesy Mattia Rizzi) Fermilab - slip-stacking 16 April 2018

  16. SPS LLRF Beam control Beam based loops B-field reception (White-rabbit) • RF freq calculation (FPU) • RF freq distribution (White-rabbit) • Synchro Loop • Phase loop • Radial loop • Cogging /Rephasing (extr. to LHC) • Slip stacking (Ions 50ns) • AMC: FMC Carrier, 2x FMC (HPC) • SoC (FPGA+ARM) • White-Rabbit (2x) • MTCA.4 • RTM : Fig16: Beam control in MTCA.4 (Courtesy A. Spierer) 4x SFP+, 3xQSFP+ • MTCA.4.1 (optional) • Fermilab - slip-stacking 17 April 2018

  17. SPS LLRF Beam Phase, Radial Position, Intensity • Signals received from beam position monitors typically cover several GHz • SPS RF frequency: 200 MHz → bunch spacing 5 ns • Direct sampling of beam signals with fixed sampling clock at >> GSPS • Beam synchronous feature extraction in digital • Beam instantaneous frequencies received via WR link • System clocks are deterministic for every cycle (“absolute time”, based on WR) Hardware Parameters: • Input channels ≥2 • Sampling rate ≥ 5 GSPS • Analog BW ≥ 1 GHz • Vertical Res. ≥ 8 bits • Data output 200 MSPS Fig17: Beam phase, Radial pos, Intensity • Clocks derived from WR (125 MHz) (Courtesy G. Kotzian) Fermilab - slip-stacking 18 April 2018

  18. SPS LLRF MTCA.4.1 Equipment MTCA 9U Crate MCH (crate controller) Fig18: MCTA.4.1, 19’’, 9U (Pentair GmbH, N.A.T. GmbH) RF backplane Fig19: MCH (N.A.T. GmbH) Fig20: NAT-LLRF-Backplane (DESY, N.A.T. GmbH) Fermilab - slip-stacking 19 April 2018

  19. CERN SPS-LIU Schedule We are here Beam for physics Long Shutdown Long Shutdown Commissioning Commissioning Operation Operation Technical Stop Technical Stop Fig21: SPS-LIU Master plan • Q1 2018: MTCA Cavity controller tests on 200MHz cavity • Q2/Q3 2018: Prototype HW for Beam control (FMC carrier) MTCA HW for Beam phase/Intensity measurement • End 2018: CERN Accelerator complex stop → Long Shutdown 2 • 2019-2020 : LLRF Upgrade • Q4 2020 : LLRF commissioning • Q1/Q2 2021: Beam commissioning & Run 3 0.55A DC → 1.1A DC (HiLumi LHC) Fermilab - slip-stacking 20 April 2018

  20. SPS LLRF 200MHz cavity Controller DS8VM1 (Desy/Struck) CERN design Fclk=125/250 MHz SIS8300-KU Fig22 – SPS 200MHz Cavity Controller (Direct sampling) (Desy/Struck) Fermilab - slip-stacking 21 April 2018

  21. SPS LLRF 200MHz cavity Controller Fig23 – Cavity Controller, FPGA processing Fermilab - slip-stacking 22 April 2018

  22. SPS LLRF 200MHz cavity Controller 𝑐 # + 𝑐 2 3 𝑎 56 𝐼 *+,- = 𝐻 1 + 𝑏 # 3 𝑎 56 + 𝑏 2 3 𝑎 5%6 One Turn delay feedback Fig24 – One Turn Delay feedback with triple comb Fermilab - slip-stacking 23 April 2018

  23. SPS LLRF 200MHz cavity Controller MIMO feedback Fig25 – MIMO RF Feedback (3 cavities) Fermilab - slip-stacking 24 April 2018

  24. SPS LLRF 200MHz cavity Controller PCIE Gen3 x4 DDR Memory WR Link (SFP) SPI/I2C (AD9510, AD9268, etc). ADC/DAC Raw data AXI4 Full, 512 bits, 125 MHz Fig26 – SIS8300 Firmware ( Courtesy T. Wlostowski ) AXI4 Lite, 32 bits, 62.5 MHz 25 Fermilab - slip-stacking April 2018

  25. SPS LLRF 200MHz cavity Controller IF processing to be studied (Down-converter) DWC8VM1 (Desy/Struck) CERN design Fclk=125/250 MHz SIS8300-KU Fig27 – SPS 200MHz Cavity Controller (Down converter) (Desy/Struck) Fermilab - slip-stacking 26 April 2018

  26. References [1] J. Coupard & al. LHC INJECTOR UPGRADE – Technical Design Report – Volume I: Protons, CERN-ACC-2014-0337, 15.12.2017 [2] J. Coupard & al. LHC INJECTOR UPGRADE – Technical Design Report – Volume II: Ions, CERN-ACC-2016-0041, 01.04.2016 [3] T. Argyropoulos, MOMENTUM SLIP-STACKING OF THE I-LHC BEAM IN THE SPS, talk at LIU-SPS BD WG, CERN, 27.02.2014 [4] G. Hagmann & al., SPS LLRF Upgrade project, LLRF Workshop 2017, Barcelona, Spain, Poster P-9 Fermilab - slip-stacking 27 April 2018

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend