LLRF Tests in the FEL and CEBAF with the Cornell Digital LLRF System
JLAB: C. Grenoble, K. Davis, A. Hofler
- C. Hovater, T. Plawski, E. Pozdeyev, and T. Powers
Cornell: Sergey Belomestnykh, Roger Kaplan, and Matthias Liepe
LLRF Tests in the FEL and CEBAF with the Cornell Digital LLRF System - - PowerPoint PPT Presentation
LLRF Tests in the FEL and CEBAF with the Cornell Digital LLRF System JLAB: C. Grenoble, K. Davis, A. Hofler C. Hovater, T. Plawski, E. Pozdeyev, and T. Powers Cornell: Sergey Belomestnykh, Roger Kaplan, and Matthias Liepe JLAB-Cornell
JLAB: C. Grenoble, K. Davis, A. Hofler
Cornell: Sergey Belomestnykh, Roger Kaplan, and Matthias Liepe
performance and RF control systems: FY04 ($75K) and FY05($50K) The second “First Generation Upgrade CM” (known as FEL-3) will be used as a test bed to benchmark the lessons learned from SL-21. These changes include: 1) doubling of the cavity cooling, and 2) doubling of the waveguide
will also be tested. Risk Reduction: Reduction in technical risk through validation of design features the high-performance cryomodules need for system cost minimization; cost and schedule risk are also reduced. Deliverable: Benchmark of 12 GeV specifications for RF and cryogenic performance, and component testing of RF control system prototypes. Completion date: 28-Feb-05
Power Amplifier (klystron, tetrode etc.) Reflected Power Forward Power Superconducting Cavity Waveguide Coupler RF Controls
Master Reference Control System Interface
Field Probe Signal
LLRF System in VME Crate System Clock Quadrature Modulator
CMK-705s DC Block ZFL-500HLN LO 1485.1 MHz 20 dBm A TTN TBD RF 1497 MHz 20 dBm Max 17 dBm
15 dB A TTN
550 MHz LPFDC Block ZFL-500HLN A TTN TBD RF 1497 MHz 20 dBm Max Forward Power
15 dB A TTN
550 MHz LPFDC Block ZFL-500HLN A TTN TBD RF 1497 MHz 20 dBm Max Reflected Power
15 dB A TTN 6 dB Directional Coupler 3-W ay Divider ZFM-2000 ZFM-2000
1497 MHz BPFDC Block ZFL-2000 A TTN TBD IF 11.9 MHz 0 dBm Max Reference 0 dBm 15 dB A TTN ZFM-2000 IF 11.9 MHz IF 11.9 MHz IF 11.9 MHz RF 1497 MHz
Cornell LLRF FEL Zone 03
LLRF System VME Crate Quadrature Modulator Transceiver System Clock & Synthesizer
Blue: JLAB Supplied
controller
Phase: ~ 0.02 degrees rms. (Required 0.24 degrees rms.) Amplitude: ~ 3 x 10-4 rms. (Required 4.5 x 10-4 rms.)
algorithm)
0 to 12 MV/m in ~ 80 ms using Piezo Tuner (PZT)
algorithm)
Recovered cavity from 30 kHz away from nominal 1497 MHz
LLRF system controlled field to required stability
0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0
200
Detuning (Hz) E n e r g y C o n te n t ( N o r m a liz e d ) CEBAF 6 GeV CEBAF Upgrade
107) if KL = 2 then the frequency deflection at 20 MV/m (the required gradient) would be 800 Hz. This is greater than 10 cavity bandwidths away from nominal 1497 MHz!
need twice the power to operate, it is
especially for quick cavity recovery.
Recovery test: 0 to 12 MV/m
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0
0.000 0.020 0.040 0.060 0.080 0.100 0.120 0.140 0.160
time [sec] gradient [MV/m] phase gradient Pforward
High Q/ Recovery test 0.00 2.00 4.00 6.00 8.00 10.00 12.00 14.00 0.5 1 1.5 2 2.5 3 3.5 4 4.5 time [sec] gradient [MV/m] gradient
Note: there was no electronic feedback on and cavity QL was ~ 1x108!
Cavity Gradient PZT Turned on
Amplitude: ~ 2x10-4 rms. Phase: < ~ 0.05 degrees rms.
susceptible to the background microphonics.
in recirculated mode.
Operation at QL’s of 2x107 and 1.2x108 Phasing +/-40 degrees off crest
Helpful assistance from the CEBAF & FEL operations staff and beam time from Nuclear Physics made these tests possible