State Highway 19 Improvements
(Beginning 5 Miles East of US-81, Extending East 8.35 Miles to the Roaring Creek Bridge, Grady County)
June 29, 2017
Open House State Highway 19 Improvements (Beginning 5 Miles East of - - PowerPoint PPT Presentation
Open House State Highway 19 Improvements (Beginning 5 Miles East of US-81, Extending East 8.35 Miles to the Roaring Creek Bridge, Grady County) June 29, 2017 State Highway 19 Improvements Open House Purpose Purpose and need for SH-19
State Highway 19 Improvements
(Beginning 5 Miles East of US-81, Extending East 8.35 Miles to the Roaring Creek Bridge, Grady County)
June 29, 2017
State Highway 19 Improvements
Open House Purpose
State Highway 19 Improvements
Existing Facility
the statewide rate for similar facilities
State Highway 19 Improvements
Purpose and Need
State Highway 19 Improvements
Project Extents
State Highway 19 Improvements
Collisions, 2006 – 2016, West Half
State Highway 19 Improvements
Collisions, 2006 – 2016, East Half
State Highway 19 Improvements
Proposed Project
State Highway 19 Improvements
Study Segments
and through Alex
State Highway 19 Improvements
Proposed Project
State Highway 19 Improvements
Proposed Project – Typical Section
Proposed Improvements
Segment A – West of Alex
State Highway 19 Improvements
Segment A, Alternatives Considered
Segment B – Thru Alex
(widen about centerline)
(widen to south)
(widen to south)
* No widening to north considered, due to area development
State Highway 19 Improvements
Segment B, Alternatives Considered
State Highway 19 Improvements
Segment B, Alternative 1: Curb and Gutter
State Highway 19 Improvements
Segment B, Alternative 2: Open Section with 4’ Shoulders
State Highway 19 Improvements
Segment B, Alternative 3: Open Section with 8’ Shoulders
Segment C – East of Alex
State Highway 19 Improvements
Segment C, Alternatives Considered
Reconnaissance performed to identify constraints
State Highway 19 Improvements
Constraints Mapping
State Highway 19 Improvements
Composite Constraints Map
State Highway 19 Improvements
Segment A: Comparison of Alternatives
Comparison Parameters* Existing Alignment North Offset South Offset
Geometric Design Vertical Alignment 50 mph 65 mph 65 mph Environmental Impacts Wetlands Impacts (ac.) 0.47 0.55 0.48 Utility Relocation Utilities Relocation Impacts Low Medium High Right-of-Way Acquisition Potential Residential Relocations 1 2 Potential Commercial Properties Impacted 3 3 3 Southern Plains Landfill (ac.) 3.33 10.11 0.63 Total Project Cost** Estimated Construction Costs $23,008,800 $29,140,800 $28,560,000 Estimated Utility Costs $1,536,500 $2,000,600 $4,477,600 Estimated Right-of-Way Costs $880,900 $2,022,600 $1,285,800 Estimated Total Costs $25,425,900 $33,163,400 $34,323,400
*: All other parameters same for all alternatives. **: Does not include wetlands/waters mitigation costs.
Segment A: Comparison of Alternatives
Alternative 1 – Improvements on Existing Alignment
Alternative 2 – North Offset
Alternative 3 – South Offset
Segment A Preferred Alternative: Alt. 2, North Offset
State Highway 19 Improvements
Segment A: Preferred Alternative Selection
State Highway 19 Improvements
Segment B: Comparison of Alternatives
Comparison Parameters* Curb and Gutter Open Section, 4’ Shoulders Open Section, 8’ Shoulders
Geometric Design Speed Limit 45 mph 50 mph 50 mph Environmental Impacts Wetlands Impacts (ac.) Utility Relocation Utilities Relocation Impacts Medium Low High Right-of-Way Acquisition Potential Residential Relocations 1 1 1 Potential Commercial Properties Impacted Total Project Cost** Estimated Construction Costs $2,167,400 $2,088,200 $2,456,600 Estimated Utility Costs $45,100 $40,600 $57,200 Estimated Right-of-Way Costs $294,000 $297,400 $298,800 Estimated Total Costs $2,506,500 $2,426,200 $2,812,600
*: All other parameters same for all alternatives. **: Does not include wetlands/waters mitigation costs.
Segment B: Comparison of Alternatives
Alternative 1 – Curb and Gutter
Alternative 2 – Open Section, 4’ Shoulders
Alternative 3 – Open Section, 8’ Shoulders
Segment B Preferred Alternative: Alt. 2, Open Section, 4-ft. Shldrs
State Highway 19 Improvements
Segment B: Preferred Alternative Selection
State Highway 19 Improvements
Segment C: Comparison of Alternatives
Comparison Parameters* Existing Alignment North Offset South Offset
Geometric Design Vertical Alignment 55 mph 65 mph 65 mph Environmental Impacts (Approximate) Wetlands Impacts (ac.) 0.19 0.04 0.27 Utility Relocation Utilities Relocation Impacts Low High Medium Right-of-Way Impacts Potential Residential Relocations 1 1 1 Potential Commercial Properties Impacted 2 2 2 Total Project Cost** Estimated Construction Costs $5,203,100 $6,304,700 $6,395,900 Estimated Utility Costs $285,100 $1,151,00 $727,700 Estimated Right-of-Way Costs $395,600 $191,200 $396,400 Estimated Total Costs $5,883,800 $7,646,900 $7,520,000
*: All other parameters same for all alternatives. **: Does not include wetlands/waters mitigation costs.
Segment C: Comparison of Alternatives
Alternative 1 – Improvements on Existing Alignment
Alternative 2 – North Offset
Alternative 3 – South Offset
Segment C Preferred Alternative:
State Highway 19 Improvements
Segment C: Preferred Alternative Selection
Segment A: North Offset Segment B: Open Section, 4-Ft. Shoulders Segment C: Improvements on Existing Alignment
State Highway 19 Improvements
Preferred Alternative
State Highway 19 Improvements
What Happens Next?
State Highway 19 Improvements
Roadway Improvement Process
www.odot.org/publicmeetings
Oklahoma Department of Transportation Environmental Programs Division 200 N. E. 21st Street Oklahoma City, OK 73105
(405) 522-5193
environment@odot.org
State Highway 19 Improvements
Submit Your Comments
State Highway 19 Improvements