open house
play

Open House State Highway 19 Improvements (Beginning 5 Miles East of - PowerPoint PPT Presentation

Open House State Highway 19 Improvements (Beginning 5 Miles East of US-81, Extending East 8.35 Miles to the Roaring Creek Bridge, Grady County) June 29, 2017 State Highway 19 Improvements Open House Purpose Purpose and need for SH-19


  1. Open House State Highway 19 Improvements (Beginning 5 Miles East of US-81, Extending East 8.35 Miles to the Roaring Creek Bridge, Grady County) June 29, 2017

  2. State Highway 19 Improvements Open House Purpose • Purpose and need for SH-19 improvements • 3 alternatives considered for each segment • Preferred Alternative • Feedback and public input

  3. State Highway 19 Improvements Existing Facility • Two-lane facility with 12-ft. driving lanes • 1-ft. shoulder widths • Inadequate vertical alignment • Annual average daily traffic • Current (2017) =2,600 vehicles per day • Projected (2037) = 3,600 vehicles per day

  4. State Highway 19 Improvements Purpose and Need • Improve safety • 96 collisions recorded from 2006 through 2016 • Collision rate for western half of the project is 1.5 times the statewide rate for similar facilities • Provide a facility which meets current design standards • Correct sight distance due to substandard vertical alignment • Provide adequate shoulders and clear zone

  5. State Highway 19 Improvements Project Extents

  6. State Highway 19 Improvements Collisions, 2006 – 2016, West Half

  7. State Highway 19 Improvements Collisions, 2006 – 2016, East Half

  8. State Highway 19 Improvements Proposed Project • SH-19 divided into 3 segments for study purposes: • Segment A: from 5 miles east of US-81 to Alex • Segment B: through Alex • Segment C: from Alex to Roaring Creek Bridge

  9. State Highway 19 Improvements Study Segments

  10. State Highway 19 Improvements Proposed Project • Correct the vertical alignment • Add shoulders • Establish clear zone • Add turn lanes to Cedar Hills Road intersection (Landfill) and through Alex

  11. State Highway 19 Improvements Proposed Project – Typical Section Proposed Improvements • Two 12-Ft. Lanes • 1:3 Backslopes • 8-Ft. Paved Shoulders • 1:6 Foreslopes • 8-Ft. Wide Ditches • Establish Adequate Clear Zone (~28-Ft.)

  12. State Highway 19 Improvements Segment A, Alternatives Considered Segment A – West of Alex • Alternative 1: Improvements on Existing Alignment • Alternative 2: North Offset • Alternative 3: South Offset

  13. State Highway 19 Improvements Segment B, Alternatives Considered Segment B – Thru Alex • Alternative 1: Curb and Gutter (widen about centerline) • Alternative 2*: Open Section with 4-ft. Shoulders (widen to south) • Alternative 3*: Open Section with 8-ft. Shoulders (widen to south) * No widening to north considered, due to area development

  14. State Highway 19 Improvements Segment B, Alternative 1: Curb and Gutter

  15. State Highway 19 Improvements Segment B, Alternative 2: Open Section with 4’ Shoulders

  16. State Highway 19 Improvements Segment B, Alternative 3: Open Section with 8’ Shoulders

  17. State Highway 19 Improvements Segment C, Alternatives Considered Segment C – East of Alex • Alternative 1: Improvements on Existing Alignment • Alternative 2: North Offset • Alternative 3: South Offset

  18. State Highway 19 Improvements Constraints Mapping Reconnaissance performed to identify constraints • Wetlands and waters • Threatened & endangered species critical habitat • Archeological sites and historic properties • Aboveground or underground storage tanks • Oil/gas wells • Residences • Commercial facilities • Utilities

  19. State Highway 19 Improvements Composite Constraints Map

  20. State Highway 19 Improvements Segment A: Comparison of Alternatives Segment A: Comparison of Alternatives Comparison Parameters* Existing Alignment North Offset South Offset Geometric Design Vertical Alignment 50 mph 65 mph 65 mph Environmental Impacts Wetlands Impacts (ac.) 0.47 0.55 0.48 Utility Relocation Utilities Relocation Impacts Low Medium High Right-of-Way Acquisition Potential Residential Relocations 0 1 2 Potential Commercial Properties Impacted 3 3 3 Southern Plains Landfill (ac.) 3.33 10.11 0.63 Total Project Cost** Estimated Construction Costs $23,008,800 $29,140,800 $28,560,000 Estimated Utility Costs $1,536,500 $2,000,600 $4,477,600 Estimated Right-of-Way Costs $880,900 $2,022,600 $1,285,800 Estimated Total Costs $25,425,900 $33,163,400 $34,323,400 *: All other parameters same for all alternatives. **: Does not include wetlands/waters mitigation costs .

  21. State Highway 19 Improvements Segment A: Preferred Alternative Selection Alternative 1 – Improvements on Existing Alignment • Minimal improvements • Lower geometric standard (lower design speed) Alternative 2 – North Offset • Good improvements • Lower offset alignment cost Alternative 3 – South Offset • Good improvements • Most potential residential relocations • Highest cost Segment A Preferred Alternative: Alt. 2, North Offset

  22. State Highway 19 Improvements Segment B: Comparison of Alternatives Segment B: Comparison of Alternatives Open Section, Open Section, Comparison Parameters* Curb and Gutter 4’ Shoulders 8’ Shoulders Geometric Design Speed Limit 45 mph 50 mph 50 mph Environmental Impacts Wetlands Impacts (ac.) 0 0 0 Utility Relocation Utilities Relocation Impacts Medium Low High Right-of-Way Acquisition Potential Residential Relocations 1 1 1 Potential Commercial Properties Impacted 0 0 0 Total Project Cost** Estimated Construction Costs $2,167,400 $2,088,200 $2,456,600 Estimated Utility Costs $45,100 $40,600 $57,200 Estimated Right-of-Way Costs $294,000 $297,400 $298,800 Estimated Total Costs $2,506,500 $2,426,200 $2,812,600 *: All other parameters same for all alternatives. **: Does not include wetlands/waters mitigation costs .

  23. State Highway 19 Improvements Segment B: Preferred Alternative Selection Alternative 1 – Curb and Gutter • Drainage issues (flooding outside lanes) • Safety concerns (proximity of curbs thru traffic) Alternative 2 – Open Section, 4’ Shoulders • Lower Cost Alternative 3 – Open Section, 8’ Shoulders • Higher Cost Segment B Preferred Alternative: Alt. 2, Open Section, 4-ft. Shldrs

  24. State Highway 19 Improvements Segment C: Comparison of Alternatives Segment C: Comparison of Alternatives Comparison Parameters* Existing Alignment North Offset South Offset Geometric Design Vertical Alignment 55 mph 65 mph 65 mph Environmental Impacts (Approximate) Wetlands Impacts (ac.) 0.19 0.04 0.27 Utility Relocation Utilities Relocation Impacts Low High Medium Right-of-Way Impacts Potential Residential Relocations 1 1 1 Potential Commercial Properties Impacted 2 2 2 Total Project Cost** Estimated Construction Costs $5,203,100 $6,304,700 $6,395,900 Estimated Utility Costs $285,100 $1,151,00 $727,700 Estimated Right-of-Way Costs $395,600 $191,200 $396,400 Estimated Total Costs $5,883,800 $7,646,900 $7,520,000 *: All other parameters same for all alternatives. **: Does not include wetlands/waters mitigation costs.

  25. State Highway 19 Improvements Segment C: Preferred Alternative Selection Alternative 1 – Improvements on Existing Alignment • Moderate geometric improvements • Lowest cost Alternative 2 – North Offset • Utility conflict • Highest cost Alternative 3 – South Offset • High cost Segment C Preferred Alternative: Alt. 1, Improvements on Existing Alignment

  26. State Highway 19 Improvements Preferred Alternative Segment A: North Offset Segment B: Open Section, 4-Ft. Shoulders Segment C: Improvements on Existing Alignment

  27. State Highway 19 Improvements What Happens Next? • Consider comments from Open House • Finalize design report • Complete environmental studies and design plans

  28. State Highway 19 Improvements Roadway Improvement Process • Acquire right-of-way (year 2020) • Relocate utilities (year 2020) • Begin construction (year 2022 / 2023)

  29. State Highway 19 Improvements Submit Your Comments • Leave your written comments with us tonight. • Download and submit a comment form at: www.odot.org/publicmeetings • Submit your written comments by mail to: Oklahoma Department of Transportation Environmental Programs Division 200 N. E. 21st Street Oklahoma City, OK 73105 • Fax your written comments to: (405) 522-5193 • Email your comments to: environment@odot.org • Please submit your comments by July 14, 2017.

  30. State Highway 19 Improvements Thank you! Thank you!

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend