Offshore Transmission update on regulatory options Robert Hull - - PowerPoint PPT Presentation

offshore transmission update on regulatory options
SMART_READER_LITE
LIVE PREVIEW

Offshore Transmission update on regulatory options Robert Hull - - PowerPoint PPT Presentation

Offshore Transmission update on regulatory options Robert Hull & Giles Stevens 1 Contents Background: aim of project Re-cap of initial options Our current thinking Way forward 2 Background: aim of project To


slide-1
SLIDE 1

1

Offshore Transmission – update on regulatory options

Robert Hull & Giles Stevens

slide-2
SLIDE 2

2

Contents

Background: aim of project Re-cap of initial options Our current thinking Way forward

slide-3
SLIDE 3

3

Background: aim of project

To institute a regulatory framework and design price controls Powers derive from Energy Act New area of “network” regulation

slide-4
SLIDE 4

4

Background: existing and planned generation sites

slide-5
SLIDE 5

5

Background: the REZ

slide-6
SLIDE 6

6

Background: particular characteristics

Radial connections (largely) with no demand customers No existing regime/ incumbents/ infrastructure 100% load related capex investment

slide-7
SLIDE 7

7

Options for implementation – July OTEG

1. Extension of Onshore Arrangements to adjacent areas

The current 3 TO onshore zones are extended offshore - in practice this results in a single TO (National Grid) actually

  • perating offshore (for Round 1 and 2), although future Rounds for wind or wave and tidal are likely to result in the
  • ther TOs starting operations.

2. Single Offshore Zone (1 TO)

A competitive tender is held for a single offshore zone, awarded to one TO (in perpetuity).

3. 3-5 Zones (competitive tender)

Between 3 and 5 zones are established within the Strategic Areas and a competitive tender is held for a TO licence in respect of each zone (resulting in between1 and 5 TOs).

4. 3-5 Bundles of Lines (competitive tender)

A competitive tender is held for 3-5 ‘bundles’ of generating stations located in close proximity to each other (resulting in between 1 and 5 TOs).

5. Distribution Model - many TOs

A number of TO licences are granted (using existing applications route) for a single offshore zone, developers then (jointly or individually) hold a competitive tender amongst licensed TOs to supply their grid connection.

6. Point to Point - many TOs

Developers hold a competitive tender to prospective TOs to supply the grid connection, the winner then approaches Ofgem for a TO licence via application.

OFFSHORE TRANSMISSION REGIME Options for implementing the price control regime

slide-8
SLIDE 8

8

Our current thinking

  • Moving from theory to reality
  • Led to two broad approaches:
  • 1. Exclusive:
  • 2. Non-exclusive:
  • Focus to develop workable option for each approach
  • Difficult problem – no natural fit
  • Used onshore as basis of the two approaches
  • Aim is to get approaches refined enough so we can

consult on two tangible options

slide-9
SLIDE 9

9

Exclusive licences

Single TO would be exclusively responsible for a defined geographic area Number of ways this could be done – ultimately a somewhat arbitrary approach Suggest competitively tendered regional monopoly zones Has potential element of competition Multi-zones allows possible benchmarking Discretion in future award of licences in other areas

slide-10
SLIDE 10

10

Conceptually – exclusive licences

Users GBSO

Incumbent TO

Ofgem

Pay TNUoS Charges

Offer Terms

TOCO

slide-11
SLIDE 11

11

Conceptually – non-exclusive licences

Users GBSO

TO1 TO2 TO3 Etc.

Ofgem

Pay TNUoS Charges

Offer Terms

TOCO

slide-12
SLIDE 12

12

Non-exclusive licences - changes

TO licenses issued to any party which applies and meets the application criteria After application from generator, all offshore TOs have the right to submit a TOCO Bids can be for single / multiple applications TOs bid revenue stream Winning TO gets price control Impact:

– Generators: minimal change – TOs: must bid for work – Customers: share risk, share reward

slide-13
SLIDE 13

13

Promoting choice and value for all gas and electricity customers