offshore transmission update on regulatory options
play

Offshore Transmission update on regulatory options Robert Hull - PowerPoint PPT Presentation

Offshore Transmission update on regulatory options Robert Hull & Giles Stevens 1 Contents Background: aim of project Re-cap of initial options Our current thinking Way forward 2 Background: aim of project To


  1. Offshore Transmission – update on regulatory options Robert Hull & Giles Stevens 1

  2. Contents � Background: aim of project � Re-cap of initial options � Our current thinking � Way forward 2

  3. Background: aim of project � To institute a regulatory framework and design price controls � Powers derive from Energy Act � New area of “network” regulation 3

  4. Background: existing and planned generation sites 4

  5. 5 Background: the REZ

  6. Background: particular characteristics � Radial connections (largely) with no demand customers � No existing regime/ incumbents/ infrastructure � 100% load related capex investment 6

  7. OFFSHORE TRANSMISSION REGIME Options for implementing the price control regime Options for implementation – July OTEG 1. Extension of Onshore Arrangements to adjacent areas The current 3 TO onshore zones are extended offshore - in practice this results in a single TO (National Grid) actually operating offshore (for Round 1 and 2), although future Rounds for wind or wave and tidal are likely to result in the other TOs starting operations. 2. Single Offshore Zone (1 TO) A competitive tender is held for a single offshore zone, awarded to one TO (in perpetuity). 3. 3-5 Zones (competitive tender) Between 3 and 5 zones are established within the Strategic Areas and a competitive tender is held for a TO licence in respect of each zone (resulting in between1 and 5 TOs). 4. 3-5 Bundles of Lines (competitive tender) A competitive tender is held for 3-5 ‘bundles’ of generating stations located in close proximity to each other (resulting in between 1 and 5 TOs). 5. Distribution Model - many TOs A number of TO licences are granted (using existing applications route) for a single offshore zone, developers then (jointly or individually) hold a competitive tender amongst licensed TOs to supply their grid connection. 6. Point to Point - many TOs Developers hold a competitive tender to prospective TOs to supply the grid connection, the winner then approaches Ofgem for a TO licence via application. 7

  8. Our current thinking � Moving from theory to reality � Led to two broad approaches: 1. Exclusive: 2. Non-exclusive: � Focus to develop workable option for each approach � Difficult problem – no natural fit � Used onshore as basis of the two approaches � Aim is to get approaches refined enough so we can consult on two tangible options 8

  9. Exclusive licences � Single TO would be exclusively responsible for a defined geographic area � Number of ways this could be done – ultimately a somewhat arbitrary approach � Suggest competitively tendered regional monopoly zones � Has potential element of competition � Multi-zones allows possible benchmarking � Discretion in future award of licences in other areas 9

  10. Conceptually – exclusive licences Pay TNUoS Charges TOCO Incumbent Users Ofgem GBSO TO Offer Terms 10

  11. Conceptually – non-exclusive licences Pay TNUoS Charges TO1 TOCO TO2 Users Ofgem GBSO TO3 Etc. Offer Terms 11

  12. Non-exclusive licences - changes � TO licenses issued to any party which applies and meets the application criteria � After application from generator, all offshore TOs have the right to submit a TOCO � Bids can be for single / multiple applications � TOs bid revenue stream � Winning TO gets price control � Impact: – Generators: minimal change – TOs: must bid for work – Customers: share risk, share reward 12

  13. Promoting choice and value for all gas and electricity customers 13

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend