ODOT District 6 Brian Davidson, P.E., Planning and Engineering - - PowerPoint PPT Presentation

odot district 6
SMART_READER_LITE
LIVE PREVIEW

ODOT District 6 Brian Davidson, P.E., Planning and Engineering - - PowerPoint PPT Presentation

ODOT District 6 Brian Davidson, P.E., Planning and Engineering Nancy Burton & Breanna Badanes, Public Information Office April 2014 The North Side Fix 3 rd Most Congested in Ohio I-270 SR 315 US 23 The North Side Fix Project Estimated


slide-1
SLIDE 1

ODOT District 6

Brian Davidson, P.E., Planning and Engineering Nancy Burton & Breanna Badanes, Public Information Office

April 2014

slide-2
SLIDE 2

The North Side Fix

I-270 US 23 SR 315 3rd Most Congested in Ohio

slide-3
SLIDE 3

The North Side Fix

3rd Most Congested in Central Ohio 270 270

Project Phasing Letter County--Route-Section PID Estimated Construction Cost Construction Ready Funding Available F FRA-315-11.37 81738 B2 FRA-270-24.14 81737 C1 FRA-270-22.42 81739 B/B1 FRA-23-22.23 81746 $71.5 M 2013 2013 C FRA-270-21.67 81747 $42.6 M 2014 2020 D FRA-270-22.85 81748 $38.3 M 2014 2024 G* FRA-315-NB Ramp 81749 Future Future Constructed Constructed Constructed

slide-4
SLIDE 4

Existing: I-270 & US-23 (Looking Northeast)

270

slide-5
SLIDE 5

Adding Two US-23 NB Express Lanes Reconfigure Interchange from Full- Cloverleaf to Partial-Cloverleaf Future I-270 WB to SR-315 CD Future US-23 SB to I-270 WB (Project D) US-23 SB to SR-315

The North Side Fix

Construction starts Summer 2013

270

slide-6
SLIDE 6

High Street Over I-270 Enhancements

slide-7
SLIDE 7

Ramp Enhancements

US-23

270

WORTHINGTON

slide-8
SLIDE 8

Construction Progress

slide-9
SLIDE 9

Construction Progress

slide-10
SLIDE 10

Construction Progress

slide-11
SLIDE 11

Traffic Switch

slide-12
SLIDE 12

Construction Maintenance of Traffic

270

Continuous Improvement Through Lanes Maintained

  • Loop Ramps Eliminated
  • Triple Left Turn Lane at US

23 & Campus View

  • New Cameras & Interconnect
slide-13
SLIDE 13

Ramps Under Construction

Loop Ramps to Close Late August (Estimate)

slide-14
SLIDE 14

York Temple Dr., E. Campus View Blvd. and Dimension Dr.

slide-15
SLIDE 15

WHAT’S NEXT?

Estimated Timeline

  • Retaining Walls More than ½ Complete
  • I-270 east to US 23 south
  • I-270 west to US 23 north
  • Temporary Pavement Complete on US 23
  • Shift Traffic
  • Close Left/Right Turns onto Campus

View/Detour Dimension Drive

  • Digging for the Trench - APRIL
slide-16
SLIDE 16

Project Website www.270-23.com

slide-17
SLIDE 17

Traffic Cameras

slide-18
SLIDE 18

Driving Thru Construction and Alternate Routes