1 SFY 2017 Q1: ODOT Critical Success Factors
Critical Success Factors SFY 2017 Q1
People System Conditions Safety Capital Program
Critical Success Factors SFY 2017 Q1 SFY 2017 Q1: ODOT Critical - - PowerPoint PPT Presentation
People Safety Capital Program System Conditions Critical Success Factors SFY 2017 Q1 SFY 2017 Q1: ODOT Critical Success Factors 1 People CSFs SFY 2017 Q1: ODOT Critical Success Factors 2 Work Life Index (from 2015 Quality of Work Life
1 SFY 2017 Q1: ODOT Critical Success Factors
Critical Success Factors SFY 2017 Q1
People System Conditions Safety Capital Program
2 SFY 2017 Q1: ODOT Critical Success Factors
3 SFY 2017 Q1: ODOT Critical Success Factors
This CSF measures employee responses to the ODOT Quality of Work Life Survey- Specifically to questions regarding:
environment, and
strategic issues.
State Goal: 75% State Total: 72.1%
Work Life Index (from 2015 Quality of Work Life Survey)
Above Goal Below Goal 1-Year Trend Up 1-Year Trend Down 1-Year No Change4 SFY 2017 Q1: ODOT Critical Success Factors
This CSF measures the number of PERRP recordable injuries per 100 ODOT employees over the course of a calendar year.State Goal: 5.23 State Total: 4.25
(Goal Varies by District)Workforce Injuries (July 2016 – Sept. 2016)
Above Goal Below Goal 1-Year Trend Up 1-Year Trend Down 1-Year No Change5 SFY 2017 Q1: ODOT Critical Success Factors
This CSF measures the number of crashes (where ODOT is at fault) involving ODOT owned or rented equipment per 100 employees over the course of a calendar year.State Goal: 8.44 State Total: 6.53
(Goal Varies by District)Workforce Crashes (July 2016 – Sept. 2016)
Above Goal Below Goal 1-Year Trend Up 1-Year Trend Down 1-Year No Change6 SFY 2017 Q1: ODOT Critical Success Factors
This CSF is measured by the following equation: Direct Billable Labor Hours Total Labor HoursState Goal: 70% State Total: 71.3%
Direct Labor Ratio (July 2016 – Sept. 2016)
Above Goal Below Goal 1-Year Trend Up 1-Year Trend Down 1-Year No Change7 SFY 2017 Q1: ODOT Critical Success Factors
Disadvantaged Business Enterprise (DBE) (July 2016 – Sept. 2016)
State Goal: 8.9% State Total: 10.6%
This CSF measures the percent of participation by DBE certified businesses on ODOT’s federally funded construction contracts. This CSF measures the percent of participation by EDGE certified businesses on ODOT’s state funded construction contracts.
State Goal: 5.0% State Total: 4.9%
Encouraging Diversity, Growth, and Equity (EDGE) (July 2016 – Sept. 2016)
8 SFY 2017 Q1: ODOT Critical Success Factors
This CSF measures the percent of ODOT’sState Goal: 15% State Total: 27.3%
Minority Business Enterprise (MBE) (July 2016 – Sept. 2016)
Above Goal Below Goal 1-Year Trend Up 1-Year Trend Down 1-Year No Change9 SFY 2017 Q1: ODOT Critical Success Factors
10 SFY 2017 Q1: ODOT Critical Success Factors
This CSF measures the weighted average bridge condition as determined by general appraisal values that range from 0-9.State Goal: 6.8 State Total: 7.01
Bridge General Appraisal (GA) (as of Sept. 2016)
Above Goal Below Goal 1-Year Trend Up 1-Year Trend Down 1-Year No Change11 SFY 2017 Q1: ODOT Critical Success Factors
This CSF measures the weighted average pavement condition rating (PCR) for all interstates and interstate lookalikes. The PCR goal is for the state as a whole, not individual Districts. Priority System RoadsState Goal: 85 State Total: 85.63
Priority System Pavements (as of Sept. 2016)
Above Goal Below Goal 1-Year Trend Up 1-Year Trend Down 1-Year No Change12 SFY 2017 Q1: ODOT Critical Success Factors
This CSF measures the weighted average pavement condition rating (PCR) for all 2-lane US and State Routes outside ofState Goal: 80 State Total: 83.11
General System Pavements (as of Sept. 2016)
Above Goal Below Goal 1-Year Trend Up 1-Year Trend Down 1-Year No Change13 SFY 2017 Q1: ODOT Critical Success Factors
This CSF measures the weighted average pavement condition rating (PCR) for all 2-lane US and State Routes outside ofState Goal: 80 State Total: 78.37
Urban System Pavements (as of Sept. 2016)
Above Goal Below Goal 1-Year Trend Up 1-Year Trend Down 1-Year No Change14 SFY 2017 Q1: ODOT Critical Success Factors
This CSF measures the percent of ODOT’s roadways without certain deficiencies. ODOT surveys roadways in 1/10th mile segments for 14 types of deficiencies related to barriers, pavement, pavement markings, and signals.State Goal: 99% State Total: 99.6%
Maintenance Condition Rating (as of Sept. 2016)
Above Goal Below Goal 1-Year Trend Up 1-Year Trend Down 1-Year No Change15 SFY 2017 Q1: ODOT Critical Success Factors
This CSF measures the percent of time between 5am and 9pm that ODOT’s roads
flow speeds.
State Goal: 88% State Total: 95%
Travel Time Reliability Index (TTRI) (as of Sept. 2016)
Above Goal Below Goal 1-Year Trend Up 1-Year Trend Down 1-Year No Change16 SFY 2017 Q1: ODOT Critical Success Factors
This CSF measures the percent of Ohio’s interstates and interstate lookalikes that return to expected speeds within two hours of a snow and/or ice event. Expected speeds are based on factors including speed limit, time of day, and day of week. Above State Goal Below State Goal Not Applicable Above State Goal Below State Goal Not ApplicableSnow and Ice Control
State Goal: 96% State Total: Not Applicable
Snow and Ice Control (July 2016 – Sept 2016)
17 SFY 2017 Q1: ODOT Critical Success Factors
18 SFY 2017 Q1: ODOT Critical Success Factors
This CSF measures fatalities that have occurred on ODOT roadways in calendar year 2016 (Jan-Sept). The goal is a 1% decrease over the 5 year average.State Goal (Jan-Sept): 360 State Total (Jan-Sept):397
Fatalities (Calendar Year 2016 Goal = 418)
Above Goal Below Goal 1-Year Trend Up 1-Year Trend Down 1-Year No Change19 SFY 2017 Q1: ODOT Critical Success Factors
This CSF measures serious injuries that have occurredState Goal (Jan-Sept): 2,637 State Total (Jan-Sept): 2,704
Serious Injuries (Calendar Year 2016 Goal = 3,498)
Above Goal Below Goal 1-Year Trend Up 1-Year Trend Down 1-Year No Change20 SFY 2017 Q1: ODOT Critical Success Factors
This CSF measures crashes that have occurred on ODOT roadways in calendar year 2016 (Jan-Sept). The goal is a 1% decrease over the 5 year average.State Goal (Jan-Sept): 59,707 State Total (Jan-Sept): 63,613
Total Crashes (Calendar Year 2016 Goal = 85,596)
Above Goal Below Goal 1-Year Trend Up 1-Year Trend Down 1-Year No Change21 SFY 2017 Q1: ODOT Critical Success Factors
22 SFY 2017 Q1: ODOT Critical Success Factors
This CSF measures the percent of ODOT’s ODOT let contract construction projects awarded within 30 days of their target date.State Goal: 90% State Total: 97.2%
ODOT Let Projects Awarded on Time
(July 2016 – Sept. 2016)
State Goal: 90% State Total: 99.4% All Project Delays Considered Only Preventable Delays Considered
Above Goal Below Goal 1-Year Trend Up 1-Year Trend Down 1-Year No Change23 SFY 2017 Q1: ODOT Critical Success Factors
This CSF measures the percent of ODOT’s Local let contract construction projects awarded within 30 days of their target date.State Goal: 85% State Total: 90.7%
Local Let Projects Awarded on Time
(July 2016 – Sept. 2016)
All Project Delays Considered State Goal: 85% State Total: 97.5% Only Preventable Delays Considered
Above Goal Below Goal 1-Year Trend Up 1-Year Trend Down 1-Year No Change24 SFY 2017 Q1: ODOT Critical Success Factors
This CSF measures the total amount of construction contracts awarded to date in SFY 2017.
State Goal: $314M State Total: $347M
SFY 2016 Construction Program
(July 2016 – Sept. 2016)
Above Goal Below Goal25 SFY 2017 Q1: ODOT Critical Success Factors
This CSF measures the percent of ODOT’s construction program attributable to preventable change orders.
State Goal: 1.5% State Total: 0.3%
Preventable Change Orders (July 2016 – Sept. 2016)
Above Goal Below Goal 1-Year Trend Up 1-Year Trend Down 1-Year No Change