FRA 70 14.56 Project Matchmaker Event Jack R. Marchbanks, District - - PowerPoint PPT Presentation

fra 70 14 56
SMART_READER_LITE
LIVE PREVIEW

FRA 70 14.56 Project Matchmaker Event Jack R. Marchbanks, District - - PowerPoint PPT Presentation

FRA 70 14.56 Project Matchmaker Event Jack R. Marchbanks, District 6 Deputy Director April 18, 2016 John R. Kasich, Jerry Wray, Ohio Governor ODOT Director ODOT S M ISSION To provide easy movement of people and goods from place to


slide-1
SLIDE 1

John R. Kasich, Jerry Wray, Ohio Governor ODOT Director

FRA 70 14.56 Project Matchmaker Event

Jack R. Marchbanks, District 6 Deputy Director April 18, 2016

slide-2
SLIDE 2

To provide easy movement of people and goods from place to place, we will:

__________________________________

Take care of what we have;

_________________________________

Make our system work better;

_________________________________

Improve safety;

_________________________________

Enhance capacity.

ODOT’ S M ISSION

slide-3
SLIDE 3

3

  • Eight Counties
  • 4,800 miles of roads
  • 1,552 Bridges
  • 17 Garages/Outposts
  • Operating Budget
  • approx. $52 million
  • CAPITAL PROGRAM
  • Over 60 Construction Projects
  • Over 200 Million Dollars

District 6

slide-4
SLIDE 4

John R. Kasich, Jerry Wray, Ohio Governor ODOT Director

Leslie Montgomery, P .E. ,Project Manager David Poling, P .E. ,Construction Area Engineer Natina Ariss, P .E. ,Construction Project Engineer April, 2017

slide-5
SLIDE 5

5

  • PROJ. NO. 170268

FRA-70-14.56 PID 103487

Project Location

slide-6
SLIDE 6

6

Project Overview

  • Purpose: Widen Grant Ave spans for new

ramps, One way Mound St to Front St

ESTIMATED COST

$36 Million

slide-7
SLIDE 7

7

Project Schematic

  • PROJ. NO. 170268

FRA-70-14.56 PID 103487

slide-8
SLIDE 8

8

Project Work

  • Grant Avenue bridge full replacement
  • 2000’ of drilled shaft retaining walls
  • 1000’ of cantilevered CIP walls
  • New transition pavement on I-70 W
  • 2 blocks of Mound St
  • Bridge Maintenance

WORK WILL INCLUDE:

slide-9
SLIDE 9

9

Schedule

  • Sale Date:

05/11/2017

  • Award Date:

05/22/2017

  • Construction

Start: 07/17/2017

  • Construction

End: 09/15/18

slide-10
SLIDE 10

10

Construction Work Types

Construction Work Types

Code Description Code Description 1 Clearing and Grubbing 29 Structure Repairs 2 Building Removal 34 Earth Retaining Structures 5 Major Roadway Excavation 35 Drainage (culverts, misc) 7 Soil Stabilization 36 Guardrail/Attenuators 8 Temporary Soil Erosion & Sediment Control 37 Fence 9 Aggregate Bases 38 Misc Concrete 10 Flexible Paving 39 Maintenance of Traffic 12 Rigid Paving 40 Waterproofing 13 Pavement Planing, Milling, Scarification 41 Raised Pavement Markers 16 Flexible Replacement 42 Signing 19 Structure Removal 43 Highway Lighting 20 Level 1 Bridge 44 Traffic Signals - Standard 21 Level 2 Bridge 45 Pavement Markings 23 Reinforcing Steel 46 Landscaping 24 Structural Steel Erection 53 Piling 25 Stud Welding 56 Fiber Optic Cable Installation, Splicing, Termination and Testing - ITS 26 Structural Steel Painting 57 Sealing of Concrete Surfaces with Epoxy or Non-Epoxy Sealers 27 Expansion & Contraction Joints, Joint Sealers, Bearing Devices

slide-11
SLIDE 11

11

Roadway Pavement Work Types

  • 302 Asphalt: 5,700 CY
  • 304 Aggregate Base: 7,000 CY
  • 305 Concrete Base: 17,400 SY
  • 441 & 442 Inter. Asphalt: 2,100 CY
  • 441 & 442 Surface Asphalt: 1,900 CY
  • 452 Concrete Pavement: 2,200 SY

Roadway & Pavement Work

Estimated Cost $6.3 M

FRA 70 14.56 Project Matchmaker

slide-12
SLIDE 12

12

Structures Work Types

  • Grant Ave. Bridge Replacement: Deck

replacement and widening: steel girder bridge

  • 4 Retaining walls: 2 Drilled Shaft Walls & 2

Cast In Place

  • Repair & Debris Containment for 6 bridges

Structures Work

Estimated Cost $17.1M

FRA 70 14.56 Project Matchmaker

slide-13
SLIDE 13

13

Drainage, Erosion Control & Waterwork Work Types

  • 605 Underdrains: 20,700 LF
  • Misc. 12 in. to 96 in. drainage conduit: 4,800 FT
  • Misc. Catch Basins, Inlets & Manholes: 32 EA
  • Ductile Iron Water Pipe: 2,400 LF

Drainage, Erosion Control & Waterwork

Estimated Cost $ 1.6 M

FRA 70 14.56 Project Matchmaker

slide-14
SLIDE 14

14

Traffic Control, Traffic Signals, Lighting Work Types

  • Misc. overhead and ground mounted signs
  • LED street lights: 48 EA
  • 804 Fiber Optic cable: 3,000 LF

Traffic Control, Traffic Signals, Power & Lighting Work

Estimated Cost $ 3.2 M

FRA 70 14.56 Project Matchmaker

slide-15
SLIDE 15

15

Maintenance of Traffic Work Types

  • 614 Maintaining Traffic
  • 622 Port. Concrete Barrier: 15,700 LF

Maintenance of Traffic Work

Estimated Cost $0.9 M

FRA 70 14.56 Project Matchmaker

slide-16
SLIDE 16

16

Disadvantage Business Enterprise (DBE)

DBE Goal 12%

  • Contains the Proposal Note 013 - Disadvantaged Business

Enterprise (DBE) Utilization Plan and Good Faith Efforts, updated 05/29/2015

  • All bidders shall submit a DBE Utilization Plan at the

time of bid setting forth specific information demonstrating how the bidder will achieve the DBE goal.

  • DBE Certified Firms:

FRA 70 14.56 Project Matchmaker

slide-17
SLIDE 17

John R. Kasich, Jerry Wray, Ohio Governor ODOT Director

Questions

How to Find US ODOT District 6 400 E. William St. Delaware, OH 43015 740-833-8000

slide-18
SLIDE 18

18

Thank you for Attending

FRA 70 14.56 Project Matchmaker