NORTHERN PIPELINES- PIE IN THE SKY OR PATHWAYS TO PROSPERITY? Alan - - PowerPoint PPT Presentation

northern pipelines pie in the
SMART_READER_LITE
LIVE PREVIEW

NORTHERN PIPELINES- PIE IN THE SKY OR PATHWAYS TO PROSPERITY? Alan - - PowerPoint PPT Presentation

1 NORTHERN PIPELINES- PIE IN THE SKY OR PATHWAYS TO PROSPERITY? Alan Murray SNAME Arctic Section January 19 th 2012 Outline A Brief History The Resource The Demand The Potential Projects The Competition Whats Next?


slide-1
SLIDE 1

NORTHERN PIPELINES- PIE IN THE SKY OR PATHWAYS TO PROSPERITY?

Alan Murray SNAME Arctic Section January 19th 2012

1

slide-2
SLIDE 2

Outline

  • A Brief History
  • The Resource
  • The Demand
  • The Potential Projects
  • The Competition
  • What’s Next?
  • Lessons Learned
  • Questions???

2

slide-3
SLIDE 3

A Brief History

  • 1922 first well drilled at Norman Wells
  • 1944 Canol Pipeline constructed (decommissioned in 1948 )
  • 1967 discovery of large natural gas reserves in Prudhoe Bay,

Alaska

  • 1969 first oil well in The Mackenzie Delta
  • 1970 first natural gas well built at Parson's Lake.
  • 1973 Canadian Arctic Gas Pipeline mooted linking Prudhoe -

>North Yukon-> Delta -> Mackenzie Valley -> Alberta

  • 1974 March Berger Inquiry begins visiting 35 communities

and criss crossing Canada

  • 1977 June Berger issues 40,000 page report ‘Northern Frontier,

Northern Homeland” concludes “no pipeline should be built through the northern Yukon, and that a pipeline through the Mackenzie Valley should be delayed for 10 years”

3

slide-4
SLIDE 4

A Brief History

  • 1977 Lysyk Alaska Highway Pipeline Inquiry reached similar

conclusions to Berger noting ” most of the economic benefits of the pipeline would go outside of the Yukon, but that there was large conditional support for the project if native land claims were settled and the pipeline companies agreed to pay to mitigate negative social impacts of the project.

  • 1978-1982 stage 1 of Alaska Highway pipeline pre-build
  • 2004 MGP proponents apply to NEB
  • 2008 TransCanada Alaska Co. received a license under the

Alaska Gas Inducement Act (AGIA) to pursue Stage Two of the AHGP (funding of $500MM provided to develop project)

  • 2010 December NEB gives conditional approval to the MGP with

a “sunset” condition, onus now on proponents

  • 2011 BP led Denali gas pipeline proposal scrapped

4

slide-5
SLIDE 5

Northern Canada Total Wells Drilled

5

Courtesy: Dan Masterson Chevron

slide-6
SLIDE 6

The Resource

6

slide-7
SLIDE 7

Distribution of Natural Gas Resources Outside the WCSB in Tcf

Arctic Islands UR 8.0-33.0+ DR 12.0-20.0 RR 0.0 CP 0.0 Total 20.0-53.0 Grand Banks / Labrador UR 36.5 DR 9.6 RR 0.0 CP 0.0 Total 46.1 Scotia Shelf UR 15-41 DR 3.6-5.3 RR 2.7 CP 0.5 Total 18.6-46.3 Ontario UR 1 DR 1 RR 0.7 CP 1.2 Total 2.4 Other Frontier ** UR 34.0 DR 0.0 RR 0.0 CP 0.0 Total 40.0

** Other Frontier areas include: the Georges Bank, Laurentian, East Newfoundland Basin and Southern Grand Banks, the St. Lawrence Lowland and Maritimes Basin, Hudson's Bay, Baffin Bay and offshore British Columbia.

CP = Cumulative Production RR = Remaining Marketable Reserves DR = Discovered Resources

Mackenzie/Beaufort UR 52.0 DR 9.0 RR 0.0 CP 0.0 Total 61.0

Source: National Energy Board, Canada’s Conventional Natural Gas Resources: A Status Report

UR = Undiscovered Resources

Offshore West Coast UR 17.0-43.4 DR 0.0 RR 0.0 CP 0.0 Total 17.0-43.4 Yukon & NWT UR 10.3 DR 25.0-26.0 RR <1.0 CP 0.3 Total 36.6-37.6

7

slide-8
SLIDE 8

The Demand

8

slide-9
SLIDE 9

Natural Gas End Use Demand – Canada

273,370 766,994 173,993 79,626 882,133 181,858

Provincial Gas Consumption End use, Final Demand 2008 (Terajoules) Canada 2,376,882

Source: Statistics Canada 57-003-X1E

1,256 16,314 Atlantic Provinces 9

slide-10
SLIDE 10

Canadian Natural Gas Consumption

Residential 689,049 (25.2%)

2,731,476 Terajoules (2008)

Commercial &

  • ther institutional

468,656 (17.2%) Industrial 1,025,391 (37.5%) Agriculture 22,635 (<1%) Public Administration 22,313 (<1%)

Source: Statistics Canada 57-003-X1E

Transportation 148,837 (5.4%) Power Generation 354,594 (13%)

10

slide-11
SLIDE 11

US Natural Gas Consumption Consumers by Sector

22,167 Bcf (2010)

Residential 4,951 Bcf = 22.3% Industrial* 6599 Bcf = 29.8% Commercial 3,205 Bcf = 14.5% Power Generation 7,377 Bcf = 33.2%

Source: US Energy Information Administration 2007 Statistics

Transportation 32.9 Bcf = .15%

* Includes Pipelines and Distribution System own-use 11

slide-12
SLIDE 12

US Annual Natural Gas Consumption

2009 = 22,810 Bcf

West 14.6% Central 14.9% Midwest 18.6% Gulf 24% South Atlantic 11.2% Northeast 14.2% Alaska 1.8%

Source: US Energy Information Administration

12

slide-13
SLIDE 13

Oil & Gas Jnl April 7 2009

13

slide-14
SLIDE 14

Historical Production in Canada

* Raw Gas is raw natural gas production less raw and processed gas injection.

Source: CAPP 2009 Statistical Handbook, Tables 3.9b and 3.10a

14

slide-15
SLIDE 15

Projected Annual Natural Gas Production from United States

15

slide-16
SLIDE 16

The Potential Projects

Region Pipeline Resource Potential Tcf Alaska North Slope AHPP 126 Mackenzie D/Beaufort Sea MVP/MGP 52 North Yukon MVP or AHPP 11.3 16

slide-17
SLIDE 17

Mackenzie/Beaufort and Alaska Gas Transportation

Source: Oil and Gas Journal

17

The Northern Route is fanciful at best! The Denali Project backed by BP and Conoco Philips and solely funded by them was cancelled in May 2011 due to a combination of poor open season response, low gas prices and the technological advances in shale gas development in the lower 48 states Much closer to the markets.

slide-18
SLIDE 18

Bridging to the Arctic -MVP

Norman Wells Great Slave Lake

Northwest Terrotories

Great Bear Lake Fort Good Hope Mackenzie River –

Mackenzie Delta & Beaufort Sea Middle Mackenzie Valley Liard River Basin Cameron Hills

Proposed Mackenzie Valley Pipeline

18

slide-19
SLIDE 19

Mackenzie Valley Pipeline

  • The Mackenzie Valley Pipeline “MGP” is a joint venture between the

3 anchor field holders, Imperial Oil, Exxon Mobil Canada, Conoco- Phillips, Shell Canada.

  • TransCanada (TCPL) has provided funding to the Aboriginal Pipeline

Group in return for rights to acquire an interest in the pipeline and future expansions

  • MGP is a 30 “ dia. Pipeline extending 1220km from Inuvik to N

Alberta and could ship up to 1.2 bcf/day ( with compression)

  • In addition a liquids line would parallel the gas line from Inuvik to

Norman Wells connecting to the existing Enbridge NW line

19

slide-20
SLIDE 20

Mackenzie Valley Pipeline

20

slide-21
SLIDE 21

21

Phase Envelopes for Hydrocarbons

slide-22
SLIDE 22

Mackenzie Valley Pipeline

22

slide-23
SLIDE 23

Mackenzie Valley Pipeline

23

Project would use about 440,000 tonnes of steel Would require facility and camp modules, construction and drilling equipment, borrow material and fuel. Plan is to move materiel and fuel to Hay River then barge to locations north of Fort Simpson and truck to points south . Personnel would be moved by plane and bus Borrow material ( soil and gravel used for construction) would be moved by truck on project roads Peak Activities would occur: In summer, with barges on the Mackenzie from Hay River and Fort Liard. In winter with trucks transporting material to infrastructure sites. At the start and end of winter with aircraft transporting project personnel

slide-24
SLIDE 24

MGP – the Regulatory Decision

24

“We have decided that the project is in the public interest. In reaching this Decision, we have considered the social , environmental and economic effects And listened to the views of Northerners and other parties. Our approval of the applications ...depends on the companies meeting a combined total of more than 200 conditions to address the concerns we have heard” “The economic benefits would be real and large. The companies proposing the project estimate they would spend $16.2 billion. This would increase Canada’s GDP by more than $13Bn, generate almost $6Bn in labour income and Governments would gain $2.9Bn in tax revenues” “Our decision requires that the gathering and transmission pipelines provide “Open Access”… encouraging further exploration and production” “We are confident that the companies are fully capable of designing, constructing and operating the proposed facilities in a safe manner” Our decision is a major step towards allowing the project to proceed, but does not mean that it will be built. It is up to the companies to decide whether theproject makes economic sense for them based on their view of gas prices ad project costs. By the end of 2013 we require the companies to file an updated cost estimate and decide on building the project Actual construction must begin by end of 2015 for our approval to remain valid.

slide-25
SLIDE 25

Alaskan Pipeline Project

Prudhoe Bay Boundary Lake Graphic Courtesy of TransCanada’s Alaskan Pipeline Project

25

The ANGTS Pipeline received US and Canadian Government Approvals in 1977 Led to the creation of the Northern Pipeline Agency in Canada Foothills Stage 1 Pre build 35Tcf of recoverable gas Question: Is the original approval still valid for the present proposal?

slide-26
SLIDE 26

In Canada a further 972 miles of pipe

Alaskan Pipeline Project

26

slide-27
SLIDE 27

Project parameters

Point Thomson transmission pipeline

  • Pipeline length:. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 58 miles (94 km)
  • Pipeline diameter:. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32 inches
  • Maximum operating pressure:. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1130 psig
  • Pipeline capacity:. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.1 bcf/d

Alberta Case (Prudhoe Bay to Alberta)

  • Total length:. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1717 miles (2762 km)

–– Pipeline length (Alaska): . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 745 miles (1198 km) –– Pipeline length (Canada):. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 972 miles (1564 km)

  • Pipeline diameter:. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 48 inches
  • Maximum operating pressure:. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2500 psig
  • Pipeline capacity (base design case):. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4.5 bcf/d
  • Pipeline capacity (with max compression):. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5.9 bcf/d

Valdez LNG Case (Prudhoe Bay to Valdez)

  • Pipeline length:. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 811 miles (1305 km)
  • Pipeline diameter:. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 48 inches
  • Maximum operating pressure:. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2500 psig
  • Pipeline capacity (base design case):. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.0 bcf/d

Compression Alberta Case Alberta Case Valdez LNG Case 4.5 bcf/d 5.9 bcf/d 3.0 bcf/d Total compressor stations (Alaska) 8 17 2 Total compressor stations (Canada) 11 20 n/a In areas of continuous permafrost or where permafrost is predominant, gas will be chilled on the discharge side of compressor stations

27

slide-28
SLIDE 28

Proposed Project Timeline

Open Season & Commercial Developments

.

Received approval from the U.S. Federal Energy Regulatory Commission (FERC) to conduct the first natural gas open season in North Slope history. Developed a credible cost estimate and competitive commercial offering for potential shippers to evaluate during the open season. The project conducted its initial open season in 2010,and is currently engaged in negotiations with potential shippers to execute signed precedent agreements

28

slide-29
SLIDE 29

Regulatory Approvals & the Permitting Process

The project is actively working to file major permit applications with FERC and the Northern Pipeline Agency (NPA) in 2012 by advancing the essential groundwork for securing permits, including environmental, regulatory, and land field studies and stakeholder engagement.

29

slide-30
SLIDE 30

Engineering & Construction Planning

30

slide-31
SLIDE 31

Engineering & Construction Planning

31

slide-32
SLIDE 32

Oil Sands & the “Big Picture”

32

slide-33
SLIDE 33

The competition

33

slide-34
SLIDE 34

US Shale Gas Deposits

34

slide-35
SLIDE 35

Approved North American LNG Terminals

Source: US Federal Energy Regulatory Commission (FERC)

35

slide-36
SLIDE 36

What’s Next?

It Depends!

36

slide-37
SLIDE 37

Natural Gas Pricing

Historical Western Canadian Natural Gas Prices

37

slide-38
SLIDE 38

Recent Horn River News

EnCana announced in 2009 over 500 Tcf Horn River gas in place

  • Only US plays Haynesville (717 Tcf) & Marcellus (1,500+Tcf)

are bigger

  • Apache & Encana drilled 40 wells with initial production rates

declining 50% after one year

  • Good decline rate in favourable geology compares to 80-90% decline

in other shale plays.

  • Little gas produced from region yet. Awaiting new & expanded

lines/ higher gas prices

  • NEB estimates unconventional gas resources: tight gas and

CBM at over 600 tcf, but low estimates can be 250 tcf of which 10-20% is maybe recoverable

38

slide-39
SLIDE 39

Lessons Learned

Irrespective of the business outcome of the current proposals unquestionably Governments, Regulators, proponents and the industry at large has learned much

  • 1. Regulatory Approvals require a sunset condition.

Thus Dec 2015 condition on MGP

  • 2. The regulatory process is far too long.

Thus the creation in Canada of the Major Project Management Office The TAPS pipeline was designed, approved and built in 8 years almost as much time as the MGP Hearings!

  • 3. Technology is readily transferable for example:

Development of high strength steels with good fracture control properties Development and Use of Strain based design methods Development of Structural Reliability Design for use in Pipelines Improved understanding of material properties Development of semi and fully automatic high productivity welding Improved inspection techniques and flaw acceptance in plastic zones Development of remote sensing ground movement and pipe straining

39

slide-40
SLIDE 40

Questions?

40

slide-41
SLIDE 41

MPMO

  • The MPMO was established in 2007 to improve coordination of

the regulatory review of major resource projects.

  • Its goal is to allow the federal government to work on major

projects as one team. As a means to that end, the system has been devised so that industry is provided with a single point of entry into federal processes, accompanied with explicit service

  • standards. A basic tool in the toolkit of the MPMO is the

execution of project agreements, signed by all deputy ministers and heads of regulatory agencies involved in major projects. As a result, issues are escalated to deputy ministers and agency heads before they become a problem. Project agreements and the service standards embodied in them are a good demonstration of the doctrine of "what gets measured gets done".

  • The NPMO was established in May 2010 to coordinate federal

regulatory work in the territories.

41