/ / 1
Network Rail: Beyond the Hendy Review
Investment & Resilience for the South West
Mark Langman, Route Managing Director – Network Rail Western Route Travel Watch South West, 5 March 2016
Network Rail: Beyond the Hendy Review Investment & Resilience - - PowerPoint PPT Presentation
Network Rail: Beyond the Hendy Review Investment & Resilience for the South West Mark Langman , Route Managing Director Network Rail Western Route Travel Watch South West, 5 March 2016 / / 1 A little about me / 2 Our railways
/ / 1
Network Rail: Beyond the Hendy Review
Investment & Resilience for the South West
Mark Langman, Route Managing Director – Network Rail Western Route Travel Watch South West, 5 March 2016
/ 2
A little about me…
/ 3
Our railways
Platform 1 at Paddington Station
/ 4
How we compare
RAIL SUBSIDY in Europe
2nd
RAIL INVESTMENT in Europe
1st
LOWEST
/ 5
How we compare
RAIL SAFETY in Europe
2nd
RAIL EFFICIENCY in Europe
2nd
/
Performance Improvement Plan
Airport Jn
esp Southall, Heathrow Airport, Dolphin Jn & and Slough West Jn
East, Southall West and Southcote junctions
Hayes area
maintenance plan
6
/
Performance Improvement Plan
7
80 82 84 86 88 90 92 94 6 7 8 9 10 11 PPM Target PPM Actual
/ 8
Network Rail’s Investment
/ 9
Enhancements Delivery Plan
2017
Hitachi Bi-modal IEPs enter service
2016
Test Track (Didcot-Reading)
2018
Big timetable change in December
2019
Crossrail (Elizabeth Line) fully open
2020
Electrification build complete
2024
Western Rail Link to Heathrow
/ /
Investment & Resilience
10
/ 11
Cowley Bridge Athelney-Cogload Jn Chipping Sodbury Hele & Bradninch Flax Bourton Patchway Up Tunnel Exeter St Davids Diversionary Route Exeter to Newton Abbot (inc. Dawlish) Whiteball Tunnel
South West Flood Resilience
/
12
Chipping Sodbury
/ 13
Whiteball Tunnel (South)
/ 14
Whiteball Tunnel (North)
/ 15
Whiteball Tunnel
/ 16
(Above) Exwick Weir (Below) Pynes Weir
Cowley Bridge
Cowley Bridge Junction
/ 17
Design stage for revised drainage
Hele & Bradninch
/ 18
Major revision of drainage system to prevent flooding of main line
Part A Part B
Somerset Levels: Athelney & Cogload
/ 19
Working with Somerset County Council and Environment Agency to mitigate future flooding No current plans to divert lines Photo taken in Feb 2014
Part A Part B
Somerset Levels
/
Whimple Crewkerne
20
We are developing the capacity to
route between London and Exeter for HSTs This would travel via the Wessex Route via Castle Cary and Yeovil For use if/when the Somerset Levels flooded One train per hour
Wessex Diversionary Route
/ 21
anticipated for March 2016
Summary Status
/
Exeter to Newton Abbot
22
/ 23
protection
Exeter to Newton Abbot
/ Flood Resilience Programme Update 26 January 2015 24
change
Ex2NA: Long Term
/ 25
resilience measures necessary for the line
Ex2NA: Long Term
/ 26
Next steps: Ground Investigation Works complete Summer ’16 Scoping & Option Selection Phase completed by Spring 2016 Final Option Selection Report to be issued May 2016 Currently no further funding for remainder of CP5 (2 years)
Current funding situation means that Project will be paused from Autumn 2016 until commencement of CP6 (2019) assuming that DfT approves
Ex2NA: Long Term
/ 27
delivered to DfT – now with Peninsula Rail Task Force
Exeter to Plymouth: Alternative Route Study
/ 28
study into delivering infrastructure interventions to support the AT300 reduced journey times by 2018.
Line Speed Improvements to SW
/ 29
For the introduction of cascaded Diesel Multiple Units
Preparation Works
/
£45m now for GRIP 3-5 Development and advanced works awaiting signoff from DfT £15m funding from Cornwall CC being sourced to deliver Stage 1, comprising additional signalling between Menheniot and Cambourne to enable a 30-min frequency between Plymouth and Penzance
30
Cornwall Resignalling
/ 31
There has never been a better time to be involved with our nation’s railways
Questions