Network Rail: Beyond the Hendy Review Investment & Resilience - - PowerPoint PPT Presentation

network rail
SMART_READER_LITE
LIVE PREVIEW

Network Rail: Beyond the Hendy Review Investment & Resilience - - PowerPoint PPT Presentation

Network Rail: Beyond the Hendy Review Investment & Resilience for the South West Mark Langman , Route Managing Director Network Rail Western Route Travel Watch South West, 5 March 2016 / / 1 A little about me / 2 Our railways


slide-1
SLIDE 1

/ / 1

Network Rail: Beyond the Hendy Review

Investment & Resilience for the South West

Mark Langman, Route Managing Director – Network Rail Western Route Travel Watch South West, 5 March 2016

slide-2
SLIDE 2

/ 2

A little about me…

slide-3
SLIDE 3

/ 3

Our railways

Platform 1 at Paddington Station

slide-4
SLIDE 4

/ 4

How we compare

RAIL SUBSIDY in Europe

2nd

RAIL INVESTMENT in Europe

1st

LOWEST

slide-5
SLIDE 5

/ 5

How we compare

RAIL SAFETY in Europe

2nd

RAIL EFFICIENCY in Europe

2nd

slide-6
SLIDE 6

/

Performance Improvement Plan

  • Reintroduced Track Circuit Care Team between Paddington and

Airport Jn

  • Reintroduced Points Care Team between Paddington and Reading,

esp Southall, Heathrow Airport, Dolphin Jn & and Slough West Jn

  • Completed reliability-focused component upgrades to Southall

East, Southall West and Southcote junctions

  • Dedicated S&T rapid response team, located in the Southall /

Hayes area

  • Strengthened route focus on daily delivery of the operational and

maintenance plan

  • Focus on right-time starts from depots and stations with GWR

6

slide-7
SLIDE 7

/

Performance Improvement Plan

7

80 82 84 86 88 90 92 94 6 7 8 9 10 11 PPM Target PPM Actual

slide-8
SLIDE 8

/ 8

Network Rail’s Investment

slide-9
SLIDE 9

/ 9

Enhancements Delivery Plan

2017

Hitachi Bi-modal IEPs enter service

2016

Test Track (Didcot-Reading)

2018

Big timetable change in December

2019

Crossrail (Elizabeth Line) fully open

2020

Electrification build complete

2024

Western Rail Link to Heathrow

slide-10
SLIDE 10

/ /

South West

Investment & Resilience

10

slide-11
SLIDE 11

/ 11

Cowley Bridge Athelney-Cogload Jn Chipping Sodbury Hele & Bradninch Flax Bourton Patchway Up Tunnel Exeter St Davids Diversionary Route Exeter to Newton Abbot (inc. Dawlish) Whiteball Tunnel

South West Flood Resilience

slide-12
SLIDE 12

/

  • Previously the most-often flooded section of the Route
  • Has NOT flooded in 2015-16 storm season.

12

Chipping Sodbury

slide-13
SLIDE 13

/ 13

Whiteball Tunnel (South)

slide-14
SLIDE 14

/ 14

Whiteball Tunnel (North)

slide-15
SLIDE 15

/ 15

Whiteball Tunnel

slide-16
SLIDE 16

/ 16

(Above) Exwick Weir (Below) Pynes Weir

  • Plans to improve resilience of the Exe at

Cowley Bridge

  • Design complete
  • Liaison with landowners ongoing

Cowley Bridge Junction

slide-17
SLIDE 17

/ 17

Design stage for revised drainage

Hele & Bradninch

slide-18
SLIDE 18

/ 18

Major revision of drainage system to prevent flooding of main line

Part A Part B

Somerset Levels: Athelney & Cogload

slide-19
SLIDE 19

/ 19

Working with Somerset County Council and Environment Agency to mitigate future flooding No current plans to divert lines Photo taken in Feb 2014

Part A Part B

Somerset Levels

slide-20
SLIDE 20

/

Whimple Crewkerne

20

We are developing the capacity to

  • perate a diversionary

route between London and Exeter for HSTs This would travel via the Wessex Route via Castle Cary and Yeovil For use if/when the Somerset Levels flooded One train per hour

Wessex Diversionary Route

slide-21
SLIDE 21

/ 21

  • Whiteball Tunnel: Complete
  • Athelney and Cogload Junction: Complete
  • Dawlish Stage 1 works: Complete
  • Cornwall resignalling: Underway
  • Chipping Sodbury: Underway
  • Flax Bourton: Underway
  • Patchway Tunnel: Underway
  • Cowley Bridge: Detailed design complete and approval

anticipated for March 2016

  • Hele & Bradninch: In design stage

Summary Status

slide-22
SLIDE 22

/

Exeter to Newton Abbot

22

slide-23
SLIDE 23

/ 23

  • Dawlish Sea Wall works and repair to cliffside – complete
  • Sea wall replaced and track reinstated
  • C.100,000 tonnes of material removed
  • Sea wall walk raised to high level to provide additional

protection

Exeter to Newton Abbot

slide-24
SLIDE 24

/ Flood Resilience Programme Update 26 January 2015 24

  • 20 miles of Western Route
  • 5 Line of Route Sections
  • Evaluation of existing asset condition
  • Optioneering process
  • 100 year resilience options including climate

change

  • Environmental Considerations

Ex2NA: Long Term

slide-25
SLIDE 25

/ 25

  • Geotechnical study took place 2015 to determine long-term

resilience measures necessary for the line

  • Reporting to DfT soon following optioneering

Ex2NA: Long Term

slide-26
SLIDE 26

/ 26

Next steps: Ground Investigation Works complete Summer ’16 Scoping & Option Selection Phase completed by Spring 2016 Final Option Selection Report to be issued May 2016 Currently no further funding for remainder of CP5 (2 years)

  • ther than reactive response to repair failures

Current funding situation means that Project will be paused from Autumn 2016 until commencement of CP6 (2019) assuming that DfT approves

Ex2NA: Long Term

slide-27
SLIDE 27

/ 27

  • Longer ‘alternative route’ study completed in June 2014 and

delivered to DfT – now with Peninsula Rail Task Force

Exeter to Plymouth: Alternative Route Study

slide-28
SLIDE 28

/ 28

  • GWR funded, through the Department for Transport, new

study into delivering infrastructure interventions to support the AT300 reduced journey times by 2018.

Line Speed Improvements to SW

slide-29
SLIDE 29

/ 29

For the introduction of cascaded Diesel Multiple Units

Preparation Works

slide-30
SLIDE 30

/

£45m now for GRIP 3-5 Development and advanced works awaiting signoff from DfT £15m funding from Cornwall CC being sourced to deliver Stage 1, comprising additional signalling between Menheniot and Cambourne to enable a 30-min frequency between Plymouth and Penzance

30

Cornwall Resignalling

slide-31
SLIDE 31

/ 31

There has never been a better time to be involved with our nation’s railways

“ “

Questions