n lynn street esplanade and custis trail improvements
play

N. Lynn Street Esplanade and Custis Trail Improvements 100% - PowerPoint PPT Presentation

Capital Projects Update: N. Lynn Street Esplanade and Custis Trail Improvements 100% Engineering Design - Progress Report UPC 70762 Locally Administered PE Phase VDOT Administered CN Phase 4/6/17 1 Project Overview The Lynn Street


  1. Capital Projects Update: N. Lynn Street Esplanade and Custis Trail Improvements 100% Engineering Design - Progress Report – UPC 70762 – Locally Administered PE Phase VDOT Administered CN Phase 4/6/17 1

  2. Project Overview The Lynn Street Esplanade and Custis Trail Improvements project is a pedestrian and bicycle safety, traffic management and street beautification initiative located in Rosslyn. The project incorporates findings from the 1999 Esplanade Study, (A) Lynn Street Esplanade: North Lynn Street from the 2003 Rosslyn Circle Safety eastbound Lee Highway to westbound Lee Study and the 2006 Lynn Street Highway. Esplanade Preliminary Design (B) Custis Trail: Westbound Lee Highway from Study. N. Lynn Street to N. Oak Street. 2

  3. Project Location : (A) Lynn Street Esplanade: North Lynn Street from eastbound Lee Highway to westbound Lee Highway (B) Custis Trail: westbound Lee Highway from N. Lynn Street to N. Oak Street. N B A 3

  4. Project Location Street View : (A) Lynn Street Esplanade: North Lynn Street from eastbound Lee Highway to westbound Lee Highway 4

  5. Project Location Street View : (B) Custis Trail: westbound Lee Highway from N. Lynn Street to N. Oak Street. 5

  6. The Lynn Street Esplanad e (A) Project includes: • Widened sidewalks and larger pedestrian and (A) Lynn Street Esplanade bike waiting areas (B) Custis Trail • 11’ traffic lanes • Upgraded traffic signals and new signage • On-street bike lane on Lynn Street • Upgraded street lights • “Corridor of Light” public art elements at the four corners of the I-66 bridge • Custom fencing • Landscaping 6

  7. N. Lynn Street Bridge Improvements (A) N EB Lee Highway Gateway Park 7

  8. East side of Lynn Street Improvements (A) N Plan and elevation showing new bridge barrier, custom fence , 20’ wide sidewalk and integrated sculptures. 8

  9. East side Lynn Street (B) NE Corner Luminous Body Foundation and Lighting N 9

  10. West Side Lynn Street / Gateway Park (A) Plan and Elevation Graphics N 10

  11. Sculpture Locations: Foundations in scope of work, Sculptures by others N 11

  12. East side Lynn Street Southeast corner of Lynn Street and Lee Highway Sculptures by others / NIC 12

  13. Semi-Custom Fence Full size mock-up 15

  14. Custis Trail Improvements (B) Project area includes: • Bicycle and pedestrian facility upgrades • Intersection improvement at Lee Highway and (A) Lynn Street Esplanade (B) Custis Trail N. Lynn Street • Trail widening to 16’ • Increased trail separation from traffic • Westbound lane reduction from Ft. Myer Drive to N. Oak Street • Curb extensions and wider curb ramps • New traffic and dedicated bike signals • New streetlights on both sides of westbound Lee Highway 16

  15. Overview - Custis Trail and Westbound Lee Highway Improvements (B) N • Planned 16’ wide trail with 6 - foot buffer (existing 10’ & 3’buffer) • VDOT approved lane reduction on westbound Lee Highway provides space for wider trail and improved sight distances • Improved pedestrian queuing areas at street crosswalks • Upgraded traffic and trail signals at major intersections N. Oak Street to N. Lynn Street 17

  16. Custis Trail at N. Lynn Street (B) • Reduced crossing distances N • New traffic and trail signals • Larger trail queuing areas • Barrier removed for Improved visibility of trail users • Tighter corners to slow traffic in pedestrian areas 18

  17. Custis Trail at Fort Myer Drive (B) N Dashed lines show existing curb location 19

  18. Custis Trail at Marriot Entrance (B) . N N. Nash Street and Marriot Entrance 20

  19. Existing Custis Trail – N. Fort Myer Drive to N. Oak Street (B) 36’ 3’ 10’ 21

  20. Approved Lane Reduction – N. Fort Myer Drive to N. Oak Street (B) 22

  21. Project Status Changes to the Construction Phase VDOT has agreed to transition the construction phase of work from Arlington to VDOT. County staff has accepted this option and has identified multiple reasons it is in the best interest of the County: • VDOT has greater construction management capacity for projects of this scale • Structural modifications to the VDOT bridge over I-66 are part of their work • All work is being performed in VDOT right of way • Risk management related to proximity to I-66 tunnel would be conveyed to VDOT 23

  22. Project Schedule • Updated Signed and Sealed Plans Submission: March 2, 2017 • Construction Advertisement: October 2017 • Project bidders On-Site Show Date: Mid-October 2017 • Bid Opening Date December 2017 • Executed Contract (Bid Date + 60 days) February 2018 • NTP** (Contract Execution + 15 Days) Mid-February 2018 • Duration of Construction: Two years • Substantial Completion Date: February 2020 24

  23. For More Information Visit our project webpage: projects.arlingtonva.us/projects/lynn-street-esplanade-custis-trail-improvements/ Thank you! End of Presentation 25

  24. Project History 2/1999 CB appropriates $50K of the Rosslyn Fund to prepare a study for Improvements to Rosslyn. The original Rosslyn Esplanade Study completed – Simple concepts show ways to better link Rosslyn with 8/1999 the Potomac River. Study presented to the public and the Waterview SP committee. 7/2000 CB approves Waterview SP#25. $3.6M for the development of two offsite projects: - Improvements at 19 th and Kent Street - Improvements to N. Lynn Street 2/2002 Rosslyn Circle Safety Study Ph I, completed and presented to the Pedestrian Advisory Committee. 8/2003 Rosslyn Circle Safety Study Phase II completed. Explored additional bike and pedestrian options around Rosslyn Circle and along the Custis Trail. Planning work starts for19 th and Kent Street Improvements. 12/2004 Engineering design starts for 19 th and Kent Street. 2/2005 6/2005 I-66 Entry Ramp Study completed 11/2005 CB approves Contract with Toole Design Group for Lynn Street Planning and Environmental Services. Project stakeholders include VDOT, NPS, Civic Associations and Rosslyn Renaissance. 3/2006 JBG Public Arts contribution linked to the Lynn Street project. 4/2006 Lynn Street design charrette completed 7/2006 NEPA / Environmental Assessment completed. 26

  25. Project History (cont.) 4/2006 Lynn Street public engagement / design charrette completed. 2/2007 Lynn Street Esplanade Planning / Conceptual Design Completed. 2/2008 All Development Condition Funds received from JBG. 12/2008 Lynn and Custis Trail PE Phase Authorized by VDOT. 6/2009 MWCOG TLC Arlington Trail Study completed for Custis Trail improvements from N. Scott St. to N. Lynn St 19 th and Kent Street Improvements complete. 3/2009 11/2009 CB approves contract with Toole Engineering for Design Services for Lynn and WB Lee Highway and Custis Trail Improvements 2/2010 Lynn Street and Custis Trail 25% engineering design complete 6/2010 CB approves revision to VDOT Project Funding Agreement to combine the Rosslyn Circle Improvements project with the Lynn Street Esplanade Project. 12/2010 Scope changed to remove proposed improvements on NPS property. 5/2011 CB approves design contract amendment #1 for additional traffic analysis, geotechnical work and survey. 1/2013 60% Plans complete 9/2013 CB approves design contract amendment #2 for major geometry changes as requested by VDOT, coordination with artist and new signals on westbound Lee Highway. 4/2014 CB approves Amendment #3 for additional design services for modifications to the Lynn street Bridge barrier wall and water main relocation design. 27 7/2015 90% plans submitted to VDOT and Arlington County 8/9/2016 100% Plans submitted to VDOT

  26. Project History (cont.) 8/2016 100% Plans submitted to VDOT 9/2016 VDOT Risk Assessment and Pre Advertisement Conf. Complete 12/2016 Final VDOT comments Addressed and Plan Set resubmitted 2/2017 VDOT central Office approves Project for Advertisment 6/2017 Dominion Power Undergrounding work 90% complete 3/2017 Construction Advertised By VDOT 4/2017 Bid opening / One bid received 5/2017 Bid rejected / Contractor not qualified by VDOT for Project work over $1M 6/2017 Plans updated to address questions received during advertisement and in preparation for rebid. 7/2017 New Schedule set for re-advertisement in October 2017 28

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend