1
Capital Projects Update:
- N. Lynn Street Esplanade and
Custis Trail Improvements
Advertisement for Construction - Progress Report –
UPC Design 70762 / CN 109813 Locally Administered PE Phase VDOT Administered CN Phase
4-9-2018
N. Lynn Street Esplanade and Custis Trail Improvements Advertisement - - PowerPoint PPT Presentation
Capital Projects Update: N. Lynn Street Esplanade and Custis Trail Improvements Advertisement for Construction - Progress Report UPC Design 70762 / CN 109813 Locally Administered PE Phase VDOT Administered CN Phase 4-9-2018 1 Project
1
UPC Design 70762 / CN 109813 Locally Administered PE Phase VDOT Administered CN Phase
4-9-2018
2
(A) Lynn Street Esplanade: North Lynn Street from eastbound Lee Highway to westbound Lee Highway (B) Custis Trail: Westbound Lee Highway from
3
(A) Lynn Street Esplanade: North Lynn Street from eastbound Lee Highway to westbound Lee Highway (B) Custis Trail: westbound Lee Highway from N. Lynn Street to N. Oak Street.
4
(A) Lynn Street Esplanade: North Lynn Street from eastbound Lee Highway to westbound Lee Highway
5
(B) Custis Trail: westbound Lee Highway from N. Lynn Street to N. Oak Street.
6
(A) Lynn Street Esplanade (B) Custis Trail
7
Gateway Park EB Lee Highway
8
Plan and elevation showing new bridge barrier, custom fence, 20’ wide sidewalk and integrated sculptures
9
10
11
Foundations in scope of work, Sculptures by others
12
Southeast corner of Lynn and Lee Highway Sculptures by others / NIC
15
Full size mock-up
16
(A) Lynn Street Esplanade (B) Custis Trail
17
space for wider trail and improved sight distances
N
18
Improved visibility of trail users
in pedestrian areas
19
Dashed lines show existing curb location
20
21
22
23
In 2017, The construction phase of the project was transferred from Arlington to VDOT.
24
Design Plans Completed and sent to VDOT:
Project Advertised for Construction:
1st Bid Opening Date / Project re-bid due to low bid activity
2nd Bid opening: .
VDOT has Approved Contract for Construction
Planned Construction Start:
Duration of Construction:
Substantial Completion Date:
25
projects.arlingtonva.us/projects/lynn-street-esplanade-custis-trail-improvements/ Thank you!
End of Presentation
26
2/1999 CB appropriates $50K of the Rosslyn Fund to prepare a study for Improvements to Rosslyn. 8/1999 The original Rosslyn Esplanade Study completed – Simple concepts show ways to better link Rosslyn with the Potomac River. Study presented to the public and the Waterview SP committee. 7/2000 CB approves Waterview SP#25. $3.6M for the development of two offsite projects:
2/2002 Rosslyn Circle Safety Study Ph I, completed and presented to the Pedestrian Advisory Committee. 8/2003 Rosslyn Circle Safety Study Phase II completed. Explored additional bike and pedestrian options around Rosslyn Circle and along the Custis Trail. 12/2004 Planning work starts for19th and Kent Street Improvements. 2/2005 Engineering design starts for 19th and Kent Street. 6/2005 I-66 Entry Ramp Study completed 11/2005 CB approves Contract with Toole Design Group for Lynn Street Planning and Environmental Services. Project stakeholders include VDOT, NPS, Civic Associations and Rosslyn Renaissance. 3/2006 JBG Public Arts contribution linked to the Lynn Street project. 4/2006 Lynn Street design charrette completed 7/2006 NEPA / Environmental Assessment completed.
27
4/2006 Lynn Street public engagement / design charrette completed. 2/2007 Lynn Street Esplanade Planning / Conceptual Design Completed. 2/2008 All Development Condition Funds received from JBG. 12/2008 Lynn and Custis Trail PE Phase Authorized by VDOT. 6/2009 MWCOG TLC Arlington Trail Study completed for Custis Trail improvements from N. Scott St. to N. Lynn St 3/2009 19th and Kent Street Improvements complete. 11/2009 CB approves contract with Toole Engineering for Design Services for Lynn and WB Lee Highway and Custis Trail Improvements 2/2010 Lynn Street and Custis Trail 25% engineering design complete 6/2010 CB approves revision to VDOT Project Funding Agreement to combine the Rosslyn Circle Improvements project with the Lynn Street Esplanade Project. 12/2010 Scope changed to remove proposed improvements on NPS property. 5/2011 CB approves design contract amendment #1 for additional traffic analysis, geotechnical work and survey. 1/2013 60% Plans complete 9/2013 CB approves design contract amendment #2 for major geometry changes as requested by VDOT, coordination with artist and new signals on westbound Lee Highway. 4/2014 CB approves Amendment #3 for additional design services for modifications to the Lynn street Bridge barrier wall and water main relocation design. 7/2015 90% plans submitted to VDOT and Arlington County 8/9/2016 100% Plans submitted to VDOT
28
8/2016 100% Plans submitted to VDOT 9/2016 VDOT Risk Assessment and Pre Advertisement Conf. Complete 12/2016 Final VDOT comments Addressed and Plan Set resubmitted 2/2017 VDOT central Office approves Project for Advertisment 6/2017 Dominion Power Undergrounding work 90% complete 3/2017 Construction Advertised By VDOT 4/2017 Bid opening / One bid received 5/2017 Bid rejected / Contractor not qualified by VDOT for Project work over $1M 6/2017 Plans updated to address questions received during advertisement and in preparation for rebid. 7/2017 New Schedule set for re-advertisement in November 2017 1/2018 New Bid opening Date 3/2018 Construction Contract awarded by VDOT 4/2018 Planned Pre-construction Conference 5/2018 Planned Construction Start