municipal collection system wastewater treatment plant
play

Municipal Collection System &Wastewater Treatment Plant Town of - PowerPoint PPT Presentation

Municipal Collection System &Wastewater Treatment Plant Town of Woodhull Agenda Introduction Project History & Project Status Project Review Construction Schedule & Overview Property Disturbance &


  1. Municipal Collection System &Wastewater Treatment Plant Town of Woodhull

  2. Agenda Introduction ◼ Project History & Project Status ◼ Project Review ◼ Construction Schedule & Overview ◼ Property Disturbance & Restoration ◼ Wastewater Service & Connection ◼ Comments & Questions ◼

  3. Introduction Town of Woodhull Scott Grant, Town Supervisor ◼ Twig Terwilliger, Town of Woodhull ◼ Hunt Engineers, Architects, Land Surveyors & Landscape Architects, DPC Christopher L. Wood, Project Manager ◼ Charles Franzese, Construction Administrator ◼ Aaron Vergason, Construction Manager/Inspector ◼ Rick Pope, King Consulting Engineers, Construction Inspector ◼ Vacri Construction Corporation Matthew Thomas, Project Manager ◼ Andrew Breznay, Resident Superintendent ◼

  4. Project History & Status 2008 Board Conceptualized Project & Completed Feasibility Study ◼ 2010 Submitted for Original Funding ◼ 2012 Received Initial Funding Offer ◼ 2012 Town Board Acceptance of Project ◼ 2012 Sewer District Formation ◼ 2013 Project Funding Obtained ◼ NYS Environmental Facilities Corporation ❑ 2014 Original Engineering Design & Securing Easements ◼ 2016-2017 Additional Funding Submitted & Secured ◼ NYS WQIA & CDBG ❑ 2018 Updated Engineering Design/Bidding ◼ October 2018 Contract Awards ◼ April 2019 Start of Construction ◼

  5. Service Area

  6. Construction Contracts Multi-Prime Contracts for Project Contract #1A: General Construction Treatment Facility ◼ Contractor: Vacri Construction Corporation ❑ Contract #1B: Electrical Treatment Facility ◼ Contractor: M.W. Control Services, Inc ❑ Contract #1C: Mechanical/HVAC Treatment Facility ◼ Contractor: Kimble Inc. ❑ Contract #1D: Plumbing Treatment Facility ◼ Contractor: Kimble Inc. ❑ Contract #2: Municipal Collection System ◼ Contractor: Vacri Construction Corporation ❑

  7. Construction Schedule & Operation Typical Hours of Operation ◼ 8-10 hours per day, 5 days per week; 7:00 am to 3:30 pm ❑ April 2019 - Start of Construction ◼ May 2019 – August 2019 – Treatment Plant Construction ◼ April 2019 – November 2019 Collection System Construction ◼ August 2019 - Treatment Plant Commissioning/Operational ◼ August 2019 – November 2019 – Sewer Lateral Installation ◼ November 2019 – General Restoration ◼ December 2019 - March 2019 - Winter Shutdown ◼ April 2020 – Public Meeting (Restoration Concerns) ◼ April 2020 – June 2020 - Final Restoration ◼

  8. Property Disturbance and Restoration ◼ Contractor shall work with landowner to clear path for sewer lateral piping and septic tank decomissioning. Contractor to remove fencing, clear trees, etc. Fencing shall be reset ◼ Town, Contractor & Engineer understand the sensitivity of construction on private property and its impact. A 20 ft. Construction Easement has been obtained ◼ Contractor shall complete activities within construction easement. ◼ If contractor needs to access areas outside of easement, owner will be contacted for approval. Contractor will not utilize private utilities ◼ Private Utilities will be protected if locations are known ◼

  9. Property Disturbance and Restoration ◼ Contractor will complete general restoration of sewer laterals as work is completed. General restoration shall consist of backfilling trench, and general ❑ grading to allow property owner to access all areas of yard. ◼ Contractor shall re-enter private parcels to complete restoration and “punch list” items after natural settlement has occurred and to place final seed, mulch and/or plant shrubbery/trees as part of project.

  10. Property Disturbance and Restoration ◼ Town has developed a protocol to address construction related issues if they should arise. Submit concern via email ◼ WoodhullSewer@gmail.com ◼ Contact Construction Manager/Inspector ◼ Aaron Vergason, HUNT-EAS: (607) 481-3937 ◼ Rick Pope, King Consulting Engineers: (716) 800-9721 ◼ Visit/Call Town Hall, to add concern to project log book ◼ ◼ It is Important that your concerns/issues are brought to our attention immediately not after construction is complete. ◼ It should be noted that the entire route will be videotaped before and after construction to document site conditions ◼ Prior to closeout of construction the Town will conduct a Public Meeting to confirm all concerns have been addressed.

  11. Comments & Questions

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend