Municipal Collection System &Wastewater Treatment Plant Town of - - PowerPoint PPT Presentation

municipal collection system wastewater treatment plant
SMART_READER_LITE
LIVE PREVIEW

Municipal Collection System &Wastewater Treatment Plant Town of - - PowerPoint PPT Presentation

Municipal Collection System &Wastewater Treatment Plant Town of Woodhull Agenda Introduction Project History & Project Status Project Review Construction Schedule & Overview Property Disturbance &


slide-1
SLIDE 1

Municipal Collection System &Wastewater Treatment Plant

Town of Woodhull

slide-2
SLIDE 2

Agenda

Introduction

Project History & Project Status

Project Review

Construction Schedule & Overview

Property Disturbance & Restoration

Wastewater Service & Connection

Comments & Questions

slide-3
SLIDE 3

Introduction

Town of Woodhull

Scott Grant, Town Supervisor

Twig Terwilliger, Town of Woodhull

Hunt Engineers, Architects, Land Surveyors & Landscape Architects, DPC

Christopher L. Wood, Project Manager

Charles Franzese, Construction Administrator

Aaron Vergason, Construction Manager/Inspector

Rick Pope, King Consulting Engineers, Construction Inspector

Vacri Construction Corporation

Matthew Thomas, Project Manager

Andrew Breznay, Resident Superintendent

slide-4
SLIDE 4

Project History & Status

2008 Board Conceptualized Project & Completed Feasibility Study

2010 Submitted for Original Funding

2012 Received Initial Funding Offer

2012 Town Board Acceptance of Project

2012 Sewer District Formation

2013 Project Funding Obtained

NYS Environmental Facilities Corporation

2014 Original Engineering Design & Securing Easements

2016-2017 Additional Funding Submitted & Secured

NYS WQIA & CDBG

2018 Updated Engineering Design/Bidding

October 2018 Contract Awards

April 2019 Start of Construction

slide-5
SLIDE 5

Service Area

slide-6
SLIDE 6

Construction Contracts

Multi-Prime Contracts for Project

Contract #1A: General Construction Treatment Facility

Contractor: Vacri Construction Corporation

Contract #1B: Electrical Treatment Facility

Contractor: M.W. Control Services, Inc

Contract #1C: Mechanical/HVAC Treatment Facility

Contractor: Kimble Inc.

Contract #1D: Plumbing Treatment Facility

Contractor: Kimble Inc.

Contract #2: Municipal Collection System

Contractor: Vacri Construction Corporation

slide-7
SLIDE 7

Construction Schedule & Operation

Typical Hours of Operation

8-10 hours per day, 5 days per week; 7:00 am to 3:30 pm

April 2019 - Start of Construction

May 2019 – August 2019 – Treatment Plant Construction

April 2019 – November 2019 Collection System Construction

August 2019 - Treatment Plant Commissioning/Operational

August 2019 – November 2019 – Sewer Lateral Installation

November 2019 – General Restoration

December 2019 - March 2019 - Winter Shutdown

April 2020 – Public Meeting (Restoration Concerns)

April 2020 – June 2020 - Final Restoration

slide-8
SLIDE 8

Property Disturbance and Restoration

◼ Contractor shall work with landowner to clear path for

sewer lateral piping and septic tank decomissioning. Contractor to remove fencing, clear trees, etc. Fencing shall be reset

◼ Town, Contractor & Engineer understand the sensitivity

  • f construction on private property and its impact.

A 20 ft. Construction Easement has been obtained

Contractor shall complete activities within construction easement. If contractor needs to access areas outside of easement, owner will be contacted for approval.

Contractor will not utilize private utilities

Private Utilities will be protected if locations are known

slide-9
SLIDE 9

Property Disturbance and Restoration

◼ Contractor will complete general restoration of sewer laterals

as work is completed.

General restoration shall consist of backfilling trench, and general grading to allow property owner to access all areas of yard.

◼ Contractor shall re-enter private parcels to complete

restoration and “punch list” items after natural settlement has

  • ccurred and to place final seed, mulch and/or plant

shrubbery/trees as part of project.

slide-10
SLIDE 10

Property Disturbance and Restoration

◼ Town has developed a protocol to address construction

related issues if they should arise.

Submit concern via email

WoodhullSewer@gmail.com

Contact Construction Manager/Inspector

Aaron Vergason, HUNT-EAS: (607) 481-3937

Rick Pope, King Consulting Engineers: (716) 800-9721

Visit/Call Town Hall, to add concern to project log book

◼ It is Important that your concerns/issues are brought to our

attention immediately not after construction is complete.

◼ It should be noted that the entire route will be videotaped

before and after construction to document site conditions

◼ Prior to closeout of construction the Town will conduct a

Public Meeting to confirm all concerns have been addressed.

slide-11
SLIDE 11

Comments & Questions