Municipal Collection System &Wastewater Treatment Plant Town of - - PowerPoint PPT Presentation
Municipal Collection System &Wastewater Treatment Plant Town of - - PowerPoint PPT Presentation
Municipal Collection System &Wastewater Treatment Plant Town of Woodhull Agenda Introduction Project History & Project Status Project Review Construction Schedule & Overview Property Disturbance &
Agenda
◼
Introduction
◼
Project History & Project Status
◼
Project Review
◼
Construction Schedule & Overview
◼
Property Disturbance & Restoration
◼
Wastewater Service & Connection
◼
Comments & Questions
Introduction
Town of Woodhull
◼
Scott Grant, Town Supervisor
◼
Twig Terwilliger, Town of Woodhull
Hunt Engineers, Architects, Land Surveyors & Landscape Architects, DPC
◼
Christopher L. Wood, Project Manager
◼
Charles Franzese, Construction Administrator
◼
Aaron Vergason, Construction Manager/Inspector
◼
Rick Pope, King Consulting Engineers, Construction Inspector
Vacri Construction Corporation
◼
Matthew Thomas, Project Manager
◼
Andrew Breznay, Resident Superintendent
Project History & Status
◼
2008 Board Conceptualized Project & Completed Feasibility Study
◼
2010 Submitted for Original Funding
◼
2012 Received Initial Funding Offer
◼
2012 Town Board Acceptance of Project
◼
2012 Sewer District Formation
◼
2013 Project Funding Obtained
❑
NYS Environmental Facilities Corporation
◼
2014 Original Engineering Design & Securing Easements
◼
2016-2017 Additional Funding Submitted & Secured
❑
NYS WQIA & CDBG
◼
2018 Updated Engineering Design/Bidding
◼
October 2018 Contract Awards
◼
April 2019 Start of Construction
Service Area
Construction Contracts
Multi-Prime Contracts for Project
◼
Contract #1A: General Construction Treatment Facility
❑
Contractor: Vacri Construction Corporation
◼
Contract #1B: Electrical Treatment Facility
❑
Contractor: M.W. Control Services, Inc
◼
Contract #1C: Mechanical/HVAC Treatment Facility
❑
Contractor: Kimble Inc.
◼
Contract #1D: Plumbing Treatment Facility
❑
Contractor: Kimble Inc.
◼
Contract #2: Municipal Collection System
❑
Contractor: Vacri Construction Corporation
Construction Schedule & Operation
◼
Typical Hours of Operation
❑
8-10 hours per day, 5 days per week; 7:00 am to 3:30 pm
◼
April 2019 - Start of Construction
◼
May 2019 – August 2019 – Treatment Plant Construction
◼
April 2019 – November 2019 Collection System Construction
◼
August 2019 - Treatment Plant Commissioning/Operational
◼
August 2019 – November 2019 – Sewer Lateral Installation
◼
November 2019 – General Restoration
◼
December 2019 - March 2019 - Winter Shutdown
◼
April 2020 – Public Meeting (Restoration Concerns)
◼
April 2020 – June 2020 - Final Restoration
Property Disturbance and Restoration
◼ Contractor shall work with landowner to clear path for
sewer lateral piping and septic tank decomissioning. Contractor to remove fencing, clear trees, etc. Fencing shall be reset
◼ Town, Contractor & Engineer understand the sensitivity
- f construction on private property and its impact.
◼
A 20 ft. Construction Easement has been obtained
◼
Contractor shall complete activities within construction easement. If contractor needs to access areas outside of easement, owner will be contacted for approval.
◼
Contractor will not utilize private utilities
◼
Private Utilities will be protected if locations are known
Property Disturbance and Restoration
◼ Contractor will complete general restoration of sewer laterals
as work is completed.
❑
General restoration shall consist of backfilling trench, and general grading to allow property owner to access all areas of yard.
◼ Contractor shall re-enter private parcels to complete
restoration and “punch list” items after natural settlement has
- ccurred and to place final seed, mulch and/or plant
shrubbery/trees as part of project.
Property Disturbance and Restoration
◼ Town has developed a protocol to address construction
related issues if they should arise.
◼
Submit concern via email
◼
WoodhullSewer@gmail.com
◼
Contact Construction Manager/Inspector
◼
Aaron Vergason, HUNT-EAS: (607) 481-3937
◼
Rick Pope, King Consulting Engineers: (716) 800-9721
◼
Visit/Call Town Hall, to add concern to project log book
◼ It is Important that your concerns/issues are brought to our
attention immediately not after construction is complete.
◼ It should be noted that the entire route will be videotaped
before and after construction to document site conditions
◼ Prior to closeout of construction the Town will conduct a
Public Meeting to confirm all concerns have been addressed.