INTERIOR ENERGY PROJECT AIDEA UPDATE
October 23, 2019
INTERIOR ENERGY PROJECT AIDEA UPDATE October 23, 2019 Interior - - PowerPoint PPT Presentation
INTERIOR ENERGY PROJECT AIDEA UPDATE October 23, 2019 Interior Energy Project PURPOSE AND GOALS . . . to bring low-cost energy to as many residents and businesses of Interior Alaska as possible, as quickly as possible ... Stabilize the
October 23, 2019
giving Interior residents a natural gas heating option for the first time.
utility power via transfers from the City of Fairbanks and the City of North Pole and established the Interior Alaska Natural Gas Utility (IGU).
providing AIDEA with the financing package to finance and develop the supply and delivery of natural gas to Interior Alaska.
requiring the AIDEA Board of Directors to approve, by resolution, a project plan prior to deploying additional financing.
to further the goals of the IEP and facilitate consolidation of the Interior gas utilities.
Agreement governing AIDEA’s financing of IGU; utilizing the tools established by the IEP.
Liquefaction
Transportation
Storage
Distribution
North Pole.
Expansion Area
Customer Conversion Program
Braemar Technical Services contracted to conduct the front-end engineering and design (FEED) for the expansion (100,000gpd) of the Titan liquefied natural gas facility. Scope includes:
tanks, new truck loading rack and power generation. (Complete)
budget to +/- 10% accuracy.
containment design
Transfer Skid – LNG Loading and Offloading Balance of Plant
issued 10/15/2019, with a target completion date of 9/30/2020
Fairbanks – 140+ Miles of Distribution Piping (1150 Customers)
Fairbanks – New Services IGU has started installing service lines in advance of the storage project completion. We have installed 50 new service lines this season.
North Pole – 73+ Miles of Distribution Piping
Quarter2020.
Agreement increasing the SETS loan by $10MM to $135MM on the same loan terms as the original $125MM.
Fitch rating agency and has received a preliminary rating assessment of Investment Grade on the planned 2019 Power Revenue Bonds ($60MM Par Issuance).
Bond Counsel in preparation of bond issuance.
Transition Plan
future supply
Planning to:
Put in a fence? Install amailbox? Build a patio ordeck? Plant trees or shrubbery? Excavate a new gardenarea? Install or maintain a septicsystem? Install awell?
Call the Alaska Digline at 811 at least 72 hours (3 Days) prior todigging and get your underground utility lines located and marked for free.