MPWSP Governance Committee Topic: Potrero Rd Test Well Permitting Contingency
April 16, 2014 Ian Crooks California American Water
MPWSP Governance Committee Topic: Potrero Rd Test Well Permitting - - PowerPoint PPT Presentation
MPWSP Governance Committee Topic: Potrero Rd Test Well Permitting Contingency April 16, 2014 Ian Crooks California American Water Potrero Road Site Benefits & Challenges Environmental Disturbed area - Parking lot and roadway
April 16, 2014 Ian Crooks California American Water
to higher cost
2
3
July April May June Aug. Sept. Oct. Nov.
30 Day Public Comment Period (5/2–6/1) Finalize Report (6/2- 6/20) 49-days maximum Coastal Commission to Hear Appeal (8/14 – 10/1) Draft Report & City Review Complete (Present - 4/30)
Continues with Coastal Commissi
Y/N
Potrero Timeline Marina CEMEX Timeline Dec. Jan.
8/20 2nd Council Mtg 8/7 1st Council Mtg 7/10 1st PC Mtg 7/24 2nd PC Mtg Project Description
Application Filed with County 4/17 – 5/15
Feb.
Prepare IS/EA w/ Lead Agencies (5/15 – mid Aug.) 30 Day Public Comment Period (Mid Aug to Mid Sept.) Prepare, Review, Finalize MND/FONSI (mid Sept – mid Nov.) Submit to Coastal Commission and State Lands Commission for hearing
CCC Meeting Feb. 2015 CCC Meeting Oct. 10/8-10
2015
Cemex Test Well Construction Window $50k $150k $180k $220k $270k $300k
4 4
Cemex Slant Well Permitting
2018 2017 2016 2015 2014
Draft EIR CPUC EIR & CPCN APPROVAL Pipelines, Terminal Reservoirs, BPS Construction
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J
60% Design 09-2014 90% Plant Design 12-2014 Final Design 02-2016
Full Start-up June 2018
GWR Decision 11-2015 30% Design 06-2014 Value Eng. 06-2014
Desal Plant Construction Desal Plant Design/Permitting
NTP Start Construction 02-2016 Pipelines, Terminal Reservoirs, BPS Design, Permitting & Contracts
Q3-2014
Coastal Commission MPWSP EIR Approval CCC Approval October
Updated April 14, 2014
Slant Wells Phase 1 Test Slant Well Construction Slant Wells Phase 2 Slant Wells Phase 3 (if needed) Basis of Design Report 05-2014
Q1-2015
Note: The schedule is based on the information and assumptions available at time of update and is accurate to +/- 6 months.
Snowy Plover Nesting Season No Construction Activity Snowy Plover Nesting Season No Construction Activity Snowy Plover Nesting Season No Construction Activity
Potrero Rd Permitting
$150k
Marina Approval August
$300k $200k
Construction Operation SWRCB Current Deadline
!
5
6
Facing South Facing West Facing North Facing East
7
8