Former Potrero Power Plant Site Remediation
WELCOME PG&E Community Open House Former Potrero Power Plant - - PowerPoint PPT Presentation
WELCOME PG&E Community Open House Former Potrero Power Plant - - PowerPoint PPT Presentation
Former Potrero Power Plant Site Remediation WELCOME PG&E Community Open House Former Potrero Power Plant Site Remediation Former Potrero Power Plant Site Header 1 This is paragraph style 1 Photo taken: March 2012. Former Potrero Power
Former Potrero Power Plant Site Remediation
Header 1
This is paragraph style 1
Former Potrero Power Plant Site
Photo taken: March 2012.
Former Potrero Power Plant Site Remediation
What is a Manufactured Gas Plant (MGP)?
GAS RESIDENCES STREET LAMPS BUSINESSES
MANUFACTURING PROCESS
GAS HOLDER
COAL OR OIL
Former Potrero Power Plant Site Remediation
Goals
Fulfill our commitment to address impacts from historic MGP and power plant operations. Protect human health and the environment. Work collaboratively with stakeholders and the community. Protect the safety of the community and site workers. Allow for the productive re-use of the site.
Approximate boundaries shown. Map not to scale.
PG&E-Owned Properties NRG Potrero, LLC Owned Properties Port of San Francisco Property Impacted by Historical MGP Activities
2 3 R D S T . 2 2 N D S T . ILLINOIS ST. 3RD ST. TENNESSEE ST. OFFSHORE SEDIMENT AREA
(Cleanup Approach Approved / Cleanup Plan Pending)
Port Property
(Cleanup Plan Approved / In Design)
Station A (NRG Owned)
(Anticipated 2016 Closure / Completion)
Station A (PG&E Owned)
(Anticipated 2016 Closure / Completion)
Tank Farm
(Investigation Pending Tank Removal by NRG)
Northeast Area
(Cleanup Plan Approved / In Design)
Hoe Down Yard
(Cleanup Complete)
Former Power Generation Facility
(Investigation Completed)
Former Potrero Power Plant Site Remediation
Project Site
Switchyard/ Construction Yard
(Cleanup Complete)
2016 2017 2018 2019
NRG Potrero, LLC Owned Properties PG&E Owned Properties
Regulatory Closure Cleanup Plan Completion Public Comment Period Cleanup Plan Development Construction and Field Work Regulatory Closure Design / Permitting Contracting and Construction Permitting Timeline Under Development Design/Permitting Investigation and Risk Assessment Public Review and Regulatory Closure Regulatory Closure Construction and Field Work Regulatory Closure Cleanup Completed in 2012. Cleanup Completed in 2012. Contracting and Construction Permitting TANK FARM STATION A FMR POWER GENERATION FACILITY (UNIT 3) NORTHEAST AREA
(INCLUDING PORT PROPERTY)
OFFSHORE SEDIMENT AREA STATION A HOE DOWN YARD SWITCHYARD
Former Potrero Power Plant Site Remediation
Cleanup Timeline
■ Feasibility Study (FS) of Cleanup
Approach approved in 2015
■ Approved Cleanup Approach
addresses different conditions:
Nearshore Area Dredging of impacted sediments and capping with natural materials Northern Transition Area In-place treatment with activated carbon Southern Transition Area Monitored natural recovery
■ Next Steps
- Cleanup Plan review by Water Board: Fall 2016
- Public Comment Period /Public Meeting: Late-2016
View of Offshore Sediment Area
1 2 3
N
Port Property Station A Tank Farm Northeast Area Former Power Generation Facility
OFFSHORE SEDIMENT AREA
1 2 3
NRG Potrero, LLC Owned Properties Port of San Francisco Property Impacted by Historical MGP Activities Transition Areas Where Impacts Will be Addressed Shoreline and Nearshore Areas Where Impacts Will be Addressed
Former Potrero Power Plant Site Remediation
Offshore Sediment Area
■ Cleanup Plan approval: Summer 2016 ■ Cleanup Plan:
- A portion of MGP residues around
Pier 70 structures excavated
- A portion of MGP residues on Power Plant Property
treated in-place using cement mix (solidification) Durable cover installed/maintained
■ Active cleanup: 2017/2018 ■ Community Meeting before work starts
Port Property Station A Tank Farm Northeast Area Former Power Generation Facility
3
1 2 3
1 2 2
NRG Potrero, LLC Owned Properties Port of San Francisco Property Impacted by Historical MGP Activities Solidification Area Excavation Area
Former Potrero Power Plant Site Remediation
Northeast Area Cleanup
Tank Farm (NRG owned)
- Includes three large above-ground fuel tanks formerly
used to store fuel oil
- Investigation pending tank removal by NRG
Former Power Generation Facility (NRG owned)
- Includes the Unit 3 power plant and surrounding areas
- Soil and groundwater investigations complete
- PG&E, NRG and Water Board working to evaluate
results and plan for closure