MONTEREY PENINSULA WATER SUPPLY PROJECT UPDATE Add photo of pipeline - - PowerPoint PPT Presentation

monterey peninsula water supply project update
SMART_READER_LITE
LIVE PREVIEW

MONTEREY PENINSULA WATER SUPPLY PROJECT UPDATE Add photo of pipeline - - PowerPoint PPT Presentation

MONTEREY PENINSULA WATER SUPPLY PROJECT UPDATE Add photo of pipeline install MPWSP Governance Committee Meeting July 18, 2018 1 MPWSP ANTICIPATED SCHEDULE 2017 2018 2019 2020 2021 EIR/EIS AUTHORIZATIONS CDP CPCN IN- PWM SERVICE IN-


slide-1
SLIDE 1

Add photo of pipeline install

MPWSP Governance Committee Meeting July 18, 2018

1

MONTEREY PENINSULA WATER SUPPLY PROJECT UPDATE

slide-2
SLIDE 2

2017 2018 2019 2020 2021 AUTHORIZATIONS PWM MONTEREY PL & PS DESAL

EIR/EIS CPCN

IN- SERVICE

MPWSP ANTICIPATED SCHEDULE

CDP

IN- SERVICE

IN- SERVICE START CONSTRUCTI ON

slide-3
SLIDE 3

Status Update Pipeline and Pump Station

3

slide-4
SLIDE 4

8

Pipeline Bridge Crew

~6.5 miles of 36” pipe installed

Pump Station Crew

MONTEREY PIPELINE CONSTRUCTION

slide-5
SLIDE 5

ASR 5 & 6 RFPs

5

slide-6
SLIDE 6

ASR Wells 5 & 6 RFPs

  • ASR Well Drilling
  • Design – Bid - Build (DBB)
  • ASR Well Above Ground Facilities
  • Design - Build (DB)

Interconnects RR-B & HH-TG 6

slide-7
SLIDE 7

ASR Wells 5 & 6 Anticipated Schedule

7

Estimated Schedule Start Construction Q2 - Q3 2019 J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

Specs

Note: Aniticpated schedule is dependent on permit approvals and could shift by up to six months.

Start-up Site Prep Well Construction/Testing

Bidding

2017 2019 2020

PDR PDR

2018

Facility Construction

Bidding Design

ASR-5 and ASR-6 Wells Fitch Park ASR Facility

slide-8
SLIDE 8

GC Review of RFPs

8

slide-9
SLIDE 9

ASR Wells 5 & 6 RFP Evaluation Criteria

9

slide-10
SLIDE 10

Additional future RFPs

  • Castroville Pipeline
  • Satellite system interconnect pipelines
  • Slant Wells Civil & Electrical Work

Interconnects RR-B & HH-TG 10

slide-11
SLIDE 11

Q & A

11