MPWSP Governance Committee Meeting July 18, 2018
1
MONTEREY PENINSULA WATER SUPPLY PROJECT UPDATE Add photo of pipeline - - PowerPoint PPT Presentation
MONTEREY PENINSULA WATER SUPPLY PROJECT UPDATE Add photo of pipeline install MPWSP Governance Committee Meeting July 18, 2018 1 MPWSP ANTICIPATED SCHEDULE 2017 2018 2019 2020 2021 EIR/EIS AUTHORIZATIONS CDP CPCN IN- PWM SERVICE IN-
Add photo of pipeline install
MPWSP Governance Committee Meeting July 18, 2018
1
2017 2018 2019 2020 2021 AUTHORIZATIONS PWM MONTEREY PL & PS DESAL
EIR/EIS CPCN
IN- SERVICE
MPWSP ANTICIPATED SCHEDULE
CDP
IN- SERVICE
IN- SERVICE START CONSTRUCTI ON
3
8
Pipeline Bridge Crew
~6.5 miles of 36” pipe installed
Pump Station Crew
MONTEREY PIPELINE CONSTRUCTION
5
Interconnects RR-B & HH-TG 6
7
Estimated Schedule Start Construction Q2 - Q3 2019 J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Specs
Note: Aniticpated schedule is dependent on permit approvals and could shift by up to six months.
Start-up Site Prep Well Construction/Testing
Bidding
2017 2019 2020
PDR PDR
2018
Facility Construction
Bidding Design
ASR-5 and ASR-6 Wells Fitch Park ASR Facility
8
9
Interconnects RR-B & HH-TG 10
11