Upper Peninsula of Michigan November 2016 Existing power supply to - - PowerPoint PPT Presentation

upper peninsula of michigan
SMART_READER_LITE
LIVE PREVIEW

Upper Peninsula of Michigan November 2016 Existing power supply to - - PowerPoint PPT Presentation

Providing Reliable Energy to the Upper Peninsula of Michigan November 2016 Existing power supply to the Upper Peninsula We Energies purchased the Presque Isle Power Plant in 1988 Units 1 and 2 retired in 2007 Units 3 and 4 retired in


slide-1
SLIDE 1

Providing Reliable Energy to the Upper Peninsula of Michigan November 2016

slide-2
SLIDE 2

1

Existing power supply to the Upper Peninsula

 We Energies purchased the

Presque Isle Power Plant in 1988

 Units 1 and 2 retired in 2007  Units 3 and 4 retired in 2009  Anticipate retiring Units 5 – 9

by 2020

 New generation needed to replace

the units being retired

 Transmission constraints limit

ability to import power

slide-3
SLIDE 3

2

Providing a long-term energy solution

 Filed a proposal with Michigan Public Service Commission

in June 2016 to form a new utility (Upper Michigan Energy Resources Corporation) to serve region as part of an agreement reached with State of Michigan

 Executed power contract with Tilden Mine in August 2016

which allows customers of new utility to save on plant costs

 Agreement calls for new utility to construct, own and operate

approximately 170 megawatts (MW) of generation by 2019

slide-4
SLIDE 4

3

Site areas being considered

slide-5
SLIDE 5

4

Proposed generation solution

Reciprocating Internal Combustion Engines (RICE)

 Extremely reliable and flexible

  • perations

 Efficiency is maintained over a wide

  • utput range

 Low environmental impact and very

little water needed for operation

 Engines delivered and installed

in modules sized for the needed capacity

 Some natural gas and transmission

infrastructure needed

slide-6
SLIDE 6

5

slide-7
SLIDE 7

6

Site requirements

 Working on design and size  We are targeting approximately 130MW at this site

 Engine sizes being evaluated: 9MW or 18MW

 Plant size is expected to be 500 feet X 500 feet –

approximately 6 acres

 Engine building size to be refined once engines are selected –

generally we anticipate approximately 100 feet wide x 250 feet long x 35 feet high

 Another 5-10 acres needed for construction laydown and

parking

slide-8
SLIDE 8

7

Additional site features

 Small out building for storage tanks  Anticipate three exhaust stacks – approximately

150 feet high

 Radiator banks are sized to accommodate the heat release

from the engine – anticipate up to 400 feet long to accommodate a plant of this size

 A road will go around the plant for operating access and fire

response

slide-9
SLIDE 9

8

Sound

 Site design parameter

includes 50 decibel limit

 Once engines are selected,

site design will be refined to include a detailed sound modeling

Source: OSHA

slide-10
SLIDE 10

9

Example of a RICE generating station

Pioneer Generation Station – 110MW (12 units)

slide-11
SLIDE 11

10

Example of a RICE generating station

Tom Darte Energy Center – 25MW (3 Units)

slide-12
SLIDE 12

11

Next steps for selected site

 Continue to communicate with community officials

and residents

 Continue working on design and engineering plans  Obtain option to purchase land  Obtain local approvals and permits  File for regulatory approvals by early 2017  If approved, construction to begin late 2017 or

early 2018

 Operation anticipated in 2019

slide-13
SLIDE 13

12

A solution for the future

 Provides a long-term generation solution that

assures electric reliability in the Upper Peninsula

 Significantly reduces environmental emissions in

the region

 Provides tax benefits to the local host communities  Reduces the need for significant future

transmission investments

slide-14
SLIDE 14