Irfu.cea.fr
MM weekly meeting – 3rd of December 2013
ATLAS - NSW
(NEW SMALL WHEEL)
MICROMEGAS DETECTORS Status on mechanical prototypes construction @ Saclay
Patrick PONSOT for the Saclay ATLAS-Micromegas group
MICROMEGAS DETECTORS Status on mechanical prototypes construction @ - - PowerPoint PPT Presentation
ATLAS - NSW (NEW SMALL WHEEL) MICROMEGAS DETECTORS Status on mechanical prototypes construction @ Saclay Patrick PONSOT for the Saclay ATLAS-Micromegas group MM weekly meeting 3 rd of December 2013 Irfu.cea.fr Outline M4 construction
Irfu.cea.fr
MM weekly meeting – 3rd of December 2013
Patrick PONSOT for the Saclay ATLAS-Micromegas group
MM Weekly meeting - 3rd of December 2013 | PAGE 2 CEA-Saclay/DSM/Irfu - Patrick PONSOT
Gluing of the panels with the stiffback Tooling to integrate the 4 meshes during the assembly
machine
M4@Saclay)
MM Weekly meeting - 3rd of December 2013 | PAGE 3 CEA-Saclay/DSM/Irfu - Patrick PONSOT
are expected after the signing of the MoU
Sharing of the technicians with other projects In almost of the cases, impossible to machine the pieces inside our mechanical workshop Companies are not reactive for small production (e.g. we lost 6 weeks by waiting the delivery of the M4-frames)
The existing cleaning rooms are completely busy until 2017 We decided to build a new one dedicated to the assembly of large detectors Part of the time is dedicated to the definition of this new cleaning room ISO-7 (specifications to take in account the tooling that we need) Delivery of the cleaning room is expected on 2015 for production The module zero must be built in the same temporary room as for prototypes Increasing of the work to reinforce the cleanliness and to adapt the tooling for this temporary room.
MM Weekly meeting - 3rd of December 2013 | PAGE 4 CEA-Saclay/DSM/Irfu - Patrick PONSOT
and general drawings are ongoing
MM Weekly meeting - 3rd of December 2013 | PAGE 5 CEA-Saclay/DSM/Irfu - Patrick PONSOT
equipped with laminar airflux system cleanliness and tooling must be improved to build the M0
Gluing of the panels has just been begun +10 days Waiting for the 4 meshes and associate tooling done in the industry delivery expected on week 51 (last open week before Xmas vacation) Gluing of the pillars, mesh assembly, assembly of the module by gluing of the panels +10 days Due to the very bad tolerances that we found on the thickness of our aluminum honeycombs (~200 microns to compensate with the glue), few days have been dedicated to test the gluing procedure with the stiffback Bad result with the glue DP490 peeling is very easy and capillarity of the glue is very bad (not enough glue on the cells of the honeycombs) We decided to use the glue 2011 for the M4
MM Weekly meeting - 3rd of December 2013 | PAGE 6 CEA-Saclay/DSM/Irfu - Patrick PONSOT
~200 m
MM Weekly meeting - 3rd of December 2013 | PAGE 7 CEA-Saclay/DSM/Irfu - Patrick PONSOT
First drift panel made with 2x4 FR4 skins and aluminum honeycombs (glue 2011) has been glued on this morning (second step with the stiffback) Preparation of the second gluing step Vacuum bag on the stiffback
MM Weekly meeting - 3rd of December 2013 | PAGE 8 CEA-Saclay/DSM/Irfu - Patrick PONSOT
MM Weekly meeting - 3rd of December 2013 | PAGE 9 CEA-Saclay/DSM/Irfu - Patrick PONSOT
Simplified design just to be able to study the deformation of the panel with the tension of the mesh Common frame to close the gas-gap and to glue the mesh 4 enlarge frames (with mesh glued on it) have been
Delivery expected on week 51
Transfer frame is fixed on the mesh frame Mechanical adjustment to be in contact with the mesh during the gluing Cutting of the mesh Fixation on the panel Dismounting of the transfer frame and measurement of the deformation and of the tension
Source: Marabu
MM Weekly meeting - 3rd of December 2013 | PAGE 10 CEA-Saclay/DSM/Irfu - Patrick PONSOT
Mesh frame fixed on the transfer frame Enlarged frame with the mesh glued on it (provided by the industry) Transfer of the mesh
Vertical adjustment system
MM Weekly meeting - 3rd of December 2013 | PAGE 11 CEA-Saclay/DSM/Irfu - Patrick PONSOT
to evaluate the impact of the material on the layout
The main deformation is coming from the thermal loading 2 parameters must be taken in account: the thermal behavior of the assembly of the panels and the stiffness of the panels
estimated 17GPa but:
The segmentation has been changed (2 MM modules) The detail design was not taken in account (interconnections of the panel) Margin was applied on the boundary conditions: 2°C temperature gradient between the inner and outer panels (for commissioning on surface and running in the cavern) Don’t forget that we need to guaranty that we will have no failure during the assembly, storage and transportation
Qualification of the material and mechanical prototypes Full simulation of the MM sectors Identification of the margin to take the decision (Aluminum, Nomex or foam?)
MM Weekly meeting - 3rd of December 2013 | PAGE 12 CEA-Saclay/DSM/Irfu - Patrick PONSOT
Bending test (3 points) on a qualified testing machine (2 Instron machines at Saclay) Testing of 3 samples Dimensions of the samples : 110mmx17mmx~10mm Measurement of the displacement according to the loading until the destroying of the sample
FEA method to take in account the shear modulus, the poisson coefficients and the anisotropy of the material Glue film is not modeling but the level of the shear stress between honeycomb and the skins is relevant and must stay under the limit for the glue
Francesco and Stefano), we need to validate together the final protocol to qualify the material (additional test with larger samples?)
MM Weekly meeting - 3rd of December 2013 | PAGE 13 CEA-Saclay/DSM/Irfu - Patrick PONSOT
Honeycombs material Aluminum 5056
4.8mm/0.05m 130kg/m3 Nomex Dupont-Nemours 4.8mm/0.05mm 48kg/m3 Foam Rohacell
Equivalent Young modulus (Gpa) 24 8 ~5 Shear stress for the glue (Mpa) 27-48 20-32 11 Comment on destroying Breaking of the FR4 and of the gluing Breaking of the gluing Breaking of the FR4 and of the gluing
MM Weekly meeting - 3rd of December 2013 | PAGE 14 CEA-Saclay/DSM/Irfu - Patrick PONSOT
testing of the 3 panels assembly (first result presented by Fabien during the MM workshop on 5-6th of Nov.)
transmission of the deformation of the outer panel to the inner panel through the interconnections (glued pillars in the drift gap, Nomex honeycomb)
Measurement with local loading in the middle of the panel Calculation with thermal loading
direction)
possible), second with gluing of all the components
+2°C on all the top side
MM Weekly meeting - 3rd of December 2013 | PAGE 15 CEA-Saclay/DSM/Irfu - Patrick PONSOT
middle of the panel with sliding of the panels
local loading between pillars
Location of the pillars
Panels P1-M P1-S P2-M P2-S P6-M P6-S Top
Middle
Bottom
MM Weekly meeting - 3rd of December 2013 | PAGE 16 CEA-Saclay/DSM/Irfu - Patrick PONSOT
loading between pillars
increasing of the stiffness by interconnection of 2 panels
Location of the pillars
Panels P1-M P1-S P2-M P2-S P6-M P6-S Top
Middle
Bottom
MM Weekly meeting - 3rd of December 2013 | PAGE 17 CEA-Saclay/DSM/Irfu - Patrick PONSOT
the 3 panels)
Location of the pillars
Panels P1-S P2-S Middle point P6-S Top 0.008 0.013 0.026 0.017 Middle 0.005 0.007 0.012 0.011 Bottom 0.004 0.002 0.004 0.006 +2°C on all the top side
MM Weekly meeting - 3rd of December 2013 | PAGE 18 CEA-Saclay/DSM/Irfu - Patrick PONSOT
transmission of the deformation from the outer to the inner panels
a complete module
MM Weekly meeting - 3rd of December 2013 | PAGE 19 CEA-Saclay/DSM/Irfu - Patrick PONSOT
(limited range of the bearings)
machine (3 external targets will be added to have a common reference plan for the 2 measurements calculation is in progress
MM Weekly meeting - 3rd of December 2013 | PAGE 20 CEA-Saclay/DSM/Irfu - Patrick PONSOT
MM Weekly meeting - 3rd of December 2013 | PAGE 21 CEA-Saclay/DSM/Irfu - Patrick PONSOT
the M0 before delivery of the new cleaning room
collaboration
prototypes at Freiburg are available (validation is in progress calculation and feedback)
DSM Irfu SIS/LCAP (PC N°12, Bt 123) Patrick PONSOT Commissariat à l’énergie atomique et aux énergies alternatives Centre de Saclay | 91191 Gif-sur-Yvette Cedex
Etablissement public à caractère industriel et commercial | RCS Paris B 775 685 019
MM Weekly meeting - 3rd of December 2013
CEA-Saclay/DSM/Irfu - Patrick PONSOT | PAGE 22