MCHS Construction Project Update February 4, 2019 Construction - - PowerPoint PPT Presentation

mchs
SMART_READER_LITE
LIVE PREVIEW

MCHS Construction Project Update February 4, 2019 Construction - - PowerPoint PPT Presentation

MCHS Construction Project Update February 4, 2019 Construction Project Update Buildings CTEInterior first floor CMU walls to 95%. Second floor Slab on Deck is completed in area one. Metal Decking for second floor area two is at


slide-1
SLIDE 1

MCHS

Construction Project Update – February 4, 2019

slide-2
SLIDE 2

Construction Project Update

  • Buildings

– CTE…Interior first floor CMU walls to 95%. Second floor Slab on Deck is completed in area one. Metal Decking for second floor area two is at 85%. Critical second floor corridor CMU scheduled to begin next week. – CTE…Rain and cold continue to cause delays for project. Updated schedules to be presented at the next monthly meeting. – HS…Gymnasium West wall was in construction this month along with the locker rooms in Area A-1. Locker rooms in Area A-2 are still waiting on Slab on Grade pours. – HS…the high school has also suffered weather related delays this last month.

slide-3
SLIDE 3

Construction Project Update

  • Next 30 days

– Install decking and Slab on Metal in Area Two Second Floor. Begin critical second floor corridor CMU to joist bearing plates. – Continue spray foam insulation and exterior brick on CTE. – Begin structural steel installation at Main and Auxiliary Gymnasiums. – Continue final grade work on site. – Next Progress Meeting is scheduled for February 7, 2019.

slide-4
SLIDE 4

East Wall CTE – Industrial Maintenance/Welding

slide-5
SLIDE 5

North Wall - Welding

slide-6
SLIDE 6

North Wall Flex Lab – East Wall Construction Trades – Note Foam Insulation Progress

slide-7
SLIDE 7

West Wall Auto Mechanics – Note Brick Progress

slide-8
SLIDE 8

West Wall – Wood Working – Ag Science

slide-9
SLIDE 9

Southern Walls – CTE Building

slide-10
SLIDE 10

Area 1 Slab on Deck in progress

slide-11
SLIDE 11

Floor Deck Area 2 – Health Occupations

slide-12
SLIDE 12

Structural Steel for Flex Lab roll up doors

slide-13
SLIDE 13

Structural Steel for Corridor Area 2

slide-14
SLIDE 14

View into Flex Lab below

slide-15
SLIDE 15

Gymnasium walls in construction

slide-16
SLIDE 16

END – Questions?