Market Performance and Planning Forum July 30, 2013 Objective: - - PowerPoint PPT Presentation
Market Performance and Planning Forum July 30, 2013 Objective: - - PowerPoint PPT Presentation
Market Performance and Planning Forum July 30, 2013 Objective: Enable dialogue on implementation planning and market performance issues Review key market performance topics Share updates to 2013-2014 release plans, resulting from
Objective: Enable dialogue on implementation planning and market performance issues
- Review key market performance topics
- Share updates to 2013-2014 release plans, resulting
from stakeholders inputs
- Provide information on specific initiatives
– to support Market Participants in budget and resource planning
- Focus on implementation planning; not on policy
- Clarify implementation timelines
- Discuss external impacts of implementation plans
- Launch joint implementation planning process
Slide 2
Agenda
Slide 3
10:00- 10:05 Introduction, Agenda Mercy P. Helget 10:05 – 11:15 Market Performance and Quality Update Guillermo Bautista Alderete, Nan Liu 11:15 – 12:00 CMRI Report on Transmission Constraints Dede Subatki 12:00 – 1:00 Lunch 1:00 – 1:30 Policy Updates Brad Cooper 1:30 – 2:15 Technical Updates Khaled Abdul-Rahman, Li Zhou 2:15 – 2:30 Technical User Group Update Doug Walker 2:30 – 3:00 Release Plan Updates Janet Morris, June Xie
Agenda Agenda Agenda Agenda
Note: Agenda is subject to change.
Market Performance and Quality Update
Market Quality and Renewable Integration
Guillermo Bautista-Alderete Nan Liu
Slide 4
Slide 5
1. Hot topics and follow-up items 2. Market Metrics
- Price volatility and market convergence
- RT energy/congestion imbalance offset
- Convergence bidding
- Exceptional dispatch
- Bid cost recovery
- MIP gap
- Flex-ramp cost
3. Price Corrections
Hot topic and follow up items
- Summer update
- Pay for performance
- DA and RT prices
- Wind and solar generation
Page 6
Summer Update.
- Peak load occurred on June 28 at 45097 MW.
- There were adequate supply offered in both DA and RT
to meet demand.
- One area of concern is the amount of import declines
and curtailments in real-time (1000 MW).
- Additional imports and internal generations would be
required to meet real-time system demand.
- Incurred high RTCO.
Slide 7
Slide 8
Pay for Performance
1,000 2,000 3,000 4,000 5,000 6,000 7,000 8,000 1-Jun-13 3-Jun-13 5-Jun-13 7-Jun-13 9-Jun-13 11-Jun-13 13-Jun-13 15-Jun-13 17-Jun-13 19-Jun-13 21-Jun-13 23-Jun-13 25-Jun-13 27-Jun-13 29-Jun-13 1-Jul-13 3-Jul-13 5-Jul-13 7-Jul-13 9-Jul-13 11-Jul-13 Payment ($) Trade Date
Daily Distribution of Mileage Payments
Mileage Down Mileage Up Mileage Down Mileage Up 67,716 12,460
Slide 9
Pay for Performance
0.00 2,000.00 4,000.00 6,000.00 8,000.00 10,000.00 12,000.00 14,000.00 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Payment ($)
Hourly Distribution of Mileage Payment
Mileage Down Mileage Up
Pay for Performance
Page 10
0% 10% 20% 30% 40% 50% 60% 70% 1-Jun-13 3-Jun-13 5-Jun-13 7-Jun-13 9-Jun-13 11-Jun-13 13-Jun-13 15-Jun-13 17-Jun-13 19-Jun-13 21-Jun-13 23-Jun-13 25-Jun-13 27-Jun-13 29-Jun-13 1-Jul-13 3-Jul-13 5-Jul-13 7-Jul-13 9-Jul-13 11-Jul-13 13-Jul-13 15-Jul-13
System Mileage Performance Accuracy
System Up Accuracy System Down Accuracy
Slide 11
DA vs. RT prices trends
- 10
- 8
- 6
- 4
- 2
2 4 6 8
Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 NP15 SP15 Monthly Average Price Difference between RT and DA (RT minus DA)
$/MWh
Slide 12
Wind Schedules in HASP and DA.
10,000 20,000 30,000 40,000 50,000 60,000 70,000 80,000 90,000
1-Jan 8-Jan 15-Jan 22-Jan 29-Jan 5-Feb 12-Feb 19-Feb 26-Feb 5-Mar 12-Mar 19-Mar 26-Mar 2-Apr 9-Apr 16-Apr 23-Apr 30-Apr 7-May 14-May 21-May 28-May 4-Jun 11-Jun 18-Jun 25-Jun HASP IFM MWh
Slide 13
Solar Schedules in HASP and DA.
2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 20,000
1-Jan 14-Jan 27-Jan 9-Feb 22-Feb 7-Mar 20-Mar 2-Apr 15-Apr 28-Apr 11-May 24-May 6-Jun 19-Jun HASP IFM MWh
DA monthly average DLAP LMP was higher than RTD LMP in June.
Page 14 10 20 30 40 50 60 Jan-11 Mar-11 May-11 Jul-11 Sep-11 Nov-11 Jan-12 Mar-12 May-12 Jul-12 Sep-12 Nov-12 Jan-13 Mar-13 May-13 $/MWh
IFM HASP RTD
PG&E 10 20 30 40 50 60 Jan-11 Mar-11 May-11 Jul-11 Sep-11 Nov-11 Jan-12 Mar-12 May-12 Jul-12 Sep-12 Nov-12 Jan-13 Mar-13 May-13 $/MWh
IFM HASP RTD
SCE 10 20 30 40 50 60 Jan-11 Mar-11 May-11 Jul-11 Sep-11 Nov-11 Jan-12 Mar-12 May-12 Jul-12 Sep-12 Nov-12 Jan-13 Mar-13 May-13 $/MWh
IFM HASP RTD
SDG&E 5 10 15 20 25 30 35 40 45 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 $/MWh
IFM HASP RTD
VEA
PG&E HASP prices elevated by two days of HASP congestion in HE 15 and 16.
Page 15
50 100 150 200 250 1 2 3 4 5 6 7 8 9 101112131415161718192021222324
$/MWh
IFM HASP RTD
PG&E Hour
10 20 30 40 50 60 70 1 2 3 4 5 6 7 8 9 101112131415161718192021222324 $/MWh
IFM HASP RTD
SCE
10 20 30 40 50 60 70 1 2 3 4 5 6 7 8 9 101112131415161718192021222324 $/MWh
IFM HASP RTD
SDG&E
10 20 30 40 50 60 1 2 3 4 5 6 7 8 9 101112131415161718192021222324 $/MWh
IFM HASP RTD
VEA
Monthly price distributions: mostly negative price spikes in June.
Page 16
- 10.0%
- 8.0%
- 6.0%
- 4.0%
- 2.0%
0.0% 2.0% 4.0% Jan-11 Mar-11 May-11 Jul-11 Sep-11 Nov-11 Jan-12 Mar-12 May-12 Jul-12 Sep-12 Nov-12 Jan-13 Mar-13 May-13 Percent of Real Time Intervals
- $30 to -$5
- $100 to -$30
- $300 to -$100
<-$300 $250 to $500 $500 to $750 $750 to $1000 >$1000
Insufficient up ramping capacity continued to be very low in June.
Page 17 0.00% 0.50% 1.00% 1.50% 2.00% 2.50% 3.00% 3.50% 4.00% 50 100 150 200 250 300 350 400 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Percent of Intervals Count of Intervals
5-minute intervals with insufficient upward ramping capability percent of intervals with insufficient upward ramping capability
Monthly average of RTD Intervals with insufficient down ramping capacity dropped in June.
Page 18 0.00% 0.50% 1.00% 1.50% 2.00% 2.50% 3.00% 3.50% 4.00% 50 100 150 200 250 300 350 400 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Number of Intervals
5-minute intervals with insufficient downward ramping capability percent of intervals with insufficient downward ramping capability
Slide 19
Real-time congestion offset costs increased in June.
- 10
10 20 30 40 50 60
Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13
$Millions
Congestion Imbalance Offset Energy Imbalance Offset Real-time Congestion and Energy Imbalance Offset Cost
Slide 20
Real-time congestion and energy imbalance offset costs decreased in June after increasing in five straight months.
10 20 30 40 50 60 70
Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13
$Millions
Sum of Congestion and Energy Imbalance Offset
Congestion and Energy Imbalance Offset
Exceptional dispatch volume increased in May and June.
Page 21 0.005 0.01 0.015 0.02 0.025
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2009 2010 2011 2012 2013
Total Exceptional Dispatch as Percent of Load % of Total Load
Daily exceptional dispatches– by reason
Page 22
0.00% 0.50% 1.00% 1.50% 2.00% 2.50% 3.00% 1-May 3-May 5-May 7-May 9-May 11-May 13-May 15-May 17-May 19-May 21-May 23-May 25-May 27-May 29-May 31-May 2-Jun 4-Jun 6-Jun 8-Jun 10-Jun 12-Jun 14-Jun 16-Jun 18-Jun 20-Jun 22-Jun 24-Jun 26-Jun 28-Jun 30-Jun
Fires Software Limitation Transmission Outage Unit Testing Thermal Margin Load Forecast Uncertainty SP26 Capacity 7430 Other
% of Total Load
Bid cost recovery (BCR) costs fell in June.
Page 23
2 4 6 8 10 12 14 16 18 20
Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 $Millions IFM RT RUC
MIP gap performance continued to be good in June.
Page 24
10,000 20,000 30,000 40,000 50,000 60,000 70,000 80,000 90,000 100,000
1/1/11 2/1/11 3/1/11 4/1/11 5/1/11 6/1/11 7/1/11 8/1/11 9/1/11 10/1/11 11/1/11 12/1/11 1/1/12 2/1/12 3/1/12 4/1/12 5/1/12 6/1/12 7/1/12 8/1/12 9/1/12 10/1/12 11/1/12 12/1/12 1/1/13 2/1/13 3/1/13 4/1/13 5/1/13 6/1/13
Daily Dollar 30 Day Moving Average
Mip Gap ($)
Slide 25
Flexi-ramp constraint costs declined in June.
1 2 3 4 5 6
Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13
$Millions
Monthly Flexi-Ramp Cost
Price corrections decreased in June.
Page 26
Price corrections decreased in June.
Page 27
CMRI Report on Transmission Constraints
Dede Subakti, Director Operations Engineering
Slide 28
NERC Standard Requirement for Transmission Constraint
TOP-002-2
- R6. Each Balancing Authority and Transmission
Operator shall plan to meet unscheduled changes in system configuration and generation dispatch (at a minimum N-1 Contingency planning) in accordance with NERC, Regional Reliability Organization, subregional, and local reliability requirements TOP-004-2
- R2. Each Transmission Operator shall operate so that
instability, uncontrolled separation, or cascading outages will not occur as a result of the most severe single contingency.
Page 29
N-1 Secure
Modeling Simple N-1/N-2 Contingency for Tranmission Constraint Modeling
- In the past, there are three ways to model congestion
- Method 1: Utilization of Path, Example
– Path 15
- Loss of LBN overload Los Banos-Westley
- Loss of LBS overload Gates-Panoche
- Loss of MWN overload Gates-Midway
– Path 26
- Loss of MV1+2 overload MV3 (or now MW)
Page 30
Modeling Simple N-1/N-2 Contingency
- Method 2: Utilization of LODF, Example
– Flow Limit in Bay Area: 0.24*Pittsburg-San Mateo 230 kV (,@Pittsburg) + Pittsburg-Eastshore 230 kV (,@Pittsburg) Monitor Pittsburg-Eastshore for loss of Pittsburg-San Mateo – Flow Limit in Orange County: 0.72*Barre-Villa Park 220 kV + Barre-Lewis 220 kV Monitor Barre-Lewis for loss of Barre-Villa Park
- Method 3: Utilization of Contingency Analysis
Page 31
For Discussion Purpose - Simplified System Diagram – Importing region
Page 32
Un 1 Un 2 Un 3 Line A Line B Normal Rating Emergency Rating Line A 100 150 Line B 100 150 Line C
How to Implement The Standards – Method 1: Using Proxy Path Limit
Page 33
Line A Line B
Normal Emergency Line A 100 150 Line B 100 150
- Utilizing Proxy Path Limit:
- Line A + Line B + Line C < Import Limit
Line C Problem: It’s a proxy limit calculated based on off-line assumption
How to Implement The Standards Method 2: Using LODF
Page 34
Line A Line B
Normal Emergency Line A 100 150 Line B 100 150
- Utilizing LODF
- Line A + (Distribution Factor * Line B) < Rating of Line A
Line C Problem: LODF is calculated off line and it is based on system
- topology. LODF changes when the system topology changes
How to Implement The Standards Method 3: RTCA
Page 35
Line A Line B
Normal Emergency Line A 100 150 Line B 100 150
- RTCA
- Tool automatically do calculation with the input:
- What to monitor ( Line A)
- What to simulate (Contingency of Line B)
- What is the rating (Rating of Line A)
Line C
Method 1: Example for Path 15
How does this look in CMRI
In CMRI: Transmission Constraint Definition
Page 37
Method 2: Example for BARRE-LEWIS_NG
Lewis Barre Vila Park
Utilizing Flow Limit and LODF
Page 39
Purpose: Ensure that Barre-Lewis (from Lewis to Barre) does not overload for N-1 loss of Barre-Villa Park above its 1470 Emergency Rating Utilization of LODF (Method 2): Line A + (Distribution Factor * Line B) < Rating of Line A Distribution Factor Line Rating
This is how Market Implementation is
- Utilize Nomogram
Barre-Lewis + (0.72 * Barre-Villa Park) < 1470
Page 40 200 400 600 800 1000 1200 1400 1600 500 1000 1500 2000 2500
Barre-Lewis Line Flow Barre - Villa Park Line Flow
Barre-Lewis_NG Safe Operating Region N-1 Insecure Operating Region
How does this look in CMRI
Barre-Lewis + (0.72 * Barre-Villa Park) < 1470 In CMRI: Nomogram Definition In CMRI: TCORR Definition In Market Modeling Data
Page 41
BARRE_NG_1 BARRE_NG_2
Nomogram Naming Convention
- Procedure Base nomogram will have the procedure
name. – Example:
- 7820_TL230S_OVERLOAD_NG
- This is for Procedure 7820
– New Procedure number is 6xxx – 7xxxx – Old Procedure number is T-xxx
- Outage base nomogram is normally temporary. It will
have the SLIC number in it. – Example:
- SLIC 1860182 HUMSB_SOL-2
Page 42
Method 3: Using Straight Contingency
Utilizing Contingency
- Need to ensure the line that could be overloaded is
defined as “Enforced Flowgate”
- Need to ensure the contingency is active
Page 44
Transmission Contingency Definition
- In CMRI: Contingency Definition
- In Market Modeling Data
Page 45
Policy Update
Brad Cooper Manager, Market Design and Regulatory Policy
Slide 46
Market design initiatives coming soon
- PIRP Protective Measures
− Starting August
- Reliability Services Auction
− Targeted to start September
- Load Granularity Refinements
− Targeted to start August
- Stakeholder Initiative Catalog
− Targeted to start September
Page 47
Market initiatives going to the Board for approval
Page 48
Initiative Board Presentation Revision of Price Corrections Process September PIRP Protective Measures September Contingency Modeling Enhancements November Energy Imbalance Market November Full Network Model Expansion November Flexible Resource Adequacy Criteria and Must Offer Obligations December Interconnection Process Enhancements December
Technical Updates
Khaled Abdul-Rahman, Executive Director George Angelidis, Principal Li Zhou, Senior Advisor Power Systems Technology Development
Page 49
Technical User Group Updates
Doug Walker, Lead Architect Architecture
Page 50
Technical User Group
2013 Second Half Topics – Integration
- MTOM
- GMT for services
- CIM Adoption
- Acceptable Use
– Federated Security – Smart Grid Proof of Concepts – Notifications We want your input
Slide 51
Release Plan Updates
Janet Morris, Director June Xie, Sr. Advisor Program Office
Page 52
The ISO offers comprehensive training programs
Date Training July 23 Settlements 101 July 24 Settlements 201 August 15 Welcome to the ISO Web Training
Page 53
Training calendar - http://www.caiso.com/participate/Pages/Training/default.aspx Contact us - markettraining@caiso.com
Release Plan – 2013
- Fall 2013
- Post Emergency Filing BCR changes / Mandatory MSG is combined with
RIMPR-Phase 1 / BCR Mitigation Measures / Bid Floor Cap
- Commitment Cost Refinements 2013
- Ancillary Services Buy-Back
- PIRP Logic Change
- FERC 755 Pay for Performance API Report
- CMRI “CRN” Report New API
- Independent Efforts
- Access and Identity Management
- RIMS Generation
- Replacement Requirements for Scheduled Generation Outages Phase 2
- DRS API Deployment
- GMT
Page 54
Release Plan – 2014 (proposed)
- Spring 2014
- Circular Scheduling
- FERC Order 764 Compliance / 15 Minute Market / Dynamic Transfers
- ADS User Interface Replacement
- RDPR activation / FERC 745 Compliance
- Fall 2014
- Energy Imbalance Market (EIM)
- Full Network Model Expansion
- Outage Management System Replacement (OMS)
- Flexible Resource Adequacy Criteria and Must Offer Obligation
- Subject to further release planning:
- Contingency Modeling Enhancements
- Subset of Hours
- Acceptable Use Policy
- Flexible Ramping Product
- iDAM (simultaneous IFM and RUC)
- Revisions to Price Correction Requirements
- Expanding Metering and Telemetry
- Enterprise Model Management System
Page 55
2013 Release Schedule
http://www.caiso.com/Documents/ReleaseSchedule.pdf *Mandatory MSG Market Sim occurs one week per month through October 1st 2013.
MAP-Stage Outages and SIBR-Lite
Page 57
- MAP-Stage will be unavailable for external access from August 1-26, 2013
- The ISO intends to keep SLIC available during this outage (may experience a short
maintenance window)
- SIBR-Lite will be re-instated as of August 1, 2013 and will be installed with the
Production version of SIBR
2013 – SLIC JDK 1.7 Support
Page 58
What to Expect: – SLIC web client support for all Java versions including JDK 1.7 – SLIC RTAM client support for all Java versions including JDK 1.7 – Fix for “Password could not be saved” error that occurs during the “Configure Client Password” step of the web client installation process Target Date: Mid-August 2013 Impact to Users: – There is no mandatory action required of users – Users will be able to upgrade to JDK 1.7 and then re-install the SLIC web and/or RTAM client – Installation steps will remain the same and can be found on caiso.com: http://www.caiso.com/Documents/SLICWebClientInstructions.pdf
Implementation Impact Assessment
Application Software Changes
IFM/RTM: Energy Bid Floor to -$150/MWh MQS:
- Modify MLC calculation and cost allocation rules.
- Change DA MLC determination
- Program PUIE calculation (may need to change MQS energy algorithm)
- Split netting between DA and RT markets.
Settlements:
- Requires a tune-up on formulas to determine the ON criteria for resources, and
the eligibility for Bid Cost Recovery.
- Modify and build up to 12 charge codes to implement new BCR netting rules
and MLC.
- Program PUIE (persistent UIE) calculation.
- Program new RT PM (performance metric) calculation.
- Offset DA MLC by MLE revenues.
- Develop a number of BCR mitigation measurements
SIBR: SIBR rule changes will be needed to change the bid floor from -$30 (soft) to
- $150 (hard).
CMRI:
- RTM to publish all advisory schedules including current and next hour in the
horizon for RTPD runs
- Post relevant startup or transition time period for each startup cost or transition
cost period from MQS in the commitment cost report
- Post energy allocation based on the default energy bid
- Post relevant startup ramp time or transition ramp time periods from MQS
- Monthly Market Reports incorporating greater granularity in reporting BCR
components have been made available.
Fall 2013 – RIMPR Phase 1 / BCR Mitigation / Bid Floor
Page 59
Milestone Date
BPM Changes
Settlements & Billing, Market Operation, Market Instrument
Business Process Changes
Manage Billing and Settlements, Market Performance
Board Approval
Bid Floor and BCR netting: December 15-16, 2011 Post Emergency BCR / Mandatory MSG: Feb 15, 2012 BCR Mitigation Measures: December, 2012
External Business Requirements
April 19, 2013 (Post Emergency BCR posted on Feb 1, 2013)
Technical Specifications
July 10, 2013
Draft Configuration Guides - draft
July 10, 2013
Updated BPMs
August 26, 2013
Market Simulation
August 26, 2013 – September 13, 2013
Tariff filing date
August 26, 2013
Production Activation
November 1, 2013
Fall 2013 – RIMPR Phase 1 / BCR Mitigation / Bid Floor
Page 60
Milestone Date
Application Software Changes
Masterfile: Adding the Min. Load, Startup Major Maintenance Adder (MMS) and Grid Management Charge (GMC) to the projected proxy calculations. Settlements: Operational Flow Orders, NOx, and Sox penalties must be submitted ex post under circumstances attributable to exceptional dispatch and real-time commitments. These costs will be included in a re-evaluation
- f the real-time BCR calculation for that day with the Operational Flow
Orders (OFO) costs added into the calculation of the generator’s net shortfall
- r surplus over that day. Must establish an interface in which Market
Participants can enter data to flow directly to Settlements. The long-term service agreement costs refer to the major maintenance costs. The ISO is working with POTOMAC to develop a template and will share the template with Stakeholders at first quarter of 2013.
BPM Changes
Market Instruments Billing & Settlements
Business Process Changes
Manage Reliability Requirements
Board Approval
May 2012
External Business Requirements
April 30, 2013
Updated BPMs
August 26, 2013
Market Simulation
August 26, 2013 – September 13, 2013
Tariff filing date
August 23, 2013
Production Activation
November 1, 2013
Fall 2013 – Commitment Cost Refinement
Page 61
Milestone Description/Date
Application Software Changes
RTM: Operators will have the ability to manually force a buy back due to resource or transmission constraints. Settlements: Settlements will need to map to the new payload element that will indicate the reason for disqualification. Fourteen Charge Codes related ancillary services are impacted. MQS will need to correct the new output from RTM
BPM Changes
Settlements & Billing, Market Operations
Business Process Changes
N/A
Board Approval
July 13, 2012
External Business Requirements
February 28, 2013
Updated BPMs
August 5, 2013
Technical Specifications
N/A
Draft Configuration Guides - draft
July 10, 2013
Tariff
Filed January 3, 2013 Approved Thursday June 27, 2013
Market Simulation
August 26, 2013 – September 13, 2013
Production Activation
November 1, 2013
Fall 2013 – AS Buy Back
Page 62
Fall 2013 - PIRP Logic Change
Slide 63
Milestone Date
Application Software Changes
RTM: Dispatch VER based on its economic energy bid with the forecast as its Pmax. PIRP:
- Provide the hourly PIRP forecast for RTM.
- Determine if the PIRP hourly eligibility in UIE monthly netting based on PIRP’s
RTM DOT and the hourly forecast
- For the PIRP unit and/or hours that continues to use self schedule to participate,
the existing production logic stays the same Settlements:
- Continue to perform PIRP resource monthly UIE netting based on the hourly
eligibility determined by PIRP.
BPM Changes
Market Operations, Market Instrument
Business Process Changes
Manage Billing and Settlements, Market Performance
Board Approval
May 15, 2013
External Business Requirements
May 20, 2013
Technical Specifications
Not Applicable
Updated BPMs
August 5, 2013
Market Simulation
August 26, 2013 – September 13, 2013
Tariff
August 2013
Production Activation
November 1, 2013
Milestone Description/Date
Emergency BPM Changes
See PRR 673
System Mileage Production Report UI
Jul 1 deployment to production
System Mileage Production Report API
Fall 2013
Technical Specification
Jul 15 – OASIS API technical specification
Business Process Changes
AS Certification – AGC signal certification process
DATA MILEAGE REQUESTS
Submit mileage data requests through CIDI
- Due to resource limitations, the maximum data request will be for one
trade date ,for one resource, per SC, per month.
Fall 2013 - FERC Order 755 pay for performance
Fall 2013 – Market Simulation Plan
Page 65
Fall Release 2013 Market Simulation Plan Posted - http://www.caiso.com/Documents/Fall2013ReleaseMarketSimulationPla nV1_0.pdf
Timelines - Market Simulation Trade Dates 8/27 – 9/13 Kickoff call 8/15 In scope initiates and simulation type -
- AS Buy Back – Structured
- Commitment Cost Refinements 2013 – Unstructured
- RI-MPR Phase 1 with BCR-Post Emergency and Mandatory MSG (Includes
CMRI CRN API) – Unstructured
- RRSGO Phase 2 Annual – Unstructured
- PIRP Logic Change (Includes FERC 755 OASIS AS Report and Load Forecast
Report API) - Unstructured
Milestone Date
Application Software Changes
The goal of the AIM project is to improve upon the existing approach for establishing, updating and terminating access to applications as well as providing visibility (transparency), ease of use and self-service where appropriate to POCs (Points of Contact), internal ISO users, business units and IT to manage this process from end to end. AIM: New system with UI and workflow
BPM Changes
Definitions and Acronyms (For AIM Release 1)
Business Process Changes
IT Access Mgmt. - Certificate based application access; Metering systems access
Board Approval
N/A
External Business Requirements
Jan 31, 2013
Updated BPMs
TBD
Market Simulation
N/A
Tariff
N/A
Production Activation
August 19th , 2013 (Release 1)
2013 - Access and Identity Management (AIM)
Page 66
Milestone Date
Application Software Changes
RIMS Generation module will be changed, including a revamp of the external user interface. Changes include pre-programmed notifications (based on approaching deadlines, status changes, new project creation), canned reporting and ability to push reports to project contacts. External access will be granted with an ability to upload data and attachments directly to the
- system. Dashboard will be enhanced to provide accurate project statuses,
filtering and export functions.
BPM Changes
N/A
Business Process Changes
Manage New Participating Generator Interconnections
Board Approval
N/A
External Business Requirements
April 10, 2013
Technical Specifications
N/A because there is no API. However, there will be an external UI for participants, and a user guide related to this UI will be provided six weeks in advance of the market simulation.
Updated BPMs
N/A
Market Simulation
After Fall 2013
Tariff
N/A
Production Activation
November 15th, 2013
2013 – RIMS Generation
Page 67
Milestone Date
Application Software Changes
IRR: Moving Annual IRR functionality to new CIRA (CAISO Interface for Resources Adequacy) Application (new url, same look and feel, some new interactions)
BPM Changes
606 - Replacement Requirements 607 - Resource Adequacy Resource Planned Outage Reporting
Next Monthly RR Workshops
August 12, 2013, 2:00 pm
Board Approval
July 12, 2012
Updated External Business Requirements
Posted July 19, 2013 (includes Annual and Monthly)
Technical Specifications
N/A for Annual
Training
August 22, 2013 (webinar)
Market Simulation
August 26 – September 13 2013 (unstructured)
Tariff
FERC Filing September 20, 2012 FERC Order Conditional Acceptance November 19, 2012 FERC Compliance Filing December 19, 2012 Request for Rehearing December 19, 2012
Production Activation
Annual – October, 1 2013
2013 – Replacement Requirement for Scheduled Generation Outages Phase 2 (RRSGO P2)
Page 68
Milestone Date
Application Software Changes DRS - Addition of API to support automated registration, and potentially for reporting on baseline and performance. BPM Changes TBD Board Approval N/A External Business Requirements Registration API Baseline & Performance API August 30, 2013 December 2013 (if needed) Technical Specifications - Registration September 2013 Updated BPMs TBD Market Simulation Registration API Baseline & Performance API November 2013 (tentative) Feb 3 – Mar 7, 2014 (if needed) Tariff N/A Production Activation Registration API Baseline API Performance API December 2013 (tentative) Spring 2014 (if needed) Spring 2014 (if needed)
2013 – Demand Response System (DRS) API
Page 69
Milestone Date
Application Software Changes
OASIS and CMRI All APIs will be provided with GMT option
BPM Changes
N/A
Board Approval
N/A
External Business Requirements
N/A
Technical Specifications
ISO is planning to provide options in TUG for feedback on 07/30. Based on feedback, we will provide update on technical specifications in RUG on 08/06.
Updated BPMs
N/A
Market Simulation
TBD
Tariff
N/A
Production Activation
December 2013
2013 - GMT
Page 70
Milestone Date
Application Software Changes
Currently Planning to do a proof of concept and based on results, implementation and technical solution will be communicated through TUG &
- RUG. This policy will impact all external applications.
BPM Changes
N/A
Board Approval
N/A
External Business Requirements
N/A
Technical Specifications
N/A
Updated BPMs
N/A
Market Simulation
TBD
Tariff
N/A
Production Activation
TBD
Acceptable Use Policy
Page 71
Milestone Date
Application Software Changes
Masterfile: Creation of new field to capture attestation letter submission. Change
to Generator RDT to allow participants to view the new field. CAS: Identify the circular schedules MW, import/export resource IDs for the single e-tag, with source/sink at the same BAA; the BAA could be CAISO or other BAA; Exclude dynamic, DC segment, open intertie, Wheeling through for load.
CRR Claw Back/MQS: Identify the SC’s affiliation for single SC and circular
schedule MW. Build new rule of calculate value the claw-back CRR in dollars.
Settlement: Identify the SC’s affiliation for single SC. Identify the circular schedule
Import applicable IFM and HASP scheduled MW. Build Settlement rule the settle the import schedule at lower LMP of Import/export. Circular schedule is not eligible for BCR for the interval.
BPM Changes
Market Operations, Market Instruments, Settlements & Billing
Business Process Changes
Manage Interchange Scheduling, Manage MQS, Manage Billing and Settlements
Board Approval
March 2012
External Business Requirements
March 22, 2013
Updated BPMs
December 6, 2013
Technical Specifications
Master File - August 2013
Draft Configuration Guides
TBD
Market Simulation
Feb 3 – Mar 7, 2014
Tariff
Filed November 21, 2012 Approved January 30, 2013
Production Activation
Spring 2014 (April 1, 2014)
Spring 2014 – Circular Scheduling
Page 72
Spring 2014 - FERC 764
Slide 73
Implementation Impact Assessment
Application Software Changes MasterFile: Identify variable energy resources and their selection of using ISO VER forecast or their own VER forecast. IFM/RTM:
- A new 15-Minute market with financially binding energy and AS awards for
internal generators, imports/exports, and participating loads.
- Real time bid submission process remains same
- Cleared against the CASIO forecast of real time demand
- Executed 37.5 minutes prior to the start of the binding interval, 15
minutes earlier than the current 22.5 minute prior to the binding of RTUC run
- Allow a number of bidding options for an intertie
- A new hourly process to produce the advisory hourly block schedule
for the non-dynamic intertie transaction that will be used for subsequent 15-minute market.
- Convergence bidding will be allowed on intertie scheduling point. All
convergence bids will be settled between the day-ahead market and the 15-minute market
- The “physical only” constraint at the scheduling point of the dual constraints
not enforced in the IFM but enforced in RUC.
- RUC establishes the number of eTags it can accept for day-ahead physical
market awards.
- 15-minute market and 5-minute market dispatch VER based on its
economic energy bid and use forecast as its upper operation limit
- Support Primary/Alternative ITC for DS/PTG
Spring 2014 - FERC 764
Slide 74
Implementation Impact Assessment
Application Software Changes CAS:
- Perform scheduling check-out based on the 15-minute based schedules and tag
energy profile
- Perform the tag update/approval by the hourly deadline T-20 for various intertie
bidding options
- Receive and consume the RUC cleared capacity for day-ahead tagging check-
- ut purpose
- Receive and consume the RTPD 15-minute schedules for tagging check-out
purpose
- Automatically match retag DS/PTG schedule from the primary ITC to the
alternative ITC when the primary ITC become open ADS
- As the HASP will be replaced the hourly process to accept the block schedule
and the hourly process schedule is advisory, no more HASP predispatch schedules will be issued through ADS Settlements:
- 15-minute energy settlements will be based on the 15-minute schedule and the
day-ahead energy schedule. 5-minute energy settlement will be based on the difference of 15-minute schedule and 5-minute dispatch. All metering related settlement will be changed to 5-minute base. Real-time Inter-SC trades based
- n 15-minute price.
Metering: 10-minute metering data changed to 5-minute metering data SIBR:
- Allow market participants to submit 5-minute VER forecast with a 2-hour look-
ahead window
- Allow an intertie various additional bidding options:
- An hourly block schedule
- A single curtailment for the remainder of the hour with block schedule
- Option to determine 15-minute market participation if not accepted in the
hourly process
Spring 2014 - FERC 764
Slide 75
Milestone Date
BPM Changes Market Operation, Market Instruments Settlements & Billing, Definitions & Acronyms Business Process Changes Manage Master file: Identify variable energy resources and their selection of using ISO VER forecast or their own VER forecast DA and RT processes: A new financially binding 15 minute scheduling market run for import, export, internal resources and loads Settlements: 15-minute market settlement Price Correction and Validation: Price Validation and correction tools and/or proposed MVT tool shall be modified to include 15-minute market Price validation. Interchange Scheduling: Update/approval etag hourly transmission profile and the 15-minute energy profile for various intertie bidding options. Manage Metering: Metering data for settlement for both CAISO ME polled data and SC submitted data are changed to 5-minute. Analysis Dispute and Resolution: expanded to include validation rules and corrections for the 15-minute market solution. Market Performance (MAD/DMM): expanded to monitor market performance related to the 15-minute market scheduling and settlement. Training: Training will be needed to train Operator/Analysts on the 15-minute market scheduling and settlement.
Spring 2014 - FERC 764
- Slide 76
Milestone Date
Board Approval May 15, 2013 External Business Requirements May 20th MasterFile and SIBR May 24th Metering and Settlements June 3rd ADS, OASIS and CMRI Complete BRS: June 21, 2013 External Data Requirements Specification Jul 22nd MasterFile, SIBR, ADS, CMRI and OASIS Jul 23rd RUG walkthrough each application Technical Specifications Aug - MasterFile and SIBR Sep – Oct OASIS, CMRI, ADS TBD – ADS Framework Oct – Metering Updated BPM’s Dec 2013 Draft Configuration Guides Dec 2013 initial draft Market Simulation Feb 3 – Mar 7, 2014 Tariff Nov 12, 2013 Production Activation Spring 2014 (April 1, 2014)
Milestone Date
Application Software Changes
- Port client from Delphi to new common user interface (ADS
Query Tool and Real Time Functionality)
- Conform APIs to current ISO standards
BPM Changes None Board Approval N/A External Business Requirements N/A Technical Specifications TBD Updated BPMs N/A Market Simulation Feb 3 – Mar 7, 2014 Tariff N/A Production Activation Spring 2014 (April 1, 2014)
Spring 2014 – ADS User Interface Replacement
Page 77
Milestone Date
Application Software Changes
Activation of Reliability Demand Response Product (RDRP) including FERC Order 745 compliance.
BPM Changes
TBD
Board Approval
Not required
External Business Requirements
See: http://www.caiso.com/informed/Pages/StakeholderProcesses/ReliabilityDema ndResponseProduct.aspx
Technical Specifications
See slide on DRS API
Updated BPMs
TBD
Market Simulation
Feb 3 – Mar 7, 2014
Tariff
Compliance filing due on August 19, 2013
Production Activation
Spring 2014 (April 1, 2014)
Spring 2014 - RDRP Activation / FERC 745 Compliance
Page 78
Milestone Date
Application Software Changes
Master File: Register EIM entity, EIM resources, EIM resource emission rate, EIM Interties SIBR: Accept and validate submitted EIM resource plan and load base schedule, EIM resource bids. ALFS: Forecast EIM load, EIM VER. EMS: Model updates EIM BAA, model EIM NSI. DAM/RTM: Perform the DCPA for each BAA for the constraint in the BAA and the test and mitigate the resources in the BAA; Decompose the LMP congestion by the constraint belong the same BAA; option for EIM entity unit commitment; All LMPs will not include marginal loss contributions from external network losses; The EIM entity access the interface to submit exceptional dispatch with “EIM type”; send the latest valid prior RTD advisory results to EIM when ISO run RTCD. Model Greenhouse Gas (GHG) emission for EIM to ISO; Calculate BAAs transfers; Perform flexible ramping requirement sufficiency test. Meet flexible ramping requirement by BAA and total. MQS: Calculate resource unit contribution on congestion cost for real time congestion balance account. OMS: EIM submission of resource and transmission Outages Settlement: settle 15 minute and 5 minute markets IIE and UIE at LMP ; Calculate EIM LAP hourly volumetric weighted average LMP weighted by the load forecast deviations bounded by the min/max LMPs; Settle EIM administrative cost; create real-time congestion balancing account for each BAA; Collect and allocate under- schedule penalty by month. Settle EIM resource BCR. Allocate uplift to the BAA shared by the transfers. Pay the flexible ramping capacity use current formula, allocate the cost prorata to the requirements. CMRI/OASIS/ADS: Publish the market results for EIM BAA and resources.
Fall 2014 – Energy Imbalance Market (EIM)
Page 79
Milestone Date
BPM Changes Market Operations, Market Instruments, Settlements and Billing Board Approval November 8, 2013 External Business Requirements September 1, 2013 Technical Specifications April 1, 2014 Updated BPMs TBD Market Simulation July 8, 2014 Tariff February 28, 2014 Production Activation October 1, 2014
Fall 2014 – Energy Imbalance Market (EIM)
Page 80
Milestone Date
Application Software Changes
Master File: Define external BAA scheduling point as Generation Aggregated Point (GAP) and GDF SIBR: Submit and create transaction ID for the SC Bids on Scheduling Points-BAA dynamically; Allow the SC bids at same BAA-SP to bid to different interties. DAM/RTM: Receive the dynamically formed transaction ID attributes from bid, perform contingency analysis for some critical external BAA resources and transmission equipment. Incorporate external BAA critical outages, Enforce both flow and schedule Intertie constraints, Model HVDC line. CRR: CRR market run on expanded Full Network Model. CMRI/ADS/OASIS/Settlement: Receive and process the dynamically formed transaction ID.
BPM Changes Market Operations, Market Instruments, Managing FNM Board Approval November 2013 External Business Requirements September 1, 2013 Technical Specifications April 1, 2014 Updated BPMs TBD Market Simulation July 8, 2014 Tariff TBD Production Activation Fall 2014
Fall 2014 – Full Network Model Expansion
Page 81
Milestone Date
Application Software Changes
CRR: Receive outage data from OMS ED: Provide equipment to patch mapping date to OMS EDR: Store outage data from OMS EMS: Receive outage data from OMS once outage is created or changed ETCC: Retrieves outages from OMS, updates path limits impacted by the
- utages and broadcasts path limits from OMS
IFM/RTN: Receive outage data from OMS and broadcast flowgate and nomogram data to OMS MF: Provide reference data to OMS via web services MPP and OASIS: New outage reports posted. OMS: New OMS replaces LSLIC and current OMS with improved capability. Notifications become automatic. Manual email supported. OMS takes over role for publishing data. PIRP: Receive outage data from OMS CIRA: Retrieves outages from OMS and checks if RA resources are impacted by outages. Scheduling Coordinator replaces RA units. Settlements: Receives outage data from OMS TR: Provide Transmission Equipment reference data to OMS via web services.
BPM Changes
Managing Full Network Model Market Instruments Outage Management Market Operations Compliance Monitoring
Fall 2014 – Outage Management System (OMS)
Page 82
Milestone Date
Board Approval
July 11, 2013
External Business Requirements
Posted June 28, 2013
Technical Specifications
November 1, 2013
Business Process Changes
Maintain Master File Manage Generation Outages Manage Transmission Outages Day-Ahead Process Real-Time Process – Prior to Bid Close Real-Time Process – After Bid Close Real-Time Process – 5 minute dispatch Manage FNM Maintenance Promote Network Model into Production Determine Generation of OTC – determine if it affects OTC, enter data into ETC application, notify affected parties of change in ETC values and notify requestor of decision.
Fall 2014 – Outage Management System (OMS) - continued
Page 83
Milestone Date
Business Process Changes (continued)
Evaluate Generation Initial Review and Request – disapprove new or modification request, evaluate outage request for accuracy, evaluate the
- utage request, and obtain additional information for evaluation.
Evaluate Generation Modification Request – approve forced/immediate request, assign requested status, and pend /internal consult. Evaluate Generation Outage Request – check if discrepancy is resolvable, determine appropriate action of request, determine generation OTC, evaluate request, and push ERTC data to OASIS on demand. Manage Dispatcher Load Flow Analysis Manage Extreme Long-Start Commitment Manage Generation Outages Manage Outage Request Submission Manage Outage Updates to network Model Manage Real-Tome Outage Impacts to ETC and Network Model Manage Resource Interconnections Manage Transmission Outages
Updated BPMs
September 2014
Market Simulation
July 8 – July 29, 2014
Tariff
~ August 2014
Production Activation
October 1, 2014
Fall 2014 – Outage Management System (OMS) - continued
Page 84