Market Performance and Planning Forum December 7, 2016 Objective: - - PowerPoint PPT Presentation
Market Performance and Planning Forum December 7, 2016 Objective: - - PowerPoint PPT Presentation
Market Performance and Planning Forum December 7, 2016 Objective: Enable dialogue on implementation planning and market performance issues Review key market performance topics Share updates to 2016 release plans, resulting from
Objective: Enable dialogue on implementation planning and market performance issues
- Review key market performance topics
- Share updates to 2016 release plans, resulting from
stakeholders inputs
- Provide information on specific initiatives
–to support Market Participants in budget and resource planning
- Focus on implementation planning; not on policy
- Clarify implementation timelines
- Discuss external impacts of implementation plans
- Launch joint implementation planning process
Slide 2
Market Performance and Planning Forum
Agenda – December 7, 2016
12:00 – 1:00 Lunch 1:00 – 1:30 Market Results – PSE and APS Integration Gabe Murtaugh 1:30 – 2:00 Policy Update Brad Cooper 2:00 – 3:00
- Release Update
- Annual Functional Release Lifecycle
Janet Morris Time: Topic: Presenter: 10:00 – 10:05 Introduction, Agenda Kristina Osborne 10:05 – 10:20 Real-Time Transfer Limit Increases Danny Johnson 10:20 – 10:45 November 9 Frequency Deviation Event John Phipps 10:45 – 12:00 Market Performance and Quality Update Guillermo Bautista Alderete Warren Katzenstein Amber Motley
Slide 3
Real-Time Transfer Limit Increases
Danny Johnson
- Sr. Operations Engineer, Operations Planning - South
Slide 4
Increase Transfer Capability on WECC Paths
Slide 5
Aliso Canyon Authority
- CAISO received authority to “reserve internal transfer
capability into Southern California”
- Have since moved to retire this authority as we believe
we can instead use Peak RC SOL methodology to increase Real Time transfer if needed.
Page 6
Justification for Real Time Uprate
Peak RC System Operating Limit (SOL) Methodology – Section 6 specifies that in ‘sub-seasonal’ time horizons the acceptable performance for Credible Multiple Contingencies can be relaxed if system conditions do not allow for the planned level of performance – This means in Real Time operations limits established using more stringent criteria for CMC can be revaluated during emergency NERC EOP-002-3.1 – Section 3.4 allows for a revision to SOL limits given RT information following the issuance of a EEA (Energy Emergency Alert) by the ISO.
Slide 7
Path Limits
Slide 8
- Path limits are based upon offline powerflow studies
- Does not account for Seasonal Variations or changing
load profiles
- Path limits are often pre-contingency proxy MW limits
across multiple transmission elements – Doesn’t account for minor changes in neighboring network topology due to outages – Doesn’t account for voltage conditions.
- Equipment ratings are based upon Amp rating.
- MVA = Amp*Voltage;
- MW limits are converted from MVA limits based
upon studied or assumed power factor, not RT/Operational power factor
How would CAISO implement?
CAISO RT Operations can utilize Real Time Contingency Analysis (RTCA) to monitor the actual element the path limit is trying to protect for More accurate limit because:
- Rather then limiting flows to the pre-contingency proxy
limit, CAISO can monitor and protect against post contingency overloads on the actual limiting element
- Allows for utilization of Real Time voltage conditions in
monitoring limit
- Accounts for changes in neighboring area topology
- RTCA RAS functionality allows for incorporating Real
Time congestion relief offered via RAS operation
Slide 9
Use Case – Path 26 (North-to-South)
Path Details
- 4000 MW limit from transfer capability of three transmission lines
- Is composed of Midway-Vincent #1 + Midway-Vincent #2 +
Midway-Whirlwind #1 transmission lines
- Is thermally limited by CMC of two of the three lines composing
path
- Path limit is based upon assumed RAS operation at time of study;
Gen Drop in PG&E and Load Shed in SCE
If necessary CAISO can increase Real Time limit by monitoring CMC in RTCA
– Accounts for additional load being armed in SCE; Load armed by RAS has increased significantly since Path Limit was set in 2006 – Controls to a MVA limit based upon Amp rating and post- contingency voltage. – Real Time limit above posted SOL achievable
Slide 10
Impact on Market Operation
- CAISO plans to use this methodology to increase limits
in Real Time only during emergency conditions. This will be following exhaustion of all available generation and utilization of all available demand response – Due to the Real Time data required this can not be implemented in IFM. IFM and RTM under normal conditions will continue to operate with the current ratings from CAISO Transmission Register
- Real Time Transfer Increases will NOT be posted in TTC
- Will be used to avoid pre-contingency load shedding
Slide 11
November 9 Frequency Deviation Event
John Phipps Director, Real-Time Operations
Slide 12
Slide 13
November 9 Frequency Deviation Event
– Event Description – At 11:00 a normal data transfer process with inputs for the market
- ccurred on schedule. A conflict in the process corrupted an input
that was then transferred into the market software. The next market run at 11:15 failed and advisory results were sent out based on the last successful run at 10:59. The issues and troubleshooting continued through the hour until the issue was found and fixed around 12:10. Additional related issues were discovered and fixed at approximately 12:39. – Around 11:59, the market runs started producing undesirable
- results. The ISO System Operators intervened by identifying and
blocking the undesirable dispatches. This continued until 13:35 in
- rder to keep the undesirable instructions from being sent to the
market participants via ADS. During this time period the ISO System Operators sent out multiple market messages to Scheduling Coordinators in order to raise awareness and prevent resources from following undesirable startup or shutdown
- instructions. Scheduling Coordinators were encouraged to call the
ISO to validate instructions before starting or shutting down any units.
Slide 14
November 9 Frequency Deviation Event
– 13:33 the ISO market software sent out decremental dispatch instructions of approximately 2500 MW to multiple generator resources via the Automatic Dispatch System (ADS) before the ISO’s System Operators could block or
- verride the dispatch instructions. The ISO’s Operators
verbally instructed Scheduling Coordinators to not follow the dispatches, but 1214 MW of the dispatch included fast moving resources and 730 MW of additional resources which automatically responded to the dispatch signal and reduced their output over an 11 minute period. This reduction in generation output caused the CAISO ACE and System Frequency to deviate. – At 13:35 BAAL was exceeded. At 13:45 ACE was at its lowest point -3245MW and Frequency was 59.834 HZ. – 13:53 BAAL was within limits, ACE and Frequency were recovered.
Slide 15
November 9 Frequency Deviation Event
Event Follow-up
- Action Items
– Review both automated and manual controls for improvement – Review ramp rates and expectations of units to ramp
- ver 5 minutes
– Lessons learned training and delivery by operators involved in the event
Market Performance and Quality Update
Guillermo Bautista Alderete, Ph.D. Manager, Market Validation and Quality Analysis Warren Katzenstein Lead Engineering Specialist Amber Motley Manager, Short Term Forecasting
Slide 16
Adjustment to Regulation Capacity Requirements
Slide 17
Control Performance and variable energy resources’ production affect the quantity of regulation procured
- Control Performance
– Measures the ability to adequately support the interconnection frequency – Exceedance of Balancing Authority Ace Limits (BAAL)1 – Noticed a decline in real-time CPS1 performance – Led to procured regulation up/regulation down depletion during high renewable penetration/low load periods
- High renewable penetration/low load periods
– Windy and cloudy conditions exacerbate wind and solar production variability causing larger deviations from forecast – Erratic weather (seasonal) during low load periods
Slide 18
Method for Determining Regulation Capacity
- For each hour, the ISO determines a percentage of forecasted
demand to set regulation capacity
- The amount of regulation capacity for a given month is informed by:
– Forecast Uncertainty Related To:
- Demand Forecast Deviations
- Solar Forecast Deviations
- Wind Forecast Deviations
– Seasonal/Daily Parameters
- New considerations
– Separation of Regulation Need in relation to Regulation Up and Regulation Down – Hourly Analysis of Historical Regulation Dispatch – Anticipated variability / forecast uncertainty in weather conditions
Slide 19
Method for Determining Regulation Capacity Cont.
- Historical Need
– For each hour, examine the 95th percentile of regulation required as calculated by the control algorithm – Use data from the same month last year to inform procurement for the current month (i.e. Oct 2015 informs Oct 2016)
- Anticipated variability / forecast uncertainty
– Examine performance from recent days that had higher forecast uncertainty in order to inform change in procurement related to weather – Example is a large weather system moving across California causing variability in cloud cover and wind speed/direction.
Slide 20
50 100 150 200 250 300 350 400 450 500 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Regulation Up Minimum Capacity (MW) Hour Ending
Jan Feb Mar Apr May Jun Jul Aug SEP OCT NOV DEC
Seasonal Trends are Present with New Method (Regulation Up)
Slide 21
Values above are based on historical information and are subject to change.
100 200 300 400 500 600 700 800 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Regulation Down Minimum Capacity (MW) Hour Ending
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Seasonal Trends (Regulation Down)
Slide 22
Values above are based on historical information and are subject to change.
May 2016 Regulation Procurement Versus October 2016 Procurement
Slide 23
- 1000
- 800
- 600
- 400
- 200
200 400 600 800 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Regulation Requirement (MW) Hour of the Day (Hour Ending) Spring 2016 Regulation Capacity Oct 2016 Regulation Capacity
October 2016 Results
Slide 24
Percentage of time with insufficient capacity: 1%
Flexible Ramp Product Update
Slide 25
Flexible Ramp Product
- Flexible Ramp product went live on November 1, 2016
- There is both upward and downward definitions for the
product.
- Each EIM area has its own requirement, and there is
also a system-wide EIM area enforced in the real-time market.
- There is also a flexible ramp sufficiency test done prior to
the real-time market.
- Requirements are based on historical data and
calculated in the Balancing Area Ramp Requirement (BARR) application.
Slide 26
What is the Balancing Area Ramp Requirement Tool?
- The Balancing Area Ramp Requirement (BARR) tool
calculates the uncertainty requirement and the demand curves for the Flex Ramp Product
- The uncertainty requirements are hourly values
calculated every day using the BARR tool
- Uncertainty requirements are based on net load forecast
error
- Net load = Load – Wind - Solar
- The demand curves are the prices the system is willing
to pay for a given quantity of flex ramp capacity
Slide 27
Flexible Ramp Uncertainty Requirement: 5-minute Real-Time Dispatch (RTD)
Slide 28
RTD Net Load Forecast Error is difference between the binding interval net load forecast and the prior market run first advisory net load forecast
Flexible Ramp Uncertainty Requirement: 15-minute Real-Time Pre-Dispatch (RTPD)
Slide 29
RTPD Net Load Forecast Error is maximum difference between the three RTD binding interval net load forecasts and the associated RTPD first advisory net load forecast
RTPD
Example of the Hourly Distribution of Data that Comprises the Histogram for Each EIM Entity
Slide 30
Example of the Hourly Distribution of Data and the Calculated Uncertainty Requirements (Red Lines)
Slide 31
An Example of the Flex Ramp Product Uncertainty Calculation
- Flex Up and Down Uncertainty Requirement could be calculated as
follows: – For each hour, gather the set of recent net load forecast errors for the appropriate market uncertainty – Group weekdays and weekends separately due to characteristic differences
- Weekdays use last 40 days of net load forecast error
- Weekends use last 20 days of net load forecast error
– The flex up uncertainty requirement is the 97.5 percentile – The flex down uncertainty requirement is the 2.5 percentile
- Daily thresholds are calculated using a similar process but with a
larger set of data – Significant reduction in % of time thresholds are setting the requirement compared to the Flex Ramp Constraint
Slide 32
Demand Curves
- The demand curves are used to determine how much
flexible ramp capacity the system will procure
- One demand curve for each EIM entity and ISO plus the
EIM Total Area (including ISO) for 7 total demand curves
- The demand curves are the distribution of net load errors
multiplied by the energy penalty price cap or floor – The penalty price cap is $1000 per MWh – The penalty price floor is $-150 per MWh
- The maximum price is $247 per MW
- The minimum price is $-155 per MW
Slide 33
Constructing a Demand Curve
- A demand curve starts with the probability distribution of net
load forecast errors – This is the same set of data that is used for determining the uncertainty requirement
- The flex ramp up demand curve is built by calculating the
percent of data that is greater than a given MW value
- The flex ramp down demand curve is built by calculating the
percent of data that less than a given MW value
- The percentage is converted a price by multiplying by either
the energy penalty price cap or price floor
- Finally, the curve is transformed from MW to Relaxation
Capacity by subtracting the MW values from the uncertainty requirement
Slide 34
Constructing a Demand Curve (Cont.)
- The OASIS published demand curves are comprised of two
components – The amount of capacity to relax the uncertainty requirement – The price associated for relaxing the uncertainty requirement
- Example
– With an uncertainty requirement of 100 MW, a relaxation capacity of 15 MW, and a price of $25 per MW – This means the market procured 85 MW of flexible capacity at a price of $25 per MW
Slide 35
0% 5% 10% 15% 20% 25% 30% 35% 40% 45% 20 40 60 80 100 120 140 160
Percent of Data Greater than A Given Net Load Forecast Error (%) Net Load Forecast Error Between RTPD Advisory and RTD Binding (MW)
Example of Constructing a Flex Up Demand Curve: Start with Probability Distribution of Net Load Forecast Errors
Slide 36
Curves are limited to the flex up or down uncertainty requirement
Convert Percentage to Price by Multiplying the Curve by the Energy Penalty Price Cap ($1000 per MWh)
Slide 37
50 100 150 200 250 300 350 400 450 20 40 60 80 100 120 140 160
Price ($/MW) Net Load Forecast Error Between RTPD Advisory and RTD Binding (MW)
Convert x-axis to Relaxation MW by Subtracting the Net Load Forecast Errors From the Uncertainty Requirement
Slide 38
50 100 150 200 250 300 350 400 450 20 40 60 80 100 120 140 160
Price ($/MW) Relaxaion Capacity (MW)
The Curve is then Segmented for Use in the Market Optimization
Slide 39
50 100 150 200 250 300 350 400 450 20 40 60 80 100 120 140 160
Price ($/MW) Relaxation Capacity (MW)
Finally, the Curve is Capped (if Required) at the Minimum or Maximum Price ($-155/MW or $247/MW)
Slide 40
50 100 150 200 250 300 350 20 40 60 80 100 120 140 160
Price ($/MW) Relaxation Capacity (MW) The segmented demand curve is then capped at a price of $247 per MW
FRP performance
Slide 41
FRP requirements and prices driven by the hourly profile needs
Slide 42
With FRP construct, the EIM area generally drives the
- verall procurement
Slide 43
- 2,500
- 2,000
- 1,500
- 1,000
- 500
500 1,000 1,500 2,000 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Flex Ramp (MW) APS NV Energy PSE PACW PACE ISO Credit Upward/Downward requirement
Flexible Ramp requirements adjusted with FRP activation
Slide 44
Hourly profile of ISO FRP requirements
Slide 45
Gas Price Update
- FERC clarified use of daily ICE gas price index
- Normal cycle calculates blended gas price indices the
prior night which is used for both DAM and RTM markets.
- With new provisions, the ICE index available in the
morning is used for the DAM market run.
- When no ICE price index is available, it defaults to use
previous night blended index.
Slide 46
Gas price difference of using morning ICE gas price update
Slide 47
Gas price difference of using morning ICE gas price update
Slide 48
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
- 20%
- 15%
- 10%
- 5%
0% 5% 10% 15% 20% 25% 25-Oct 27-Oct 29-Oct 31-Oct 2-Nov 4-Nov 6-Nov 8-Nov 10-Nov 12-Nov 14-Nov 16-Nov 18-Nov 20-Nov 22-Nov 24-Nov 26-Nov 28-Nov 30-Nov 2-Dec 4-Dec % of Volume Traded % Price Difference ($/MMBTu) Volume SCE CityGate Hub
Gas price difference of using morning ICE gas price update
Slide 49
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
- 20%
- 15%
- 10%
- 5%
0% 5% 10% 15% 20% 25% 25-Oct 27-Oct 29-Oct 31-Oct 2-Nov 4-Nov 6-Nov 8-Nov 10-Nov 12-Nov 14-Nov 16-Nov 18-Nov 20-Nov 22-Nov 24-Nov 26-Nov 28-Nov 30-Nov 2-Dec 4-Dec % of Volume Traded % Price Difference ($/MMBTu) Volume KRN Del Pool Hub
EIM Update
- Arizona Public Service (APS) and Puget Sound (PSE)
joined the EIM market on October 1, 2016.
- In the first hours after the activation, market observed
minor transitional issues.
- Both entities are under the six-month transitional period,
under which price discovery provisions apply.
Slide 50
APS and PSE have passed the balancing test in over 90% of the time
Slide 51
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 1-Oct 2-Oct 3-Oct 4-Oct 5-Oct 6-Oct 7-Oct 8-Oct 9-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct Passed Test Underscheduling Overscheduling
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 1-Oct 2-Oct 3-Oct 4-Oct 5-Oct 6-Oct 7-Oct 8-Oct 9-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct Passed Test Underscheduling Overscheduling
AZPS Area PSEI Area
Power balance constraint infeasibilities in both APS and PSE have been less than 0.3% of the time in October
Slide 52
0% 10% 20% 30% 40% 50% 1-Oct 2-Oct 3-Oct 4-Oct 5-Oct 6-Oct 7-Oct 8-Oct 9-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct Valid FMM Under-supply Infeasibility Correctable Infeasibilities 0% 10% 20% 30% 40% 50% 1-Oct 2-Oct 3-Oct 4-Oct 5-Oct 6-Oct 7-Oct 8-Oct 9-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct Valid RTD Under-supply Infeasibility Load Bias Limiter Correctable Infeasibilities
Power balance constraint infeasibilities in PSE have been less than 0.3% of the time in October
Slide 53
0% 10% 20% 30% 40% 50% 1-Oct 2-Oct 3-Oct 4-Oct 5-Oct 6-Oct 7-Oct 8-Oct 9-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct Valid RTD Under-supply Infeasibility Load Conformance Correctable Infeasibilities 0% 10% 20% 30% 40% 50% 1-Oct 2-Oct 3-Oct 4-Oct 5-Oct 6-Oct 7-Oct 8-Oct 9-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct Valid FMM Under-supply Infeasibility Correctable Infeasibilities
EIM Price trends
Slide 54
Transfer capabilities in EIM areas
Slide 55
Market Update
Slide 56
Slide 57
Good price convergence between IFM and RTD in September and October.
Slide 58
RT prices higher than DA prices for both NP 15 and SP 15 in September but lower than DA in SP15 in October.
Slide 59
Insufficient upward ramping capacity in ISO increased in October.
Slide 60
Insufficient downward ramping capacity remained low in 2016.
Slide 61
Congestion revenue rights market revenue inadequacy without including auction revenues.
Slide 62
Congestion revenue rights market revenue sufficiency including auction revenues.
Slide 63
Exceptional dispatch volume in the ISO area continued at low levels.
Slide 64
Daily exceptional dispatches by reason
Slide 65
Real-time Bid cost recovery dropped in October
Slide 66
Bid cost recovery (BCR) by Local Capacity Requirement area
Slide 67
Minimum online commitment (MOC)
Slide 68
Pmax of MOC Cleared Units
Slide 69
Enforcement of minimum online commitments in September and October
MOC Name Number (frequency) of hours in September and October Humboldt 7110 1436 MOC TABLE MTN 504 HNTBH 7820 187 Orange County 7630 134 MOC East Nicolaus 4385234 125 SCIT MOC 67 MOC NP15 11 MOC SAN ONOFRE BUS 10 SDGE 7820 3
Slide 70
IFM under-scheduling of solar generation
Slide 71
IFM under-scheduling of wind generation declined in September and October
Slide 72
Renewable (VERS) schedules including net virtual supply and aligns with VER forecast in September and October
http://www.caiso.com/Pages/documentsbygroup.aspx?GroupID=EFF75C 2E-F28E-4087-B88B-8DFFAED828F8
Slide 73
RTD renewable (VERS) curtailment rose since August
Slide 74
RTD renewable (VERS) curtailment versus avoided curtailment
Slide 75
Hourly distribution of maximum RTD renewable (VERS) curtailment in October
Slide 76
Wind, solar and hydro production
Monthly wind (VERS) downward flexibility in FMM
Slide 77
Monthly solar (VERS) downward flexibility in FMM
Slide 78
Monthly solar (VERS) downward flexibility in FMM from 11 AM to 5 PM
Slide 79
Slide 80
ISO area RTCO and RTIEO remains at relatively low levels in September and October.
2015 2016 (YTD) RTCO $55,489,221 $49,049,744 RTIEO $13,817,548 $380,581 Total Offset $69,306,769 $49,430,324
Slide 81
Price correction events increased in September and October
1 2 3 4 5 6 7 8 9 10 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Count of Events Process Events Software Events Data Error Events Tariff Inconsistency
Page 82
EIM BCR in September and October
Slide 83
EIM Exceptional Dispatch in September and October
Day-ahead load forecast
0.0% 0.5% 1.0% 1.5% 2.0% 2.5% 3.0% Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2014 2015 2016
MAPE
Slide 84
Day-ahead peak to peak forecast accuracy
0.0% 0.5% 1.0% 1.5% 2.0% 2.5% 3.0% 3.5% Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2014 2015 2016
MAPE
Slide 85
Day-ahead wind forecast
0.0% 1.0% 2.0% 3.0% 4.0% 5.0% 6.0% 7.0% 8.0% 9.0% 10.0% Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2014 2015 2016
MAE
Slide 86
Day-ahead solar forecast
0.0% 2.0% 4.0% 6.0% 8.0% 10.0% 12.0% 14.0% Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2014 2015 2016
MAE
Slide 87
Real-time wind forecast
0.0% 0.5% 1.0% 1.5% 2.0% 2.5% 3.0% 3.5% 4.0% 4.5% Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2014 2015 2016
MAE
Slide 88
Real-time solar forecast
0% 1% 2% 3% 4% 5% 6% Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2014 2015 2016
MAE
Slide 89
Real-time solar forecast
0% 1% 2% 3% 4% 5% 6% Oct 2014 2015 2016 2016_withCurtailedMW
MAE
2016’s October MAE becomes more comparable to previous years when the Curtailed Solar MW are added back into Actuals.
Slide 90
Load Forecast Adjustments
Gabe Murtaugh
- Sr. Market Monitoring Analyst,
Department of Market Monitoring
Slide 91
Growth in EIM transfer capacity significantly increases market competiveness.
Slide 92
Puget
300 MW 300 MW
PacifiCorp West
126 MW 85 MW
CAISO
899 MW 872 MW
NV Energy
924 MW 1,874 MW
APS PacifiCorp East
468 MW 710 MW 0 MW 293 MW 216 MW 321 MW
Total average transfer capacity (May-Oct 2016)
Congestion into EIM areas is very infrequent.
Puget
1%
(187 MW)
1%
(205 MW)
PacifiCorp West
20%
(27 MW)
2%
(221 MW)
CAISO
2% MW
(790 MW)
.2%
(611 MW)
NV Energy
0% .3% (143 MW)
APS
PacifiCorp East
.3%
(156 MW)
7%
(463 MW)
4% (105 MW) 7%
(150 MW)
1%
(119 MW)
Frequency of congestion in 15-minute market (May-Oct 2016)*
* Average transfer MW during congested intervals in parentheses.
23% (0 MW)
Slide 7
EIM areas separated by congestion from the ISO
- nly 1-3 percent of intervals.
Slide 94
Settlement prices in Arizona largely reflected prices in the ISO during October.
Slide 95 $0 $10 $20 $30 $40 $50 $60 $70 $80 $90 $100 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Average hourly price ($/MWh) Arizona Public Service settlement price Southern California Edison settlement price Bilateral price benchmark
Settlements prices in Puget Sound were lower than the ISO and reflected PacifiCorp West prices.
Slide 96 $0 $10 $20 $30 $40 $50 $60 $70 $80 $90 $100 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Average hourly price ($/MWh) Pacific Gas and Electric settlement price Puget Sound Energy settlement price PacifiCorp West settlement price Bilateral price benchmark
Positive load adjustments were more frequent in NV Energy and the ISO, while negative load adjustments were more frequent in the PacifiCorp areas.
Slide 97
Percent of intervals Average MW Percent of total load Percent of intervals Average MW Percent of total load California ISO 15-minute market 44% 471 1.4% 14%
- 274
1.1% 169 5-minute market 56% 438 1.4% 27%
- 300
1.1% 162 PacifiCorp East 15-minute market 5% 91 1.6% 42%
- 101
1.9%
- 38
5-minute market 9% 88 1.5% 63%
- 125
2.4%
- 71
PacifiCorp West 15-minute market 3% 38 1.5% 43%
- 49
2.2%
- 20
5-minute market 4% 42 1.7% 49%
- 58
2.6%
- 27
NV Energy 15-minute market 48% 132 2.3% 1%
- 171
3.6% 62 5-minute market 44% 95 1.7% 11%
- 83
1.7% 32 Positive load adjustments Negative load adjustments Average hourly bias MW
Load adjustments in NV Energy tended to be greatest in the late afternoon, while PacifiCorp East adjusted by the greatest quantity in the morning.
Slide 98
- 150
- 100
- 50
50 100 150 200 250 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 MW 15-minute market (PacifiCorp East) 5-minute market (PacifiCorp East) 15-minute market (PacifiCorp West) 5-minute market (PacifiCorp West) 15-minute market (NV Energy) 5-minute market (NV Energy)
Policy Update
Brad Cooper Manager, Market Design and Regulatory Policy
Slide 99
Ongoing policy stakeholder initiatives
- Contingency modeling enhancements
– Technical analysis results targeted Dec – Stakeholder call on technical analysis targeted Dec – May 2017 Board Meeting
- Generator contingency and remedial action scheme
modeling – Revised straw proposal targeted Jan 2017 – Jul 2017 Board Meeting
- Stepped transmission constraints
– New schedule being developed – Board Meeting TBD
Slide 100
Ongoing policy stakeholder initiatives (continued)
- Flexible resource adequacy criteria and must-offer
- bligation – phase 2
– Stakeholder call on supplemental issue paper Dec 9 – Revised straw proposal Feb 2017 – Board Meeting TBD
- Bid cost recovery enhancements
– Draft final proposal Dec 2016 – Q1 2017 Board meeting – Projected Fall 2018 implementation
- Self schedules BCR allocation
– Added to the bid cost recovery enhancements initiative
Slide 101
- Commitment Costs and Default Energy Bid Enhancements
– February 2017 Straw proposal – July 2017 Board Meeting – 2018 Implementation
- Metering rules enhancements
– Dec 2016 Board Meeting
- Energy storage and distributed energy resources (ESDER)
Phase 2 – Q1 2017 Board Meeting
Slide 102
Ongoing policy stakeholder initiatives (continued)
Ongoing policy stakeholder initiatives (continued)
- Aliso Canyon - Phase 2
– FERC Order accepting filing Nov 28 – Jan 2017 Implementation
- Stakeholder initiatives catalog
– Final 2017 policy initiatives roadmap Dec 15 – Stakeholder call Dec 22 – Feb 2017 EIM Governing Body and Board Meeting
- Frequency response – phase 2
– Issue paper targeted Dec 2016 – Schedule TBD
Slide 103
Ongoing policy stakeholder initiatives (continued)
- Regional integration and EIM greenhouse gas compliance
– Stakeholder meeting on straw proposal Dec 1 – Draft final proposal Jan 5 – Board Meeting TBD
- Transmission access charge options
– Framework published Dec 6 – Stakeholder meeting Dec 13 – No planned Board action at this time
- Regional resource adequacy
– Framework published Dec 1 – Stakeholder meeting Dec 8 – No planned Board action at this time
Slide 104
Policy stakeholder initiatives coming soon
- Planned to start in Q1 2017
– Resource adequacy enhancements – Economic and maintenance outages
Slide 105
Release Plan Update Janet Morris Director, Program Office
Slide 106
The ISO offers comprehensive training programs
Slide 107
Training calendar - http://www.caiso.com/participate/Pages/Training/default.aspx Contact us - markettraining@caiso.com Date Training January 11 Welcome to the ISO (webinar) February 7 Settlements 101 (Folsom) February 8 Settlements 201 (Folsom)
Release Plan 2016
Slide 108
Implementations by end of 2016
- Demand Response Registration Enhancements
- ADS Client Replacement (Mandatory)
- Acceptable Use Policy - CMRI
Release Plan 2017
Slide 109
Independent 2017
- RTD Local Market Power Mitigation (LMPM) Enhancements
- CRR Clawback Modifications
- MRI-S ACL Groups+ CPG Enhancements (formerly OMAR Replacement)
- PIRP System Decommissioning
- Reactive Power Requirements and Financial Compensation – no system changes
- RIMS Functional Enhancements
- Metering Rules Enhancements
Fall 2017 (tentative, to be confirmed)
- Bidding Rules Enhancements – Part B
- Reliability Services Initiative Phase 1B
- Reliability Services Initiative Part 2
- Commitment Cost Enhancement Phase 3
- EIM 2017 Enhancements
- EIM Portland General Electric (PGE)
Release Plan – 2018 and subject to further planning
Slide 110
Spring 2018
- EIM 2018 Idaho Power Company
Fall 2018 – tentative, subject to impact assessment
- Stepped Transmission Constraints
- Bid Cost Recovery Enhancements
- Generation Contingency and Remedial Action Scheme
- Flexible Resource Adequacy Criteria and Must-offer Obligation Phase 2
- ESDER Phase 2
- Regional Resource Adequacy
- Transmission Access Charge Options
- ADS User Interface Replacement
Subject to further release planning:
- Additional Data Transparency Enhancements (OASIS API changes) – work starting after Fall
2016 release; ISO will make it available for market participants to adopt as they need.
- Contingency Modeling Enhancements
2016 – Demand Response Registration Enhancements
Project Info Details/Date Application Software Changes Enhance Demand Response Registration functionality and processes Develop new registration user interface for DRRS Develop new APIs for support of enhanced registration processes BPM Changes Metering Business Process Changes Automation of internal registration-related processes
Slide 111
Milestone Type Milestone Name Dates Status
Board Approval Board Approval N/A BPMs Publish Final Business Practice Manuals (Metering) Aug 29, 2016
Post Draft BPM changes (Metering) Aug 04, 2016
External BRS External BRS - Enabling Demand Response Phase 2 - Registration Jun 04, 2015
Tariff Tariff N/A Config Guides Config Guide N/A Tech Spec Tech Specs - DRRS Phase 2 - Registration Sep 17, 2015
Market Sim Market Sim Window Sep 19, 2016 - Nov 18, 2016
Production Activation Post-Mrkt Consol - DRRS Phase 2 - Reg Nov 30, 2016
2016– ADS Client Replacement (Mandatory)
Project Info Details/Date Application Software Changes Scope includes updates to work with TLS version 1.0. After January 6, 2017, all prior supported ADS client versions (which includes 5.2.8.0 and 5.2.4.0) will be decommissioned and inaccessible.
Slide 112
ADS Client certified for Windows 7 and 10
Milestone Type Milestone Name Dates Status
Board Approval Board Approval N/A BPMs BPMs N/A External BRS External BRS N/A Tariff Tariff N/A Config Guides Config Guide N/A Tech Spec Tech Spec N/A Market Sim Market Sim Window Oct 12, 2016 - Jan 06, 2017 Production Activation ADS TLS Risk Remediation Jan 06, 2017
2016 – Acceptable Use Policy – CMRI
Project Info Details/Date Application Software Changes Scope includes enforcement of Acceptable Use Policy for CMRI services to support the full implementation of 1 call per service per identity (as designated by certificate) every 5 seconds. An error code of 429 will be returned for any violation instance of the use policy.
Slide 113
Milestone Type Milestone Name Dates Status
Board Approval Board Approval N/A BPMs BPMs N/A External BRS External BRS N/A Tariff Tariff N/A Config Guides Config Guide N/A Tech Spec Tech Spec N/A Market Sim Market Sim Window Aug 23, 2016 - Sep 23, 2016
Production Activation Acceptable Use Policy - CMRI Jan 06, 2017
Slide 114
2016 CMRI URL Standardization
Service Version # Existing URL https://wsstas.caiso.com:4445/sst/runtime.asvc https://wsstas.ecn.wepex.net:4445/sst/runtime.as vc Standardized URL https://ws.caiso.com/sst/cmri https://ws.ecn.wepex.net/sst/cmri MarketAwards v2 Decommission on 12/01/2016 None exists v3 Decommission on 12/01/2016 Supported v4 None exists Supported MarketSchedules v1 Decommission on 12/01/2016 None exists v2 Decommission on 12/01/2016 Supported v3 None exists Supported SchedulePrices v2 Decommission on 12/01/2016 None exists v3 Decommission on 12/01/2016 Supported v4 None exists Supported ExpectedEnergy AllocationDetails v1 Decommission on 12/01/2016 None exists v2 Decommission on 12/01/2016 Supported v3 None exists Supported GreenHouseGas CapData v1 None exists Supported EIMInterchange ScheduleData v1 ResourceMovementP
- int
v1 ResourceLevel Movement v1 EIRForecast v1 ElectricityPriceIndex v1 All other pre Fall 2016 existing services existing Decommission on 12/01/2016 Supported
Slide 115
2016-2017 Projects - Major Milestones Summary
Project Market Simulation Deployment/Activation Decommissioning
Demand Response Registration Enhancements Completed Completed N/A ADS Client Replacement (Mandatory) ADS Client ver 6.0.0.0 made available for testing in MAP Stage on 10/12/2016 ADS Client production-level version 6.0.x available as of 10/28/2016 Availability of production level ADS version started a grace period of approx 2 months for market participants to transition to the new version After January 6, 2017, all prior supported ADS client versions (which includes 5.2.8.0 and 5.2.4.0) will be decommissioned and inaccessible. Acceptable Use Policy - CMRI Completed Jan 6, 2017 N/A ACL Groups (formerly OMAR Replacement and PIRP Decommissioning) TBD TBD ISO decommissions PIRP based upon a two-month buffer period between ACL group functionality being active in Production. MRI-S Customer Partnership Group identified enhancements (formerly OMAR Replacement) TBD TBD OMAR will be decommissioned after a four month grace period starting when MRI-S enhancements deploy to MAP Stage (market simulation).
2017 - Real Time Dispatch Local Market Power Mitigation
Project Info
Details/Date
Application Software Changes
- CMRI – Display mitigated bids from RTD process
- OASIS (Open Access Sametime Information System): Display RTD
reports for Market Clearing, the Pnode clearing, similar to current RTPD reports
- RTM (Real Time Market)
- RTPD: Perform the LMPM run as an integral part of the binding
interval RTPD run
- RTD: Proposed mitigation in RTD run would work the same way
as the current RTPD run BPM Changes
- Energy Imbalance Market (EIM): under the proposed RTD method,
bids are not necessarily mitigated for the whole hour
- RTD MPM will work the same way as the current RTPD MPM
Business Process Changes
- Manage Markets & Grid
- ATF – System Operations: Add MPM Application to Real Time and
annotate inputs and outputs
- ATF – System Operations, Real Time: Add MPM to diagram with inputs
and outputs
- Level II – Manage Real Time Operations – maintain balancing area
Slide 116
2017 - Real Time Dispatch Local Market Power Mitigation (cont.)
Slide 117 Project CMRI OASIS ADS RTD LMPM Update (add RTD results): MPMResults v3 Update (add RTD results)-
- PRC_MPM_RTM_LMP
- PRC_MPM_RTM_NOMOGRAM
- PRC_MPM_RTM_NOMOGRAM_CMP
- PRC_MPM_RTM_FLOWGATE
- PRC_MPM_CNSTR_CMP
- PRC_MPM_RTM_REF_BUS
- ENE_MPM
N/A
Milestone Type Milestone Name Dates Status
Board Approval Board of Governors (BOG) approval Mar 24, 2016
BPMs Posted Market Operations BPM PRR 945 Nov 04, 2016
Post draft EIM BPM Dec 29, 2016 External BRS Post External BRS Apr 05, 2016
Tariff Received FERC approval Nov 08, 2016
Config Guides Configuration Guide N/A Tech Spec Publish Technical Specification - OASIS Apr 08, 2016
Publish Technical Specification - CMRI Apr 14, 2016
Market Sim Market Sim Window Jan 17, 2017 - Feb 03, 2017 Production Activation RTD - Local Market Power Mitigation Enhancement Mar 01, 2017
2017 – Congestion Revenue Rights (CRR) Clawback Modifications
Project Info
Details/Date
Application Software Changes MQS/CRR Clawback: If import bid <= day-ahead price, then the import is not considered a virtual award. If export bid >= day-ahead price, then the export is not considered a virtual award. If an import/export bid/self-schedule in real-time market is less than the day-ahead schedule, then the difference shall be still subject to CRR Clawback rule. CRR Clawback rule should include convergence bids cleared on trading hubs and load aggregation points in the flow impact used to determine if the 10% threshold is reached. Inform Market Participants of CRR annual allocation/auction for 2017. BPM Changes Market Operations Appendix F Business Process Changes TBD
Slide 118
Milestone Type Milestone Name Dates Status
Board Approval Board of Governors Approval Jun 28, 2016
BPMs Publish Final Business Practice Manuals Jan 30, 2017 External BRS Post External BRS Nov 29, 2016
Tariff File Tariff Jan 20, 2017 Receive FERC order Mar 21, 2017 Production Activation CRR Clawback Modification Apr 01, 2017
2017 - MRI-S ACL Groups+ CPG Enhancements
Project Info Details/Date Application Software Changes
The MRI-S metering (MRI-S) application cannot currently support ACL (Access Control List) groups functionality for defining a subset of resources belonging to an SCID. Enhancements to the Application Identity Management (AIM) application will enable the use of ACL groups for SCID-level read-only access for MRI-S. Conducted a Customer Partnership Group meeting on October 20 and reviewed proposed solutions.
BPM Changes
None
Business Process Changes
Potential Level-II business process changes under –
- Manage Market & Reliability Data & Modeling
- Manage Operations Support & Settlements
Slide 119
Milestone Type Milestone Name Dates Status Board Approval Board Approval N/A BPMs Metering BPM Changes N/A External BRS Post External BRS Nov 14, 2016 Tariff Pre-Tariff Filing QRB N/A Tech Spec Publish Tech Specs Nov 02, 2016 Market Simulation Phase 1 - ACL Groups TBD Phase 2 - MRI-S Metering Enhancements TBD Production Activation Phase 1 - ACL Groups TBD Phase 2 - MRI-S Metering Enhancements TBD
MRI-S ACL Groups + CPG Enhancements
Slide 120
* ACL group creation to filter for a read only role at the resource level is not currently available
# System Summary Status Estimated Fix Date 1 MRI-S CIDI 183777, 183993 - MRI-S for Metering Limitation of 100,000 records. Under review See previous slide 2 MRI-S Option to choose UOM is missing on the UI 3 MRI-S CIDI 184018 - Time zone is missing on the UI 4 MRI-S CIDI 183777, 183993 - Modification to AUP policy on data retrieval to include querying by last updated time 5 MRI-S Option to request for data in various time interval in UI 6 MRI-S Ability to view log files within the same organization 7 MRI-S Ability to provide SC ID in the data retrieve request MRI-S *ACL Group – filter read-only at the resource level In process See previous slide
2017 – PIRP Decommissioning
Project Info
Details/Date
Application Software Changes: PIRP/CMRI
- Forecast Data Reporting (resource-level) that was performed in PIRP will be done in
- CMRI. Rolling Hour Ahead, Locked Hour Ahead, and Rolling Day-Ahead forecasts.
- PIRP Decommissioning to occur in 2017
- CMRI to receive the Electricity Price Index for each resource and publish it to the
Market Participants.
- 60 Day PIRP / CMRI parallel production to start when AIM/ACL becomes available.
BPM Changes CMRI Technical Specification; New APIs will be described. Data Transparency
- Independent changes, won’t
impact existing services
- Will be made available in
Production and cutover schedule is discretionary Atlas Reference:
- 1. Price Correction Messages (ATL_PRC_CORR_MSG)
- 2. Scheduling Point Definition (ATL_SP)
- 3. BAA and Tie Definition (ATL_BAA_TIE)
- 4. Scheduling Point and Tie Definition (ATL_SP_TIE)
- 5. Intertie Constraint and Scheduling Point Mapping (ATL_ITC_SP)
- 6. Intertie Scheduling Limit and Tie Mapping (ATL_ISL_TIE)
Energy
- EIM Transfer Limits By Tie (ENE_EIM_TRANSFER_LIMITS_TIE)
- Wind and Solar Summary (ENE_WIND_SOLAR_SUMMARY)
Prices
- MPM Default Competitive Path Assessment List (PRC_MPM_DEFAULT_CMP)
Business Process Changes MPs will receive the VER reports from CMRI rather than PIRP.
Slide 121
2017 – PIRP Decommissioning
Slide 122
Milestone Type Milestone Name Dates Status Board Approval Board Approval N/A BPMs Publish Draft Business Practice Manuals (Market Instruments; PRR 936) Sep 06, 2016 External BRS External Business Requirements Jun 29, 2015 Tariff Tariff Filing Activities N/A Config Guides Settlements Configuration N/A Tech Spec Publish Technical Specifications (CMRI: PIRP Decommissioning) Feb 05, 2016 Publish Technical Specifications (CMRI; Wind and Solar) Apr 15, 2016 Market Sim CMRI Reports; VER Forecast & EPI (Fall 2016 Release) Aug 23 - Sep 23, 2016 PIRP Decommissioning TBD Production Activation CMRI Reports; VER Forecast & EPI (Fall 2016 Release) Oct 01, 2016 AIM / ACL Production Deployment TBD OASIS API Enhancements; 9 Reports TBD PIRP Decommissioning TBD
2017 – Reactive Power Requirements and Financial Compensation
Project Info
Details/Date
Application Software Changes None BPM Changes Generator Interconnection and Deliverability Allocation Procedures
- Reactive power delivery interconnection condition for asynchronous resources.
Generator Interconnection Procedures
- Reactive power delivery interconnection condition for asynchronous resources.
Generator Management
- Generators’ AVR Requirements.
Business Process Changes Develop Infrastructure (DI) (80001)
- Level II - Manage Generator Interconnection Process (GIP) (Logical Group):
Slide 123
Milestone Type Milestone Name Dates Status
BPMs Draft BPM changes TBD Post Draft BPM changes TBD Publish Final Business Practice Manuals TBD Tariff File Tariff 12/5/2016
Tariff Receive FERC order 2/1/2017 Production Activation Reactive Power and Financial Compensation activation 4/1/2017
2016 – RIMS Functional Enhancements
Project Info Details/Date Status
Application Software Changes Functional enhancements resulting from the Customer Partnership Group CPG. More details to be provided in the future. BPM Changes Generator Interconnection and Deliverability Allocation Procedures Generator Interconnection Procedures Managing Full Network Model Metering Generator Management Transmission Planning Process Customer Partnership Group 10/16/15 Application and Study Webinar 3/31/16
Slide 124
Milestone Type Milestone Name Dates Status
Board Approval Board approval not required N/A BPMs Generator Interconnection and Delivery Allocation Apr 29, 2016
External BRS External BRS not Required N/A Tariff No Tariff Required N/A Config Guides Configuration Guides not required N/A Tech Spec No Tech Specifications Required N/A Production Activation RIMS5 App & Study Mar 21, 2016
RIMS5 Queue Management, Transmission and Generation TBD
2017 – Metering Rules Enhancements
Project Info Details/Date Application Software Changes N/A BPM Changes Metering
- EIM BPM will be updated to explain Metering data reporting access
based on transitions from ISOME to SCME (shall transition to submission of SQMD meter data to Metering Data submission portal) or SCME to ISOME (shall be able to review historical meter data in MRI-S when resource was SCME). Definitions & Acronyms BPM Changes
- New Tariff and Business Process/System acronyms.
Business Process Changes
- Manage Transmission & Resource Implementation
- Manage Market & Reliability Data & Modeling (MMR) (80004)
- ISO Meter Certification (MMR LII)
- Metering Systems Access (Production) (MMR LII)
- Metering System Configuration for Market Resources (MMR
LII)
- Station Power Implementation (MMR LIII)
- Application Flow - Billing & Settlements
- Analyze Missing Measurement Report (MOS LIII)
- Manage Market Billing & Settlements (MOS LII)
- Manage Market Quality System (MOS LII)
- Manage Rules of Conduct (MOS LII)
- Meter Data Acquisition & Processing (MOS LII)
- SCME Self Audit (MOS LII)
Slide 125
2017 – Metering Rules Enhancements
Slide 126
Milestone Type Milestone Name Dates Status
Board Approval Obtain Board of Governors Approval Dec 14, 2016 BPMs Metering BPM TBD Energy Imbalance Market BPM TBD Publish Final Business Practice Manuals TBD External BRS External Business Requirements N/A Tariff File Tariff N/A Receive FERC order N/A Config Guides Settlements N/A Tech Spec Tech Specs N/A Market Sim Market Sim Window N/A Production Activation Metering Rules Enhancements Apr 01, 2017
Fall 2017 - Bidding Rules Enhancements – Part B
Slide 127
Project Info Details/Date Application Software Changes
- MasterFile:
- Provide ability to submit requests for new fuel regions (Policy Section 8.1.1.3)
- Include resource-specific start-up electricity costs in proxy costs based on wholesale
projected electricity price, unless resource verifies costs incurred are retail rates (RDT change)
- Allow ability to submit a weighting when using a more than one fuel region.
- Automation of the Aliso Canyon process for creating NEW Fuel Regions
- OASIS:
- Publish fuel regions (public information)
Business Process Change
- Manage Transmission & Resource Implementation
- Manage Entity & Resource Maintenance Updates
- Manage Full Network Model Maintenance
- Manage Market Quality System (MQS)
BPMs
Market Instruments, Market Operations, Reliability Requirements Milestone Type Milestone Name Dates Status
Board Approval BOG Approval Mar 25, 2016
BPMs Draft BPM changes TBD Post Draft BPM changes TBD Publish Final Business Practice Manuals TBD External BRS Post External BRS Dec 15, 2016 Tariff File Tariff TBD Receive FERC order TBD Config Guides Prepare Draft Configuration Guides Apr 01, 2017 Tech Spec Create ISO Interface Spec (Tech spec) Apr 01, 2017 Market Sim Market Sim Window Jul 05, 2017 - Jul 31, 2017 Production Activation Bidding Rules Part B Oct 01, 2017
Fall 2017 - Reliability Services Initiative Phase 1B
Project Info Details/Date Status
Application Software Changes
Developments under consideration include: Scope:
- Default flexible qualifying capacity provisions for phase 2 consideration (we might need data collection
performed in order to support RSI Phase 2
- Redesign of Replacement Rule for System RA and Monthly RA Process
- RA Process and Outage Rules for implementation for 2017 RA year
- Scope not delivered in RSI Phase 1A (Grandfathered Contracts, RAAM Decommissioning – SCP & CPM
screens from RAAM to CIRA, Acquired Contracts, OASIS reporting, web services related to APIs for CSP
- ffers, APIs for Generic/Flex Substitutions, and Release of Generic/Flex Subs – UI & API)
Impacted Systems:
- CIRA
- OASIS
- Integration (B2B)
- Settlements
- Decommission RAAM
Business Process Changes
Manage Market & Reliability Data & Modeling Slide 128
Milestone Type Milestone Name Dates Status
Board Approval Board Approval May 12, 2015
BPMs Draft BPM Changes - Outage Mgmt, Reliability Reqmts TBD Post Draft BPM changes TBD Publish Final Business Practice Manuals TBD External BRS Post External BRS Dec 16, 2016 Tariff File Tariff TBD Receive FERC order TBD Config Guides Config Guide Apr 01, 2017 Tech Spec Create ISO Interface Spec (Tech spec) Apr 01, 2017 Market Sim Market Sim Window Jul 05, 2017 - Jul 31, 2017 Production Activation Reliability Services Initiative Phase 1B Oct 01, 2017
Project Info Details/Date
Application Software Changes Scope: 1. Clarify use-limited registration process and documentation to determine opportunity costs 2. Each submission evaluated on a case-by-case basis to determine if the ISO can calculate opportunity costs
- ISO calculated; Modeled limitation
- Market Participant calculated; Negotiated limitation
3. Enhanced definition of “use-limited” in response to FERC’s rejection of the proposed definition in Cost Commitment Enhancements Phase 2 4. Change Nature of Work attributes (Outage cards)
- 1. Modify use-limited reached for RAAIM Treatment
- 2. Add new demand response nature of work attribute for RDRR and PDR
5. Market Characteristics
- 1. Maximum Daily Starts
- 2. Maximum MSG transitions
- 3. Ramp rates
Impacted Systems:
- 1. CIRA
- 2. CMRI
- 3. IFM/RTN
- 4. SIBR
- 5. MasterFile
- 6. OASIS
- 7. OMS
- 8. Settlements
BPM Changes Market Instruments, Outage Management, Reliability Requirement, Market Operations, Settlements & Billing Business Process Changes Level II – Manage Reliability Requirements Level II – Manage Day Ahead Market
Slide 129
Fall 2017 - Commitment Cost Enhancements Phase 3
Slide 130
Fall 2017 - Commitment Cost Enhancements Phase 3 (cont.)
Milestone Type Milestone Name Dates Status
Board Approval Board of Governors (BOG) Approval Mar 25, 2016
BPMs Draft BPM changes TBD Post Draft BPM changes TBD Publish Final Business Practice Manuals TBD External BRS Post External BRS Dec 30, 2016 Tariff File Tariff TBD Receive FERC order TBD Config Guides Config Guide Apr 01, 2017 Tech Spec Create ISO Interface Spec (Tech spec) Apr 01, 2017 Market Sim Market Sim Window Jul 05, 2017 - Jul 31, 2017 Production Activation Commitment Costs Phase 3 Oct 01, 2017
Fall 2017 – EIM Enhancements 2017
Project Info
Details/Date
Application Software Changes Addresses the following enhancements identified by policy, operations, technology, business and market participants. The following requirements are being defined:
- EIM Entity access reports
- BAAOP provisioning in AIM
- EIM Data report enhancements to support EIM Entity settlements
- Joint Owned Units modeling
- Allow MSG resource to send actual configuration in telemetry for RTM
- Comprehensive model for startup and transition energy in DAM, RTM,
RTBS, MQS BPM Changes TBD Business Process Changes TBD
Slide 131
Slide 132
Fall 2017 – EIM Enhancements 2017 (cont.)
Milestone Type Milestone Name Dates Status
Board Approval Obtain Board of Governors Approval N/A BPMs Draft BPM changes TBD Post Draft BPM changes TBD Publish Final Business Practice Manuals TBD External BRS External BRS complete Dec 30, 2016 Tariff File Tariff TBD Receive FERC order TBD Config Guides Design review - BPM and Tariff SMEs Apr 01, 2017 Tech Spec Publish Technical Specifications Apr 06, 2017 Market Sim Market Sim Window Jul 05, 2017 - Jul 31, 2017 Production Activation EIM Enhancements 2017 Oct 01, 2017
Fall 2017 – EIM Portland General Electric
Project Info Details/Date Application Software Changes Implementation of Portland General Electric as an EIM Entity. BPM Changes EIM BPM will be updated to reflect new modeling scenarios identified during PGE implementation and feedback from PGE. Market Simulation ISO promoted market network model including PGE area to non- production system and allow PGE exchange data in advance of Market Simulation. Parallel Operations August 1 – September 30, 2017
Slide 133
Milestone Type Milestone Name Dates Status
Board Approval Board approval not required N/A BPMs BPMs N/A External BRS No external BRS N/A Tariff Tariff filing at FERC N/A Config Guides Settlements N/A Tech Spec Tech Specs N/A Market Simulation Market Sim Environment Window Jun 29, 2017 – Jul 31, 2017 Production Activation EIM - Portland General Electric Oct 01, 2017
Annual Functional Release Lifecycle
Slide 134
The ISO has published the Annual Functional Release Lifecycle draft on the Release Planning page
- http://www.caiso.com/Documents/AnnualFunctionalReleaseLifecycle.pdf
This document describes the planning through execution phases of the ISO annual functional release lifecycle process including
- Introduction
- Background
- Scope
- Annual Functional Release Lifecycle
- Exceptions
- Contingency Planning
- External Deliverables
- Process Interfaces
- Stakeholder Implementation Interactions
The ISO encourages Market Participants to review the document and provide any feedback.
Market Performance and Planning Forum 2017 Schedule – Mark Your Calendars
- January 18
- March 14
- May 16
- July 18
- September 19
- November 14
Questions or meeting topic suggestions: Submit through CIDI - select the “Market Performance and Planning Forum” category
Slide 135