Market Performance and Planning Forum December 7, 2016 Objective: - - PowerPoint PPT Presentation

market performance and planning forum
SMART_READER_LITE
LIVE PREVIEW

Market Performance and Planning Forum December 7, 2016 Objective: - - PowerPoint PPT Presentation

Market Performance and Planning Forum December 7, 2016 Objective: Enable dialogue on implementation planning and market performance issues Review key market performance topics Share updates to 2016 release plans, resulting from


slide-1
SLIDE 1

Market Performance and Planning Forum

December 7, 2016

slide-2
SLIDE 2

Objective: Enable dialogue on implementation planning and market performance issues

  • Review key market performance topics
  • Share updates to 2016 release plans, resulting from

stakeholders inputs

  • Provide information on specific initiatives

–to support Market Participants in budget and resource planning

  • Focus on implementation planning; not on policy
  • Clarify implementation timelines
  • Discuss external impacts of implementation plans
  • Launch joint implementation planning process

Slide 2

slide-3
SLIDE 3

Market Performance and Planning Forum

Agenda – December 7, 2016

12:00 – 1:00 Lunch 1:00 – 1:30 Market Results – PSE and APS Integration Gabe Murtaugh 1:30 – 2:00 Policy Update Brad Cooper 2:00 – 3:00

  • Release Update
  • Annual Functional Release Lifecycle

Janet Morris Time: Topic: Presenter: 10:00 – 10:05 Introduction, Agenda Kristina Osborne 10:05 – 10:20 Real-Time Transfer Limit Increases Danny Johnson 10:20 – 10:45 November 9 Frequency Deviation Event John Phipps 10:45 – 12:00 Market Performance and Quality Update Guillermo Bautista Alderete Warren Katzenstein Amber Motley

Slide 3

slide-4
SLIDE 4

Real-Time Transfer Limit Increases

Danny Johnson

  • Sr. Operations Engineer, Operations Planning - South

Slide 4

slide-5
SLIDE 5

Increase Transfer Capability on WECC Paths

Slide 5

slide-6
SLIDE 6

Aliso Canyon Authority

  • CAISO received authority to “reserve internal transfer

capability into Southern California”

  • Have since moved to retire this authority as we believe

we can instead use Peak RC SOL methodology to increase Real Time transfer if needed.

Page 6

slide-7
SLIDE 7

Justification for Real Time Uprate

Peak RC System Operating Limit (SOL) Methodology – Section 6 specifies that in ‘sub-seasonal’ time horizons the acceptable performance for Credible Multiple Contingencies can be relaxed if system conditions do not allow for the planned level of performance – This means in Real Time operations limits established using more stringent criteria for CMC can be revaluated during emergency NERC EOP-002-3.1 – Section 3.4 allows for a revision to SOL limits given RT information following the issuance of a EEA (Energy Emergency Alert) by the ISO.

Slide 7

slide-8
SLIDE 8

Path Limits

Slide 8

  • Path limits are based upon offline powerflow studies
  • Does not account for Seasonal Variations or changing

load profiles

  • Path limits are often pre-contingency proxy MW limits

across multiple transmission elements – Doesn’t account for minor changes in neighboring network topology due to outages – Doesn’t account for voltage conditions.

  • Equipment ratings are based upon Amp rating.
  • MVA = Amp*Voltage;
  • MW limits are converted from MVA limits based

upon studied or assumed power factor, not RT/Operational power factor

slide-9
SLIDE 9

How would CAISO implement?

CAISO RT Operations can utilize Real Time Contingency Analysis (RTCA) to monitor the actual element the path limit is trying to protect for More accurate limit because:

  • Rather then limiting flows to the pre-contingency proxy

limit, CAISO can monitor and protect against post contingency overloads on the actual limiting element

  • Allows for utilization of Real Time voltage conditions in

monitoring limit

  • Accounts for changes in neighboring area topology
  • RTCA RAS functionality allows for incorporating Real

Time congestion relief offered via RAS operation

Slide 9

slide-10
SLIDE 10

Use Case – Path 26 (North-to-South)

Path Details

  • 4000 MW limit from transfer capability of three transmission lines
  • Is composed of Midway-Vincent #1 + Midway-Vincent #2 +

Midway-Whirlwind #1 transmission lines

  • Is thermally limited by CMC of two of the three lines composing

path

  • Path limit is based upon assumed RAS operation at time of study;

Gen Drop in PG&E and Load Shed in SCE

If necessary CAISO can increase Real Time limit by monitoring CMC in RTCA

– Accounts for additional load being armed in SCE; Load armed by RAS has increased significantly since Path Limit was set in 2006 – Controls to a MVA limit based upon Amp rating and post- contingency voltage. – Real Time limit above posted SOL achievable

Slide 10

slide-11
SLIDE 11

Impact on Market Operation

  • CAISO plans to use this methodology to increase limits

in Real Time only during emergency conditions. This will be following exhaustion of all available generation and utilization of all available demand response – Due to the Real Time data required this can not be implemented in IFM. IFM and RTM under normal conditions will continue to operate with the current ratings from CAISO Transmission Register

  • Real Time Transfer Increases will NOT be posted in TTC
  • Will be used to avoid pre-contingency load shedding

Slide 11

slide-12
SLIDE 12

November 9 Frequency Deviation Event

John Phipps Director, Real-Time Operations

Slide 12

slide-13
SLIDE 13

Slide 13

November 9 Frequency Deviation Event

– Event Description – At 11:00 a normal data transfer process with inputs for the market

  • ccurred on schedule. A conflict in the process corrupted an input

that was then transferred into the market software. The next market run at 11:15 failed and advisory results were sent out based on the last successful run at 10:59. The issues and troubleshooting continued through the hour until the issue was found and fixed around 12:10. Additional related issues were discovered and fixed at approximately 12:39. – Around 11:59, the market runs started producing undesirable

  • results. The ISO System Operators intervened by identifying and

blocking the undesirable dispatches. This continued until 13:35 in

  • rder to keep the undesirable instructions from being sent to the

market participants via ADS. During this time period the ISO System Operators sent out multiple market messages to Scheduling Coordinators in order to raise awareness and prevent resources from following undesirable startup or shutdown

  • instructions. Scheduling Coordinators were encouraged to call the

ISO to validate instructions before starting or shutting down any units.

slide-14
SLIDE 14

Slide 14

November 9 Frequency Deviation Event

– 13:33 the ISO market software sent out decremental dispatch instructions of approximately 2500 MW to multiple generator resources via the Automatic Dispatch System (ADS) before the ISO’s System Operators could block or

  • verride the dispatch instructions. The ISO’s Operators

verbally instructed Scheduling Coordinators to not follow the dispatches, but 1214 MW of the dispatch included fast moving resources and 730 MW of additional resources which automatically responded to the dispatch signal and reduced their output over an 11 minute period. This reduction in generation output caused the CAISO ACE and System Frequency to deviate. – At 13:35 BAAL was exceeded. At 13:45 ACE was at its lowest point -3245MW and Frequency was 59.834 HZ. – 13:53 BAAL was within limits, ACE and Frequency were recovered.

slide-15
SLIDE 15

Slide 15

November 9 Frequency Deviation Event

Event Follow-up

  • Action Items

– Review both automated and manual controls for improvement – Review ramp rates and expectations of units to ramp

  • ver 5 minutes

– Lessons learned training and delivery by operators involved in the event

slide-16
SLIDE 16

Market Performance and Quality Update

Guillermo Bautista Alderete, Ph.D. Manager, Market Validation and Quality Analysis Warren Katzenstein Lead Engineering Specialist Amber Motley Manager, Short Term Forecasting

Slide 16

slide-17
SLIDE 17

Adjustment to Regulation Capacity Requirements

Slide 17

slide-18
SLIDE 18

Control Performance and variable energy resources’ production affect the quantity of regulation procured

  • Control Performance

– Measures the ability to adequately support the interconnection frequency – Exceedance of Balancing Authority Ace Limits (BAAL)1 – Noticed a decline in real-time CPS1 performance – Led to procured regulation up/regulation down depletion during high renewable penetration/low load periods

  • High renewable penetration/low load periods

– Windy and cloudy conditions exacerbate wind and solar production variability causing larger deviations from forecast – Erratic weather (seasonal) during low load periods

Slide 18

slide-19
SLIDE 19

Method for Determining Regulation Capacity

  • For each hour, the ISO determines a percentage of forecasted

demand to set regulation capacity

  • The amount of regulation capacity for a given month is informed by:

– Forecast Uncertainty Related To:

  • Demand Forecast Deviations
  • Solar Forecast Deviations
  • Wind Forecast Deviations

– Seasonal/Daily Parameters

  • New considerations

– Separation of Regulation Need in relation to Regulation Up and Regulation Down – Hourly Analysis of Historical Regulation Dispatch – Anticipated variability / forecast uncertainty in weather conditions

Slide 19

slide-20
SLIDE 20

Method for Determining Regulation Capacity Cont.

  • Historical Need

– For each hour, examine the 95th percentile of regulation required as calculated by the control algorithm – Use data from the same month last year to inform procurement for the current month (i.e. Oct 2015 informs Oct 2016)

  • Anticipated variability / forecast uncertainty

– Examine performance from recent days that had higher forecast uncertainty in order to inform change in procurement related to weather – Example is a large weather system moving across California causing variability in cloud cover and wind speed/direction.

Slide 20

slide-21
SLIDE 21

50 100 150 200 250 300 350 400 450 500 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

Regulation Up Minimum Capacity (MW) Hour Ending

Jan Feb Mar Apr May Jun Jul Aug SEP OCT NOV DEC

Seasonal Trends are Present with New Method (Regulation Up)

Slide 21

Values above are based on historical information and are subject to change.

slide-22
SLIDE 22

100 200 300 400 500 600 700 800 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

Regulation Down Minimum Capacity (MW) Hour Ending

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Seasonal Trends (Regulation Down)

Slide 22

Values above are based on historical information and are subject to change.

slide-23
SLIDE 23

May 2016 Regulation Procurement Versus October 2016 Procurement

Slide 23

  • 1000
  • 800
  • 600
  • 400
  • 200

200 400 600 800 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Regulation Requirement (MW) Hour of the Day (Hour Ending) Spring 2016 Regulation Capacity Oct 2016 Regulation Capacity

slide-24
SLIDE 24

October 2016 Results

Slide 24

Percentage of time with insufficient capacity: 1%

slide-25
SLIDE 25

Flexible Ramp Product Update

Slide 25

slide-26
SLIDE 26

Flexible Ramp Product

  • Flexible Ramp product went live on November 1, 2016
  • There is both upward and downward definitions for the

product.

  • Each EIM area has its own requirement, and there is

also a system-wide EIM area enforced in the real-time market.

  • There is also a flexible ramp sufficiency test done prior to

the real-time market.

  • Requirements are based on historical data and

calculated in the Balancing Area Ramp Requirement (BARR) application.

Slide 26

slide-27
SLIDE 27

What is the Balancing Area Ramp Requirement Tool?

  • The Balancing Area Ramp Requirement (BARR) tool

calculates the uncertainty requirement and the demand curves for the Flex Ramp Product

  • The uncertainty requirements are hourly values

calculated every day using the BARR tool

  • Uncertainty requirements are based on net load forecast

error

  • Net load = Load – Wind - Solar
  • The demand curves are the prices the system is willing

to pay for a given quantity of flex ramp capacity

Slide 27

slide-28
SLIDE 28

Flexible Ramp Uncertainty Requirement: 5-minute Real-Time Dispatch (RTD)

Slide 28

RTD Net Load Forecast Error is difference between the binding interval net load forecast and the prior market run first advisory net load forecast

slide-29
SLIDE 29

Flexible Ramp Uncertainty Requirement: 15-minute Real-Time Pre-Dispatch (RTPD)

Slide 29

RTPD Net Load Forecast Error is maximum difference between the three RTD binding interval net load forecasts and the associated RTPD first advisory net load forecast

RTPD

slide-30
SLIDE 30

Example of the Hourly Distribution of Data that Comprises the Histogram for Each EIM Entity

Slide 30

slide-31
SLIDE 31

Example of the Hourly Distribution of Data and the Calculated Uncertainty Requirements (Red Lines)

Slide 31

slide-32
SLIDE 32

An Example of the Flex Ramp Product Uncertainty Calculation

  • Flex Up and Down Uncertainty Requirement could be calculated as

follows: – For each hour, gather the set of recent net load forecast errors for the appropriate market uncertainty – Group weekdays and weekends separately due to characteristic differences

  • Weekdays use last 40 days of net load forecast error
  • Weekends use last 20 days of net load forecast error

– The flex up uncertainty requirement is the 97.5 percentile – The flex down uncertainty requirement is the 2.5 percentile

  • Daily thresholds are calculated using a similar process but with a

larger set of data – Significant reduction in % of time thresholds are setting the requirement compared to the Flex Ramp Constraint

Slide 32

slide-33
SLIDE 33

Demand Curves

  • The demand curves are used to determine how much

flexible ramp capacity the system will procure

  • One demand curve for each EIM entity and ISO plus the

EIM Total Area (including ISO) for 7 total demand curves

  • The demand curves are the distribution of net load errors

multiplied by the energy penalty price cap or floor – The penalty price cap is $1000 per MWh – The penalty price floor is $-150 per MWh

  • The maximum price is $247 per MW
  • The minimum price is $-155 per MW

Slide 33

slide-34
SLIDE 34

Constructing a Demand Curve

  • A demand curve starts with the probability distribution of net

load forecast errors – This is the same set of data that is used for determining the uncertainty requirement

  • The flex ramp up demand curve is built by calculating the

percent of data that is greater than a given MW value

  • The flex ramp down demand curve is built by calculating the

percent of data that less than a given MW value

  • The percentage is converted a price by multiplying by either

the energy penalty price cap or price floor

  • Finally, the curve is transformed from MW to Relaxation

Capacity by subtracting the MW values from the uncertainty requirement

Slide 34

slide-35
SLIDE 35

Constructing a Demand Curve (Cont.)

  • The OASIS published demand curves are comprised of two

components – The amount of capacity to relax the uncertainty requirement – The price associated for relaxing the uncertainty requirement

  • Example

– With an uncertainty requirement of 100 MW, a relaxation capacity of 15 MW, and a price of $25 per MW – This means the market procured 85 MW of flexible capacity at a price of $25 per MW

Slide 35

slide-36
SLIDE 36

0% 5% 10% 15% 20% 25% 30% 35% 40% 45% 20 40 60 80 100 120 140 160

Percent of Data Greater than A Given Net Load Forecast Error (%) Net Load Forecast Error Between RTPD Advisory and RTD Binding (MW)

Example of Constructing a Flex Up Demand Curve: Start with Probability Distribution of Net Load Forecast Errors

Slide 36

Curves are limited to the flex up or down uncertainty requirement

slide-37
SLIDE 37

Convert Percentage to Price by Multiplying the Curve by the Energy Penalty Price Cap ($1000 per MWh)

Slide 37

50 100 150 200 250 300 350 400 450 20 40 60 80 100 120 140 160

Price ($/MW) Net Load Forecast Error Between RTPD Advisory and RTD Binding (MW)

slide-38
SLIDE 38

Convert x-axis to Relaxation MW by Subtracting the Net Load Forecast Errors From the Uncertainty Requirement

Slide 38

50 100 150 200 250 300 350 400 450 20 40 60 80 100 120 140 160

Price ($/MW) Relaxaion Capacity (MW)

slide-39
SLIDE 39

The Curve is then Segmented for Use in the Market Optimization

Slide 39

50 100 150 200 250 300 350 400 450 20 40 60 80 100 120 140 160

Price ($/MW) Relaxation Capacity (MW)

slide-40
SLIDE 40

Finally, the Curve is Capped (if Required) at the Minimum or Maximum Price ($-155/MW or $247/MW)

Slide 40

50 100 150 200 250 300 350 20 40 60 80 100 120 140 160

Price ($/MW) Relaxation Capacity (MW) The segmented demand curve is then capped at a price of $247 per MW

slide-41
SLIDE 41

FRP performance

Slide 41

slide-42
SLIDE 42

FRP requirements and prices driven by the hourly profile needs

Slide 42

slide-43
SLIDE 43

With FRP construct, the EIM area generally drives the

  • verall procurement

Slide 43

  • 2,500
  • 2,000
  • 1,500
  • 1,000
  • 500

500 1,000 1,500 2,000 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Flex Ramp (MW) APS NV Energy PSE PACW PACE ISO Credit Upward/Downward requirement

slide-44
SLIDE 44

Flexible Ramp requirements adjusted with FRP activation

Slide 44

slide-45
SLIDE 45

Hourly profile of ISO FRP requirements

Slide 45

slide-46
SLIDE 46

Gas Price Update

  • FERC clarified use of daily ICE gas price index
  • Normal cycle calculates blended gas price indices the

prior night which is used for both DAM and RTM markets.

  • With new provisions, the ICE index available in the

morning is used for the DAM market run.

  • When no ICE price index is available, it defaults to use

previous night blended index.

Slide 46

slide-47
SLIDE 47

Gas price difference of using morning ICE gas price update

Slide 47

slide-48
SLIDE 48

Gas price difference of using morning ICE gas price update

Slide 48

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

  • 20%
  • 15%
  • 10%
  • 5%

0% 5% 10% 15% 20% 25% 25-Oct 27-Oct 29-Oct 31-Oct 2-Nov 4-Nov 6-Nov 8-Nov 10-Nov 12-Nov 14-Nov 16-Nov 18-Nov 20-Nov 22-Nov 24-Nov 26-Nov 28-Nov 30-Nov 2-Dec 4-Dec % of Volume Traded % Price Difference ($/MMBTu) Volume SCE CityGate Hub

slide-49
SLIDE 49

Gas price difference of using morning ICE gas price update

Slide 49

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

  • 20%
  • 15%
  • 10%
  • 5%

0% 5% 10% 15% 20% 25% 25-Oct 27-Oct 29-Oct 31-Oct 2-Nov 4-Nov 6-Nov 8-Nov 10-Nov 12-Nov 14-Nov 16-Nov 18-Nov 20-Nov 22-Nov 24-Nov 26-Nov 28-Nov 30-Nov 2-Dec 4-Dec % of Volume Traded % Price Difference ($/MMBTu) Volume KRN Del Pool Hub

slide-50
SLIDE 50

EIM Update

  • Arizona Public Service (APS) and Puget Sound (PSE)

joined the EIM market on October 1, 2016.

  • In the first hours after the activation, market observed

minor transitional issues.

  • Both entities are under the six-month transitional period,

under which price discovery provisions apply.

Slide 50

slide-51
SLIDE 51

APS and PSE have passed the balancing test in over 90% of the time

Slide 51

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 1-Oct 2-Oct 3-Oct 4-Oct 5-Oct 6-Oct 7-Oct 8-Oct 9-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct Passed Test Underscheduling Overscheduling

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 1-Oct 2-Oct 3-Oct 4-Oct 5-Oct 6-Oct 7-Oct 8-Oct 9-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct Passed Test Underscheduling Overscheduling

AZPS Area PSEI Area

slide-52
SLIDE 52

Power balance constraint infeasibilities in both APS and PSE have been less than 0.3% of the time in October

Slide 52

0% 10% 20% 30% 40% 50% 1-Oct 2-Oct 3-Oct 4-Oct 5-Oct 6-Oct 7-Oct 8-Oct 9-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct Valid FMM Under-supply Infeasibility Correctable Infeasibilities 0% 10% 20% 30% 40% 50% 1-Oct 2-Oct 3-Oct 4-Oct 5-Oct 6-Oct 7-Oct 8-Oct 9-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct Valid RTD Under-supply Infeasibility Load Bias Limiter Correctable Infeasibilities

slide-53
SLIDE 53

Power balance constraint infeasibilities in PSE have been less than 0.3% of the time in October

Slide 53

0% 10% 20% 30% 40% 50% 1-Oct 2-Oct 3-Oct 4-Oct 5-Oct 6-Oct 7-Oct 8-Oct 9-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct Valid RTD Under-supply Infeasibility Load Conformance Correctable Infeasibilities 0% 10% 20% 30% 40% 50% 1-Oct 2-Oct 3-Oct 4-Oct 5-Oct 6-Oct 7-Oct 8-Oct 9-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct Valid FMM Under-supply Infeasibility Correctable Infeasibilities

slide-54
SLIDE 54

EIM Price trends

Slide 54

slide-55
SLIDE 55

Transfer capabilities in EIM areas

Slide 55

slide-56
SLIDE 56

Market Update

Slide 56

slide-57
SLIDE 57

Slide 57

Good price convergence between IFM and RTD in September and October.

slide-58
SLIDE 58

Slide 58

RT prices higher than DA prices for both NP 15 and SP 15 in September but lower than DA in SP15 in October.

slide-59
SLIDE 59

Slide 59

Insufficient upward ramping capacity in ISO increased in October.

slide-60
SLIDE 60

Slide 60

Insufficient downward ramping capacity remained low in 2016.

slide-61
SLIDE 61

Slide 61

Congestion revenue rights market revenue inadequacy without including auction revenues.

slide-62
SLIDE 62

Slide 62

Congestion revenue rights market revenue sufficiency including auction revenues.

slide-63
SLIDE 63

Slide 63

Exceptional dispatch volume in the ISO area continued at low levels.

slide-64
SLIDE 64

Slide 64

Daily exceptional dispatches by reason

slide-65
SLIDE 65

Slide 65

Real-time Bid cost recovery dropped in October

slide-66
SLIDE 66

Slide 66

Bid cost recovery (BCR) by Local Capacity Requirement area

slide-67
SLIDE 67

Slide 67

Minimum online commitment (MOC)

slide-68
SLIDE 68

Slide 68

Pmax of MOC Cleared Units

slide-69
SLIDE 69

Slide 69

Enforcement of minimum online commitments in September and October

MOC Name Number (frequency) of hours in September and October Humboldt 7110 1436 MOC TABLE MTN 504 HNTBH 7820 187 Orange County 7630 134 MOC East Nicolaus 4385234 125 SCIT MOC 67 MOC NP15 11 MOC SAN ONOFRE BUS 10 SDGE 7820 3

slide-70
SLIDE 70

Slide 70

IFM under-scheduling of solar generation

slide-71
SLIDE 71

Slide 71

IFM under-scheduling of wind generation declined in September and October

slide-72
SLIDE 72

Slide 72

Renewable (VERS) schedules including net virtual supply and aligns with VER forecast in September and October

http://www.caiso.com/Pages/documentsbygroup.aspx?GroupID=EFF75C 2E-F28E-4087-B88B-8DFFAED828F8

slide-73
SLIDE 73

Slide 73

RTD renewable (VERS) curtailment rose since August

slide-74
SLIDE 74

Slide 74

RTD renewable (VERS) curtailment versus avoided curtailment

slide-75
SLIDE 75

Slide 75

Hourly distribution of maximum RTD renewable (VERS) curtailment in October

slide-76
SLIDE 76

Slide 76

Wind, solar and hydro production

slide-77
SLIDE 77

Monthly wind (VERS) downward flexibility in FMM

Slide 77

slide-78
SLIDE 78

Monthly solar (VERS) downward flexibility in FMM

Slide 78

slide-79
SLIDE 79

Monthly solar (VERS) downward flexibility in FMM from 11 AM to 5 PM

Slide 79

slide-80
SLIDE 80

Slide 80

ISO area RTCO and RTIEO remains at relatively low levels in September and October.

2015 2016 (YTD) RTCO $55,489,221 $49,049,744 RTIEO $13,817,548 $380,581 Total Offset $69,306,769 $49,430,324

slide-81
SLIDE 81

Slide 81

Price correction events increased in September and October

1 2 3 4 5 6 7 8 9 10 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Count of Events Process Events Software Events Data Error Events Tariff Inconsistency

slide-82
SLIDE 82

Page 82

EIM BCR in September and October

slide-83
SLIDE 83

Slide 83

EIM Exceptional Dispatch in September and October

slide-84
SLIDE 84

Day-ahead load forecast

0.0% 0.5% 1.0% 1.5% 2.0% 2.5% 3.0% Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2014 2015 2016

MAPE

Slide 84

slide-85
SLIDE 85

Day-ahead peak to peak forecast accuracy

0.0% 0.5% 1.0% 1.5% 2.0% 2.5% 3.0% 3.5% Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2014 2015 2016

MAPE

Slide 85

slide-86
SLIDE 86

Day-ahead wind forecast

0.0% 1.0% 2.0% 3.0% 4.0% 5.0% 6.0% 7.0% 8.0% 9.0% 10.0% Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2014 2015 2016

MAE

Slide 86

slide-87
SLIDE 87

Day-ahead solar forecast

0.0% 2.0% 4.0% 6.0% 8.0% 10.0% 12.0% 14.0% Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2014 2015 2016

MAE

Slide 87

slide-88
SLIDE 88

Real-time wind forecast

0.0% 0.5% 1.0% 1.5% 2.0% 2.5% 3.0% 3.5% 4.0% 4.5% Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2014 2015 2016

MAE

Slide 88

slide-89
SLIDE 89

Real-time solar forecast

0% 1% 2% 3% 4% 5% 6% Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2014 2015 2016

MAE

Slide 89

slide-90
SLIDE 90

Real-time solar forecast

0% 1% 2% 3% 4% 5% 6% Oct 2014 2015 2016 2016_withCurtailedMW

MAE

2016’s October MAE becomes more comparable to previous years when the Curtailed Solar MW are added back into Actuals.

Slide 90

slide-91
SLIDE 91

Load Forecast Adjustments

Gabe Murtaugh

  • Sr. Market Monitoring Analyst,

Department of Market Monitoring

Slide 91

slide-92
SLIDE 92

Growth in EIM transfer capacity significantly increases market competiveness.

Slide 92

Puget

300 MW 300 MW

PacifiCorp West

126 MW 85 MW

CAISO

899 MW 872 MW

NV Energy

924 MW 1,874 MW

APS PacifiCorp East

468 MW 710 MW 0 MW 293 MW 216 MW 321 MW

Total average transfer capacity (May-Oct 2016)

slide-93
SLIDE 93

Congestion into EIM areas is very infrequent.

Puget

1%

(187 MW)

1%

(205 MW)

PacifiCorp West

20%

(27 MW)

2%

(221 MW)

CAISO

2% MW

(790 MW)

.2%

(611 MW)

NV Energy

0% .3% (143 MW)

APS

PacifiCorp East

.3%

(156 MW)

7%

(463 MW)

4% (105 MW) 7%

(150 MW)

1%

(119 MW)

Frequency of congestion in 15-minute market (May-Oct 2016)*

* Average transfer MW during congested intervals in parentheses.

23% (0 MW)

Slide 7

slide-94
SLIDE 94

EIM areas separated by congestion from the ISO

  • nly 1-3 percent of intervals.

Slide 94

slide-95
SLIDE 95

Settlement prices in Arizona largely reflected prices in the ISO during October.

Slide 95 $0 $10 $20 $30 $40 $50 $60 $70 $80 $90 $100 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Average hourly price ($/MWh) Arizona Public Service settlement price Southern California Edison settlement price Bilateral price benchmark

slide-96
SLIDE 96

Settlements prices in Puget Sound were lower than the ISO and reflected PacifiCorp West prices.

Slide 96 $0 $10 $20 $30 $40 $50 $60 $70 $80 $90 $100 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Average hourly price ($/MWh) Pacific Gas and Electric settlement price Puget Sound Energy settlement price PacifiCorp West settlement price Bilateral price benchmark

slide-97
SLIDE 97

Positive load adjustments were more frequent in NV Energy and the ISO, while negative load adjustments were more frequent in the PacifiCorp areas.

Slide 97

Percent of intervals Average MW Percent of total load Percent of intervals Average MW Percent of total load California ISO 15-minute market 44% 471 1.4% 14%

  • 274

1.1% 169 5-minute market 56% 438 1.4% 27%

  • 300

1.1% 162 PacifiCorp East 15-minute market 5% 91 1.6% 42%

  • 101

1.9%

  • 38

5-minute market 9% 88 1.5% 63%

  • 125

2.4%

  • 71

PacifiCorp West 15-minute market 3% 38 1.5% 43%

  • 49

2.2%

  • 20

5-minute market 4% 42 1.7% 49%

  • 58

2.6%

  • 27

NV Energy 15-minute market 48% 132 2.3% 1%

  • 171

3.6% 62 5-minute market 44% 95 1.7% 11%

  • 83

1.7% 32 Positive load adjustments Negative load adjustments Average hourly bias MW

slide-98
SLIDE 98

Load adjustments in NV Energy tended to be greatest in the late afternoon, while PacifiCorp East adjusted by the greatest quantity in the morning.

Slide 98

  • 150
  • 100
  • 50

50 100 150 200 250 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 MW 15-minute market (PacifiCorp East) 5-minute market (PacifiCorp East) 15-minute market (PacifiCorp West) 5-minute market (PacifiCorp West) 15-minute market (NV Energy) 5-minute market (NV Energy)

slide-99
SLIDE 99

Policy Update

Brad Cooper Manager, Market Design and Regulatory Policy

Slide 99

slide-100
SLIDE 100

Ongoing policy stakeholder initiatives

  • Contingency modeling enhancements

– Technical analysis results targeted Dec – Stakeholder call on technical analysis targeted Dec – May 2017 Board Meeting

  • Generator contingency and remedial action scheme

modeling – Revised straw proposal targeted Jan 2017 – Jul 2017 Board Meeting

  • Stepped transmission constraints

– New schedule being developed – Board Meeting TBD

Slide 100

slide-101
SLIDE 101

Ongoing policy stakeholder initiatives (continued)

  • Flexible resource adequacy criteria and must-offer
  • bligation – phase 2

– Stakeholder call on supplemental issue paper Dec 9 – Revised straw proposal Feb 2017 – Board Meeting TBD

  • Bid cost recovery enhancements

– Draft final proposal Dec 2016 – Q1 2017 Board meeting – Projected Fall 2018 implementation

  • Self schedules BCR allocation

– Added to the bid cost recovery enhancements initiative

Slide 101

slide-102
SLIDE 102
  • Commitment Costs and Default Energy Bid Enhancements

– February 2017 Straw proposal – July 2017 Board Meeting – 2018 Implementation

  • Metering rules enhancements

– Dec 2016 Board Meeting

  • Energy storage and distributed energy resources (ESDER)

Phase 2 – Q1 2017 Board Meeting

Slide 102

Ongoing policy stakeholder initiatives (continued)

slide-103
SLIDE 103

Ongoing policy stakeholder initiatives (continued)

  • Aliso Canyon - Phase 2

– FERC Order accepting filing Nov 28 – Jan 2017 Implementation

  • Stakeholder initiatives catalog

– Final 2017 policy initiatives roadmap Dec 15 – Stakeholder call Dec 22 – Feb 2017 EIM Governing Body and Board Meeting

  • Frequency response – phase 2

– Issue paper targeted Dec 2016 – Schedule TBD

Slide 103

slide-104
SLIDE 104

Ongoing policy stakeholder initiatives (continued)

  • Regional integration and EIM greenhouse gas compliance

– Stakeholder meeting on straw proposal Dec 1 – Draft final proposal Jan 5 – Board Meeting TBD

  • Transmission access charge options

– Framework published Dec 6 – Stakeholder meeting Dec 13 – No planned Board action at this time

  • Regional resource adequacy

– Framework published Dec 1 – Stakeholder meeting Dec 8 – No planned Board action at this time

Slide 104

slide-105
SLIDE 105

Policy stakeholder initiatives coming soon

  • Planned to start in Q1 2017

– Resource adequacy enhancements – Economic and maintenance outages

Slide 105

slide-106
SLIDE 106

Release Plan Update Janet Morris Director, Program Office

Slide 106

slide-107
SLIDE 107

The ISO offers comprehensive training programs

Slide 107

Training calendar - http://www.caiso.com/participate/Pages/Training/default.aspx Contact us - markettraining@caiso.com Date Training January 11 Welcome to the ISO (webinar) February 7 Settlements 101 (Folsom) February 8 Settlements 201 (Folsom)

slide-108
SLIDE 108

Release Plan 2016

Slide 108

Implementations by end of 2016

  • Demand Response Registration Enhancements
  • ADS Client Replacement (Mandatory)
  • Acceptable Use Policy - CMRI
slide-109
SLIDE 109

Release Plan 2017

Slide 109

Independent 2017

  • RTD Local Market Power Mitigation (LMPM) Enhancements
  • CRR Clawback Modifications
  • MRI-S ACL Groups+ CPG Enhancements (formerly OMAR Replacement)
  • PIRP System Decommissioning
  • Reactive Power Requirements and Financial Compensation – no system changes
  • RIMS Functional Enhancements
  • Metering Rules Enhancements

Fall 2017 (tentative, to be confirmed)

  • Bidding Rules Enhancements – Part B
  • Reliability Services Initiative Phase 1B
  • Reliability Services Initiative Part 2
  • Commitment Cost Enhancement Phase 3
  • EIM 2017 Enhancements
  • EIM Portland General Electric (PGE)
slide-110
SLIDE 110

Release Plan – 2018 and subject to further planning

Slide 110

Spring 2018

  • EIM 2018 Idaho Power Company

Fall 2018 – tentative, subject to impact assessment

  • Stepped Transmission Constraints
  • Bid Cost Recovery Enhancements
  • Generation Contingency and Remedial Action Scheme
  • Flexible Resource Adequacy Criteria and Must-offer Obligation Phase 2
  • ESDER Phase 2
  • Regional Resource Adequacy
  • Transmission Access Charge Options
  • ADS User Interface Replacement

Subject to further release planning:

  • Additional Data Transparency Enhancements (OASIS API changes) – work starting after Fall

2016 release; ISO will make it available for market participants to adopt as they need.

  • Contingency Modeling Enhancements
slide-111
SLIDE 111

2016 – Demand Response Registration Enhancements

Project Info Details/Date Application Software Changes Enhance Demand Response Registration functionality and processes Develop new registration user interface for DRRS Develop new APIs for support of enhanced registration processes BPM Changes Metering Business Process Changes Automation of internal registration-related processes

Slide 111

Milestone Type Milestone Name Dates Status

Board Approval Board Approval N/A BPMs Publish Final Business Practice Manuals (Metering) Aug 29, 2016

Post Draft BPM changes (Metering) Aug 04, 2016

External BRS External BRS - Enabling Demand Response Phase 2 - Registration Jun 04, 2015

Tariff Tariff N/A Config Guides Config Guide N/A Tech Spec Tech Specs - DRRS Phase 2 - Registration Sep 17, 2015

Market Sim Market Sim Window Sep 19, 2016 - Nov 18, 2016

Production Activation Post-Mrkt Consol - DRRS Phase 2 - Reg Nov 30, 2016

slide-112
SLIDE 112

2016– ADS Client Replacement (Mandatory)

Project Info Details/Date Application Software Changes Scope includes updates to work with TLS version 1.0. After January 6, 2017, all prior supported ADS client versions (which includes 5.2.8.0 and 5.2.4.0) will be decommissioned and inaccessible.

Slide 112

ADS Client certified for Windows 7 and 10

Milestone Type Milestone Name Dates Status

Board Approval Board Approval N/A BPMs BPMs N/A External BRS External BRS N/A Tariff Tariff N/A Config Guides Config Guide N/A Tech Spec Tech Spec N/A Market Sim Market Sim Window Oct 12, 2016 - Jan 06, 2017 Production Activation ADS TLS Risk Remediation Jan 06, 2017

slide-113
SLIDE 113

2016 – Acceptable Use Policy – CMRI

Project Info Details/Date Application Software Changes Scope includes enforcement of Acceptable Use Policy for CMRI services to support the full implementation of 1 call per service per identity (as designated by certificate) every 5 seconds. An error code of 429 will be returned for any violation instance of the use policy.

Slide 113

Milestone Type Milestone Name Dates Status

Board Approval Board Approval N/A BPMs BPMs N/A External BRS External BRS N/A Tariff Tariff N/A Config Guides Config Guide N/A Tech Spec Tech Spec N/A Market Sim Market Sim Window Aug 23, 2016 - Sep 23, 2016

Production Activation Acceptable Use Policy - CMRI Jan 06, 2017

slide-114
SLIDE 114

Slide 114

2016 CMRI URL Standardization

Service Version # Existing URL https://wsstas.caiso.com:4445/sst/runtime.asvc https://wsstas.ecn.wepex.net:4445/sst/runtime.as vc Standardized URL https://ws.caiso.com/sst/cmri https://ws.ecn.wepex.net/sst/cmri MarketAwards v2 Decommission on 12/01/2016 None exists v3 Decommission on 12/01/2016 Supported v4 None exists Supported MarketSchedules v1 Decommission on 12/01/2016 None exists v2 Decommission on 12/01/2016 Supported v3 None exists Supported SchedulePrices v2 Decommission on 12/01/2016 None exists v3 Decommission on 12/01/2016 Supported v4 None exists Supported ExpectedEnergy AllocationDetails v1 Decommission on 12/01/2016 None exists v2 Decommission on 12/01/2016 Supported v3 None exists Supported GreenHouseGas CapData v1 None exists Supported EIMInterchange ScheduleData v1 ResourceMovementP

  • int

v1 ResourceLevel Movement v1 EIRForecast v1 ElectricityPriceIndex v1 All other pre Fall 2016 existing services existing Decommission on 12/01/2016 Supported

slide-115
SLIDE 115

Slide 115

2016-2017 Projects - Major Milestones Summary

Project Market Simulation Deployment/Activation Decommissioning

Demand Response Registration Enhancements Completed Completed N/A ADS Client Replacement (Mandatory) ADS Client ver 6.0.0.0 made available for testing in MAP Stage on 10/12/2016 ADS Client production-level version 6.0.x available as of 10/28/2016 Availability of production level ADS version started a grace period of approx 2 months for market participants to transition to the new version After January 6, 2017, all prior supported ADS client versions (which includes 5.2.8.0 and 5.2.4.0) will be decommissioned and inaccessible. Acceptable Use Policy - CMRI Completed Jan 6, 2017 N/A ACL Groups (formerly OMAR Replacement and PIRP Decommissioning) TBD TBD ISO decommissions PIRP based upon a two-month buffer period between ACL group functionality being active in Production. MRI-S Customer Partnership Group identified enhancements (formerly OMAR Replacement) TBD TBD OMAR will be decommissioned after a four month grace period starting when MRI-S enhancements deploy to MAP Stage (market simulation).

slide-116
SLIDE 116

2017 - Real Time Dispatch Local Market Power Mitigation

Project Info

Details/Date

Application Software Changes

  • CMRI – Display mitigated bids from RTD process
  • OASIS (Open Access Sametime Information System): Display RTD

reports for Market Clearing, the Pnode clearing, similar to current RTPD reports

  • RTM (Real Time Market)
  • RTPD: Perform the LMPM run as an integral part of the binding

interval RTPD run

  • RTD: Proposed mitigation in RTD run would work the same way

as the current RTPD run BPM Changes

  • Energy Imbalance Market (EIM): under the proposed RTD method,

bids are not necessarily mitigated for the whole hour

  • RTD MPM will work the same way as the current RTPD MPM

Business Process Changes

  • Manage Markets & Grid
  • ATF – System Operations: Add MPM Application to Real Time and

annotate inputs and outputs

  • ATF – System Operations, Real Time: Add MPM to diagram with inputs

and outputs

  • Level II – Manage Real Time Operations – maintain balancing area

Slide 116

slide-117
SLIDE 117

2017 - Real Time Dispatch Local Market Power Mitigation (cont.)

Slide 117 Project CMRI OASIS ADS RTD LMPM Update (add RTD results): MPMResults v3 Update (add RTD results)-

  • PRC_MPM_RTM_LMP
  • PRC_MPM_RTM_NOMOGRAM
  • PRC_MPM_RTM_NOMOGRAM_CMP
  • PRC_MPM_RTM_FLOWGATE
  • PRC_MPM_CNSTR_CMP
  • PRC_MPM_RTM_REF_BUS
  • ENE_MPM

N/A

Milestone Type Milestone Name Dates Status

Board Approval Board of Governors (BOG) approval Mar 24, 2016

BPMs Posted Market Operations BPM PRR 945 Nov 04, 2016

Post draft EIM BPM Dec 29, 2016 External BRS Post External BRS Apr 05, 2016

Tariff Received FERC approval Nov 08, 2016

Config Guides Configuration Guide N/A Tech Spec Publish Technical Specification - OASIS Apr 08, 2016

Publish Technical Specification - CMRI Apr 14, 2016

Market Sim Market Sim Window Jan 17, 2017 - Feb 03, 2017 Production Activation RTD - Local Market Power Mitigation Enhancement Mar 01, 2017

slide-118
SLIDE 118

2017 – Congestion Revenue Rights (CRR) Clawback Modifications

Project Info

Details/Date

Application Software Changes MQS/CRR Clawback: If import bid <= day-ahead price, then the import is not considered a virtual award. If export bid >= day-ahead price, then the export is not considered a virtual award. If an import/export bid/self-schedule in real-time market is less than the day-ahead schedule, then the difference shall be still subject to CRR Clawback rule. CRR Clawback rule should include convergence bids cleared on trading hubs and load aggregation points in the flow impact used to determine if the 10% threshold is reached. Inform Market Participants of CRR annual allocation/auction for 2017. BPM Changes Market Operations Appendix F Business Process Changes TBD

Slide 118

Milestone Type Milestone Name Dates Status

Board Approval Board of Governors Approval Jun 28, 2016

BPMs Publish Final Business Practice Manuals Jan 30, 2017 External BRS Post External BRS Nov 29, 2016

Tariff File Tariff Jan 20, 2017 Receive FERC order Mar 21, 2017 Production Activation CRR Clawback Modification Apr 01, 2017

slide-119
SLIDE 119

2017 - MRI-S ACL Groups+ CPG Enhancements

Project Info Details/Date Application Software Changes

The MRI-S metering (MRI-S) application cannot currently support ACL (Access Control List) groups functionality for defining a subset of resources belonging to an SCID. Enhancements to the Application Identity Management (AIM) application will enable the use of ACL groups for SCID-level read-only access for MRI-S. Conducted a Customer Partnership Group meeting on October 20 and reviewed proposed solutions.

BPM Changes

None

Business Process Changes

Potential Level-II business process changes under –

  • Manage Market & Reliability Data & Modeling
  • Manage Operations Support & Settlements

Slide 119

Milestone Type Milestone Name Dates Status Board Approval Board Approval N/A BPMs Metering BPM Changes N/A External BRS Post External BRS Nov 14, 2016  Tariff Pre-Tariff Filing QRB N/A Tech Spec Publish Tech Specs Nov 02, 2016  Market Simulation Phase 1 - ACL Groups TBD Phase 2 - MRI-S Metering Enhancements TBD Production Activation Phase 1 - ACL Groups TBD Phase 2 - MRI-S Metering Enhancements TBD

slide-120
SLIDE 120

MRI-S ACL Groups + CPG Enhancements

Slide 120

* ACL group creation to filter for a read only role at the resource level is not currently available

# System Summary Status Estimated Fix Date 1 MRI-S CIDI 183777, 183993 - MRI-S for Metering Limitation of 100,000 records. Under review See previous slide 2 MRI-S Option to choose UOM is missing on the UI 3 MRI-S CIDI 184018 - Time zone is missing on the UI 4 MRI-S CIDI 183777, 183993 - Modification to AUP policy on data retrieval to include querying by last updated time 5 MRI-S Option to request for data in various time interval in UI 6 MRI-S Ability to view log files within the same organization 7 MRI-S Ability to provide SC ID in the data retrieve request MRI-S *ACL Group – filter read-only at the resource level In process See previous slide

slide-121
SLIDE 121

2017 – PIRP Decommissioning

Project Info

Details/Date

Application Software Changes: PIRP/CMRI

  • Forecast Data Reporting (resource-level) that was performed in PIRP will be done in
  • CMRI. Rolling Hour Ahead, Locked Hour Ahead, and Rolling Day-Ahead forecasts.
  • PIRP Decommissioning to occur in 2017
  • CMRI to receive the Electricity Price Index for each resource and publish it to the

Market Participants.

  • 60 Day PIRP / CMRI parallel production to start when AIM/ACL becomes available.

BPM Changes CMRI Technical Specification; New APIs will be described. Data Transparency

  • Independent changes, won’t

impact existing services

  • Will be made available in

Production and cutover schedule is discretionary Atlas Reference:

  • 1. Price Correction Messages (ATL_PRC_CORR_MSG)
  • 2. Scheduling Point Definition (ATL_SP)
  • 3. BAA and Tie Definition (ATL_BAA_TIE)
  • 4. Scheduling Point and Tie Definition (ATL_SP_TIE)
  • 5. Intertie Constraint and Scheduling Point Mapping (ATL_ITC_SP)
  • 6. Intertie Scheduling Limit and Tie Mapping (ATL_ISL_TIE)

Energy

  • EIM Transfer Limits By Tie (ENE_EIM_TRANSFER_LIMITS_TIE)
  • Wind and Solar Summary (ENE_WIND_SOLAR_SUMMARY)

Prices

  • MPM Default Competitive Path Assessment List (PRC_MPM_DEFAULT_CMP)

Business Process Changes MPs will receive the VER reports from CMRI rather than PIRP.

Slide 121

slide-122
SLIDE 122

2017 – PIRP Decommissioning

Slide 122

Milestone Type Milestone Name Dates Status Board Approval Board Approval N/A BPMs Publish Draft Business Practice Manuals (Market Instruments; PRR 936) Sep 06, 2016  External BRS External Business Requirements Jun 29, 2015  Tariff Tariff Filing Activities N/A Config Guides Settlements Configuration N/A Tech Spec Publish Technical Specifications (CMRI: PIRP Decommissioning) Feb 05, 2016  Publish Technical Specifications (CMRI; Wind and Solar) Apr 15, 2016  Market Sim CMRI Reports; VER Forecast & EPI (Fall 2016 Release) Aug 23 - Sep 23, 2016  PIRP Decommissioning TBD Production Activation CMRI Reports; VER Forecast & EPI (Fall 2016 Release) Oct 01, 2016  AIM / ACL Production Deployment TBD OASIS API Enhancements; 9 Reports TBD PIRP Decommissioning TBD

slide-123
SLIDE 123

2017 – Reactive Power Requirements and Financial Compensation

Project Info

Details/Date

Application Software Changes None BPM Changes Generator Interconnection and Deliverability Allocation Procedures

  • Reactive power delivery interconnection condition for asynchronous resources.

Generator Interconnection Procedures

  • Reactive power delivery interconnection condition for asynchronous resources.

Generator Management

  • Generators’ AVR Requirements.

Business Process Changes Develop Infrastructure (DI) (80001)

  • Level II - Manage Generator Interconnection Process (GIP) (Logical Group):

Slide 123

Milestone Type Milestone Name Dates Status

BPMs Draft BPM changes TBD Post Draft BPM changes TBD Publish Final Business Practice Manuals TBD Tariff File Tariff 12/5/2016

Tariff Receive FERC order 2/1/2017 Production Activation Reactive Power and Financial Compensation activation 4/1/2017

slide-124
SLIDE 124

2016 – RIMS Functional Enhancements

Project Info Details/Date Status

Application Software Changes Functional enhancements resulting from the Customer Partnership Group CPG. More details to be provided in the future. BPM Changes Generator Interconnection and Deliverability Allocation Procedures Generator Interconnection Procedures Managing Full Network Model Metering Generator Management Transmission Planning Process Customer Partnership Group 10/16/15 Application and Study Webinar 3/31/16

Slide 124

Milestone Type Milestone Name Dates Status

Board Approval Board approval not required N/A BPMs Generator Interconnection and Delivery Allocation Apr 29, 2016

External BRS External BRS not Required N/A Tariff No Tariff Required N/A Config Guides Configuration Guides not required N/A Tech Spec No Tech Specifications Required N/A Production Activation RIMS5 App & Study Mar 21, 2016

RIMS5 Queue Management, Transmission and Generation TBD

slide-125
SLIDE 125

2017 – Metering Rules Enhancements

Project Info Details/Date Application Software Changes N/A BPM Changes Metering

  • EIM BPM will be updated to explain Metering data reporting access

based on transitions from ISOME to SCME (shall transition to submission of SQMD meter data to Metering Data submission portal) or SCME to ISOME (shall be able to review historical meter data in MRI-S when resource was SCME). Definitions & Acronyms BPM Changes

  • New Tariff and Business Process/System acronyms.

Business Process Changes

  • Manage Transmission & Resource Implementation
  • Manage Market & Reliability Data & Modeling (MMR) (80004)
  • ISO Meter Certification (MMR LII)
  • Metering Systems Access (Production) (MMR LII)
  • Metering System Configuration for Market Resources (MMR

LII)

  • Station Power Implementation (MMR LIII)
  • Application Flow - Billing & Settlements
  • Analyze Missing Measurement Report (MOS LIII)
  • Manage Market Billing & Settlements (MOS LII)
  • Manage Market Quality System (MOS LII)
  • Manage Rules of Conduct (MOS LII)
  • Meter Data Acquisition & Processing (MOS LII)
  • SCME Self Audit (MOS LII)

Slide 125

slide-126
SLIDE 126

2017 – Metering Rules Enhancements

Slide 126

Milestone Type Milestone Name Dates Status

Board Approval Obtain Board of Governors Approval Dec 14, 2016 BPMs Metering BPM TBD Energy Imbalance Market BPM TBD Publish Final Business Practice Manuals TBD External BRS External Business Requirements N/A Tariff File Tariff N/A Receive FERC order N/A Config Guides Settlements N/A Tech Spec Tech Specs N/A Market Sim Market Sim Window N/A Production Activation Metering Rules Enhancements Apr 01, 2017

slide-127
SLIDE 127

Fall 2017 - Bidding Rules Enhancements – Part B

Slide 127

Project Info Details/Date Application Software Changes

  • MasterFile:
  • Provide ability to submit requests for new fuel regions (Policy Section 8.1.1.3)
  • Include resource-specific start-up electricity costs in proxy costs based on wholesale

projected electricity price, unless resource verifies costs incurred are retail rates (RDT change)

  • Allow ability to submit a weighting when using a more than one fuel region.
  • Automation of the Aliso Canyon process for creating NEW Fuel Regions
  • OASIS:
  • Publish fuel regions (public information)

Business Process Change

  • Manage Transmission & Resource Implementation
  • Manage Entity & Resource Maintenance Updates
  • Manage Full Network Model Maintenance
  • Manage Market Quality System (MQS)

BPMs

Market Instruments, Market Operations, Reliability Requirements Milestone Type Milestone Name Dates Status

Board Approval BOG Approval Mar 25, 2016

BPMs Draft BPM changes TBD Post Draft BPM changes TBD Publish Final Business Practice Manuals TBD External BRS Post External BRS Dec 15, 2016 Tariff File Tariff TBD Receive FERC order TBD Config Guides Prepare Draft Configuration Guides Apr 01, 2017 Tech Spec Create ISO Interface Spec (Tech spec) Apr 01, 2017 Market Sim Market Sim Window Jul 05, 2017 - Jul 31, 2017 Production Activation Bidding Rules Part B Oct 01, 2017

slide-128
SLIDE 128

Fall 2017 - Reliability Services Initiative Phase 1B

Project Info Details/Date Status

Application Software Changes

Developments under consideration include: Scope:

  • Default flexible qualifying capacity provisions for phase 2 consideration (we might need data collection

performed in order to support RSI Phase 2

  • Redesign of Replacement Rule for System RA and Monthly RA Process
  • RA Process and Outage Rules for implementation for 2017 RA year
  • Scope not delivered in RSI Phase 1A (Grandfathered Contracts, RAAM Decommissioning – SCP & CPM

screens from RAAM to CIRA, Acquired Contracts, OASIS reporting, web services related to APIs for CSP

  • ffers, APIs for Generic/Flex Substitutions, and Release of Generic/Flex Subs – UI & API)

Impacted Systems:

  • CIRA
  • OASIS
  • Integration (B2B)
  • Settlements
  • Decommission RAAM

Business Process Changes

Manage Market & Reliability Data & Modeling Slide 128

Milestone Type Milestone Name Dates Status

Board Approval Board Approval May 12, 2015

BPMs Draft BPM Changes - Outage Mgmt, Reliability Reqmts TBD Post Draft BPM changes TBD Publish Final Business Practice Manuals TBD External BRS Post External BRS Dec 16, 2016 Tariff File Tariff TBD Receive FERC order TBD Config Guides Config Guide Apr 01, 2017 Tech Spec Create ISO Interface Spec (Tech spec) Apr 01, 2017 Market Sim Market Sim Window Jul 05, 2017 - Jul 31, 2017 Production Activation Reliability Services Initiative Phase 1B Oct 01, 2017

slide-129
SLIDE 129

Project Info Details/Date

Application Software Changes Scope: 1. Clarify use-limited registration process and documentation to determine opportunity costs 2. Each submission evaluated on a case-by-case basis to determine if the ISO can calculate opportunity costs

  • ISO calculated; Modeled limitation
  • Market Participant calculated; Negotiated limitation

3. Enhanced definition of “use-limited” in response to FERC’s rejection of the proposed definition in Cost Commitment Enhancements Phase 2 4. Change Nature of Work attributes (Outage cards)

  • 1. Modify use-limited reached for RAAIM Treatment
  • 2. Add new demand response nature of work attribute for RDRR and PDR

5. Market Characteristics

  • 1. Maximum Daily Starts
  • 2. Maximum MSG transitions
  • 3. Ramp rates

Impacted Systems:

  • 1. CIRA
  • 2. CMRI
  • 3. IFM/RTN
  • 4. SIBR
  • 5. MasterFile
  • 6. OASIS
  • 7. OMS
  • 8. Settlements

BPM Changes Market Instruments, Outage Management, Reliability Requirement, Market Operations, Settlements & Billing Business Process Changes Level II – Manage Reliability Requirements Level II – Manage Day Ahead Market

Slide 129

Fall 2017 - Commitment Cost Enhancements Phase 3

slide-130
SLIDE 130

Slide 130

Fall 2017 - Commitment Cost Enhancements Phase 3 (cont.)

Milestone Type Milestone Name Dates Status

Board Approval Board of Governors (BOG) Approval Mar 25, 2016

BPMs Draft BPM changes TBD Post Draft BPM changes TBD Publish Final Business Practice Manuals TBD External BRS Post External BRS Dec 30, 2016 Tariff File Tariff TBD Receive FERC order TBD Config Guides Config Guide Apr 01, 2017 Tech Spec Create ISO Interface Spec (Tech spec) Apr 01, 2017 Market Sim Market Sim Window Jul 05, 2017 - Jul 31, 2017 Production Activation Commitment Costs Phase 3 Oct 01, 2017

slide-131
SLIDE 131

Fall 2017 – EIM Enhancements 2017

Project Info

Details/Date

Application Software Changes ​Addresses the following enhancements identified by policy, operations, technology, business and market participants. The following requirements are being defined:

  • EIM Entity access reports
  • BAAOP provisioning in AIM
  • EIM Data report enhancements to support EIM Entity settlements
  • Joint Owned Units modeling
  • Allow MSG resource to send actual configuration in telemetry for RTM
  • Comprehensive model for startup and transition energy in DAM, RTM,

RTBS, MQS BPM Changes TBD Business Process Changes TBD

Slide 131

slide-132
SLIDE 132

Slide 132

Fall 2017 – EIM Enhancements 2017 (cont.)

Milestone Type Milestone Name Dates Status

Board Approval Obtain Board of Governors Approval N/A BPMs Draft BPM changes TBD Post Draft BPM changes TBD Publish Final Business Practice Manuals TBD External BRS External BRS complete Dec 30, 2016 Tariff File Tariff TBD Receive FERC order TBD Config Guides Design review - BPM and Tariff SMEs Apr 01, 2017 Tech Spec Publish Technical Specifications Apr 06, 2017 Market Sim Market Sim Window Jul 05, 2017 - Jul 31, 2017 Production Activation EIM Enhancements 2017 Oct 01, 2017

slide-133
SLIDE 133

Fall 2017 – EIM Portland General Electric

Project Info Details/Date Application Software Changes Implementation of Portland General Electric as an EIM Entity. BPM Changes EIM BPM will be updated to reflect new modeling scenarios identified during PGE implementation and feedback from PGE. Market Simulation ISO promoted market network model including PGE area to non- production system and allow PGE exchange data in advance of Market Simulation. Parallel Operations August 1 – September 30, 2017

Slide 133

Milestone Type Milestone Name Dates Status

Board Approval Board approval not required N/A BPMs BPMs N/A External BRS No external BRS N/A Tariff Tariff filing at FERC N/A Config Guides Settlements N/A Tech Spec Tech Specs N/A Market Simulation Market Sim Environment Window Jun 29, 2017 – Jul 31, 2017 Production Activation EIM - Portland General Electric Oct 01, 2017

slide-134
SLIDE 134

Annual Functional Release Lifecycle

Slide 134

The ISO has published the Annual Functional Release Lifecycle draft on the Release Planning page

  • http://www.caiso.com/Documents/AnnualFunctionalReleaseLifecycle.pdf

This document describes the planning through execution phases of the ISO annual functional release lifecycle process including

  • Introduction
  • Background
  • Scope
  • Annual Functional Release Lifecycle
  • Exceptions
  • Contingency Planning
  • External Deliverables
  • Process Interfaces
  • Stakeholder Implementation Interactions

The ISO encourages Market Participants to review the document and provide any feedback.

slide-135
SLIDE 135

Market Performance and Planning Forum 2017 Schedule – Mark Your Calendars

  • January 18
  • March 14
  • May 16
  • July 18
  • September 19
  • November 14

Questions or meeting topic suggestions: Submit through CIDI - select the “Market Performance and Planning Forum” category

Slide 135