market performance and planning forum
play

Market Performance and Planning Forum March 17, 2016 Market - PowerPoint PPT Presentation

Market Performance and Planning Forum March 17, 2016 Market Performance and Planning Forum Agenda March 17, 2016 10:00- 10:05 Introduction, Agenda Kristina Osborne 10:05 10:20 Sub LAP Area Definition Updates Jim Price 10:20 11:30


  1. Almost 80 percent of the self-scheduled capacity in real time in 2015 was from imports, nuclear, solar and wind generation. 120% Average percent of MW without economic bid 100% Geothermal Natural gas 80% Hydro Other 60% Wind 40% Solar Nuclear 20% Imports 0% 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Hour Page 51

  2. When renewable generation bid into the ISO real-time market, almost all of the bids were at negative prices. Natural gas Hydro Geothermal Wind Solar Other 3,500 3,000 2,500 Average hourly MW 2,000 1,500 1,000 500 0 -500 -1,000 below -$50 -$50 to -$25 -$25 to $0 $0 to $25 $25 to $50 above $50 Page 52

  3. About 1.2 percent of solar generation and 0.2 percent of wind generation was curtailed in 2015. Almost all of these curtailments were economically based. Solar Wind Economic Non-economic Economic Non-economic Month downward dispatch curtailment Total curtailment downward dispatch curtailment Total curtailment Jan 1.1% 0.0% 1.1% 0.1% 0.0% 0.1% Feb 1.5% 0.0% 1.5% 0.3% 0.0% 0.3% Mar 2.0% 0.1% 2.1% 0.3% 0.1% 0.3% Apr 2.0% 0.1% 2.1% 0.4% 0.1% 0.5% May 3.2% 0.2% 3.4% 0.2% 0.1% 0.3% Jun 0.8% 0.0% 0.8% 0.1% 0.1% 0.2% Jul 0.4% 0.0% 0.5% 0.2% 0.0% 0.2% Aug 0.6% 0.1% 0.6% 0.0% 0.0% 0.1% Sept 0.3% 0.0% 0.3% 0.1% 0.0% 0.1% Oct 0.4% 0.0% 0.4% 0.0% 0.0% 0.0% Nov 1.2% 0.0% 1.3% 0.2% 0.0% 0.2% Dec 1.1% 0.1% 1.2% 0.1% 0.1% 0.1% Page 53

  4. Solar generation complied with decremental dispatch signals 94 percent of the time in 2015. 50 100% 40 80% Noncomplied decremental dispatch instruction Percent GWh Complied Generation (GWh) Complied decremental dispatch instruction 30 60% Complied percent 20 40% 10 20% 0 0% Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Page 54

  5. Wind generation complied with decremental dispatch signals only 38 percent of the time in 2015. 5 100% Noncomplied decremental dispatch instruction Complied decremental dispatch instruction Complied percent 4 80% Percent GWh Complied Generation (GWh) 3 60% 2 40% 1 20% 0 0% Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Page 55

  6. Release Plan Update Janet Morris Director, Program Office Page 56

  7. Release Plan 2016 Early release 2016 • Capacity Procurement Mechanism Replacement • Reliability Services Initiative • Commitment Cost Enhancements Phase 2 (remainder) • Post Implementation OMS Enhancements 2016 • Application Identity Management (AIM) Enhancements • Expanding Metering and Telemetry Options Phase 2 • Demand Response Registration Enhancements • RIMS Functional Enhancements • Year 1 Enhancements 2015 - Available Balancing Capacity • Bidding Rules Enhancements – Part A Fall 2016 • BAL-003 Compliance • Flexible Ramping Product • BCR modifications and VER settlement • RTD Local Market Power Mitigation (LMPM) Enhancements • Bidding Rules Enhancements – Part B • Acceptable Use Policy - CMRI • OMAR Replacement • PIRP System Application Decommissioning • Post Implementation OMS Enhancement • Energy Imbalance Market (EIM) Year 1 Enhancements Phase 2 • Energy Imbalance Market (EIM) 2016 Arizona Public Service (APS) • Energy Imbalance Market (EIM) 2016 Puget Sound Energy (PSE) Subject to further release planning : • Reliability Services Initiative Phase 1B • Commitment Cost Enhancement Phase 3 • Stepped Constraints • Energy Storage and Distributed Energy Resources (ESDER) • ADS User Interface Replacement • Reactive Power Requirements and Financial Compensation • Contingency Modeling Enhancements Page 57

  8. Early 2016 Release Market Simulation Market Simulation Dates – RSI, CPM, Commitment Costs Phase 2, and OMS Enhancements 3/15 – 4/20: Session 2 (Unstructured and Structured E2E) updated 2/16 – 4/20: OMS Enhancements (Unstructured) updated Link to Early 2016 Release Market Simulation Plan - http://www.caiso.com/Documents/MarketSimulationPlanEarly2016Release.pdf Page 58

  9. Early 2016 Settlements Release ISSUE SUMMARY BPM IMPACTED New and updated BPM Configuration guides in support of PRR# 884 (CC 6460, CC 6470, CC 6482, CC 6488, CC the Capacity Procurement Mechanism (CPM) 7891, CC 7896, CG PC MD TAC Area and CPM ) Replacement Initiative New and updated BPM Configuration guides for PRR# 885 (CC 4515, CC 4999, CC 6011, CC 6455, CC assessing resources with RA capacity in support of the 8830, CC 8831, CC 8835, CG PC IFM Net Amount, CG Phase 1 of the Reliability Services Initiative PC Metered Energy Adjustment Factor, CG PC MSS Netting, CG PC RA Availability Incentive Mechanism, CG PC RTM Net Amount, CG PC RUC Net Amount, CG PC Start-Up and Minimum Load Cost ) Terminated BPM Configuration guides in support of PRR 886: ( CC 7872, CC 7873, CC 7874, CC 7875, CC implementation of the Capacity Procurement Mechanism 7876, CC 7877, CC 7880, CC 7881, CC 7882, CC 7883, Replacement and Reliability Services Initiatives CC 7884, CC 7885, CC 7886, CC 7887, CC 8820, CC 8821, CC 8824, CC 8825, CC 8826, CC 8827, CG PC Standard Capacity Product ) Page 59

  10. Early 2016 Settlements Release Milestone Date Status Configuration Guides Posted December 8, 2015 FIRST DRAFT Configuration Output File Posted December 14, 2015 MAP Stage Deployment January 13, 2016 SECOND DRAFT Configuration Output File Posted January 14, 2016 Market Simulation: March 8 – April 7, 2016 Trade Dates to be Posted March 14 – April 14, 2016 Calendar dates of Posting Pre-Production Configuration Output File Posted April 11, 2016 Production Deployment April 25, 2016 FINAL Configuration Output File Posted April 25, 2016 Page 60

  11. Early 2016 – Capacity Procurement Mechanism Replacement (CPM) Project Info Details/Date Competitive Solicitation Process (CSP): CSP replaces the existing administrative price process for annual, monthly and intra-monthly CPM events for flexible and generic RA capacity. CSP will cover all events that allow the ISO to procure additional capacity. CIRA: − Bid Submittal system for SCs to submit capacity bids (not an existing bid type) − Capacity bids to implement new validation rules (not an existing bid type) − Capacity Bid submittal to be on a yearly, monthly, and intra-monthly level − LSE/LRA deficiency calculation to be performed for CSP for Generic and Flexible RA data − Existing CPM calculation to be deprecated for trade dates after the effective date of implementation. − Manage import allocation and bilateral trades of import allocation Application Software Changes Settlements: Settlements will need new CPM formulas that will result in charge code impacts. Reporting: If an annual or monthly CPM occurs greater than two times (over a rolling 24 month period) or more than 50% of the LSE’s RA requirement is CPMed, a report must be given to Market Participants. OASIS: − Publish all finalized offers into the competitive solicitation process on a rolling five-quarter delay. (Deferred) − Solicitation for soft offer cap. Timeline for submittal needs to be defined. − Submittal process for annual/monthly CPM bid submittal Business Process Changes − New business process for amount of capacity being relied on (non-RA from partial RA) − New process for Competitive Solicitation Process (annual/month/intra-monthly) Page 61

  12. Early 2016 – Capacity Procurement Mechanism Replacement (cont.) Milestone Details/Date Status Reliability Requirements – PRR issued 11/4/15 Market Instruments – issue PRR 1/8/16 BPM Changes - Billing & Settlements – PRR issued 1/11/16 − Solicitation for soft offer cap. Timeline for submittal needs to be defined. − Submittal process for annual/monthly CPM bid submittal Business Process Changes − New business process for amount of capacity being relied on (non-RA from partial RA) − New process for Competitive Solicitation Process (annual/month/intra-monthly) Board Approval February 5, 2015 External BRS March 31, 2015 Tariff Filed: May 26, 2015 FERC Approved: October 1, 2015 CIRA Session 1  Fall 2016, MPs will use UIs Technical Specifications OASIS Session 2  Fall 2016 Draft Configuration Guides November 23, 2015 Session 2 October 21, 2015: Session 1 – Onsite w/Webinar, Full Day (combined w/ CPG Call) • Training Materials – posted SP & RP page on 10/19 External Training January 6, 2016: Session 2 - Onsite w/ Webinar option, Full Day • Training Materials – post 1/5 Page 62

  13. Early 2016 – Capacity Procurement Mechanism Replacement (cont.) Milestone Details/Date Status November 9 – December 17, 2015: Session 1 , Structured • Scenarios – posted on Release Planning Page on 7/30/15 • Scenarios w/timeline – posted on RP page on 10/19 • CIRA User Guide – posted on RP page on 11/24 March 14 – April 20, 2016: Session 2 • Structured Scenarios: 3/16 – 3/24; 4/5 – 4/8 (New) Market Simulation • Unstructured Scenarios: 3/14 – 3/15; 3/28 – 4/1; 4/11 - 4/20 (New) • Post Structured Scenarios • SIBR Rules, Release Notes, Specs posted – 12/11 • CIRA User Guide – 1/18 • 3-Day Onsite Market Simulation (Attendance Optional) 4/5 – 4/8 (New) 1/19/2016: Session 1 Production Activation 4/21/2016: Session 2 5/1/2016: Effective Date Page 63

  14. Early 2016 – Reliability Services Initiative (RSI) – 1A Project Info Details/Date CIRA: − Manage new NQC/EFC process request for resource types. This will impact both internal users and Market Participants − Manage Import Allocation (CPM Replacement initiative is covering this scope but is needed for this initiative) − Manage RA obligation (taking into consideration substitution capacity and replacement capacity as RA capacity) will impact RA, Settlements, market, and outage. The output of CSP will be needed − Publish RA Obligations externally − Display Comparative snapshot of DA/RT obligation (outages, energy bids, RA obligation). Display input of RAAIM calculations − Display SCP and CPM availability calculation output for historic trade dates − Creation of substitution rules for flexible resource adequacy resources − Modify existing DA/RT generic substitution rules − DA substitution timeframe shall change from 6 AM to 8 AM − Enable the release of substitute capacity for generic and flexible resources Application Software Changes − Allow imports to substitute for other imports and CAISO system resources. The RA obligation will be at a daily level − Use result of Pre-qualification analysis (the pre-qualification analysis is a manual process) for real time substitution validation − API for substitution and release functionality − Enable Generic CPM substitutions − Enable Flexible CPM substitutions − Build Submit & Retrieve APIs to support Substitutions (4 types) and release of sub capacity − Substitution will now be in CIRA − Addition of RAAIM exempt and planned outage exemption flag − Allow the outage correction process to exempt outage from RAAIM calculations up to 5 business days OMS: − Add 5 nature of work attributes and various validations − Remove SCP Exempt flag from display Page 64

  15. Early 2016 – Reliability Services Initiative (cont) -1A Project Info Details/Date Status Masterfile: − Will store Use Limit Plan. There will be a new template (ULPDT – Use Limit Plan Data Template) RAAM: − Decommission RAAM Settlements: RAAIM (RA Availability Incentive Mechanism) NEW – replaces SCP for backstop. - Current SCP will retire with implementation of RAAIM. Will assess whether generic and flexible RA resources comply with MOO and better captures use limited resource Application Software Changes availability. - New charge code changes are needed for implementation of the RA Reporting: - Report on the effectiveness of the RAAIM results (1 year after implementation) (Deferred) Other: - Modification of Use Plan with new validation rules - LSE cost allocation methodology needs to automated. - Publish list of all available prequalification combinations Page 65

  16. Early 2016 – Reliability Services Initiative (cont) – 1A Milestone Details/Date Status Reliability Requirements - issued PRR #888 on 1/12/16 BPM Changes Outage Management - issued PRR #889 on 1/12/16 Billing & Settlements - issued PRR on 1/11/16 − Process to assign NQC values to NGR/PDR/DG resources − Process for PDR/NGR/DG testing Business Process − Process for RA Availability Incentive Mechanism (RAAIM). Must retire SCP business process flows. Changes − Modify DA/Real Time Substitution Process − Process for allocating year end unallocated RA Availability Incentive Mechanism (RAAIM) funds Board Approval March 26, 2015 External BRS March 31, 2015 Tariff Filed: May 28, 2015 FERC Approved: October 1, 2015 CIRA Session 2  Fall 2016, MPs will use UIs Masterfile Session 2 • posted tech spec 9/24 on Release Planning Page • Technical Specifications posted ULDT 9/11 to RP page • posted ULR documentation/ sample templates to RP page on 12/4 OMS Session 2 • posted tech spec 12/2 Draft Configuration November 23, 2015 Session 2 Guides Page 66

  17. Early 2016 – Reliability Services Initiative (cont) – 1A Milestone Details/Date Status October 21, 2015: Session 1- Onsite w/Webinar, Full Day (combined w/ CPG Call) • Training Materials – post 10/19 • NQC Template – posted RP page on 10/19 External Training January 6, 2016: Session 2 – Onsite w/ optional Webinar, Full Day • Training Materials – post 1/5 November 9 – December 17, 2015: Session 1 • Scenarios – posted on Release Planning page on 7/30/15 • Scenarios w/timeline – posted on RP page on 10/19 • CIRA User Guide – posted 11/24 March 14 – April 20, 2016: Session 2 • Structured Scenarios: 3/16 – 3/24; 4/5 – 4/8 (New) • Unstructured Scenarios : 3/14 - 3/15; 3/28 - 4/1; 4/11 – 4/20 (New) Market Simulation • Post Structured scenarios on Release Planning page • MF/OMS Market Sim inputs: 1/19 – 3/16 (Updated) • MF UI User Guide – 1/6 • OMS User Guide – embedded in application • CIRA User Guide – 1/18 • 3-Day Onsite Market Simulation (Attendance Optional) 4/5 – 4/7 (New) 1/19/2016: Session 1 Production Activation 4/21/2016: Session 2 5/1/2016: Effective Date Page 67

  18. Early 2016 – CPM & RSI Announcements Important Announcements: – The California ISO CIRA system will be opened for unstructured testing in MAP Stage on 3/14 . – The Early 2016 Release market simulation for structured scenarios will start 3/16. – On-site Market Simulation is scheduled for 4/5 – 4/7. – The ULPDT is scheduled to go to Production in mid- March. Page 68

  19. Early 2016 – CPM & RSI Market Simulation Market Simulation, Session 2: RSI/CPM/CCE2 Information: – Session 2 Market Sim delayed • Structured scenario testing - 3/16 – 3/24, 4/5 – 4/8 • Unstructured scenarios testing – 3/14 - 3/15; 3/28 – 4/1; 4/11 – 4/20 – Structured Scenario schedule. • Week 1 - RA Substitution (1B): 3/16 – 3/18 • Week 2 - RAAIM Incentive, Penalty, Exemption (2B, 3B, 4B): 3/22 – 3/24 • Week 4 - CPM Payments & Supplemental Revenue (6B, 7B, 8B) & Onsite Market Sim: 4/5 – 4/7 – Submission of OMS outages and ULPDT in preparation of Market Simulation is as follows: • OMS Outage submission – to start “ongoing”. MPs need to submit new outages based on new start date of Market simulation. The requirement to submit outages at least 7 business days prior to the start of the outage will be reduced to 2 business days for market simulation. • ULPDT submission – to start “ongoing”. If you have already issued your template, there is no need to re-upload due to delay in go live. The requirement to upload the template at least five business days prior to the effective start date of the use limitation will be deactivated for market simulation. Page 69

  20. Early 2016 – CPM & RSI Announcements Use Limited Plan Data Template (ULPDT) Timeline: Postponed Market Notice to be posted: – The California ISO has delayed the go-live date of Use Limit Plan Data Template ( ULPDT) in the Production Master File application. Scheduling coordinators (SC) for use-limited resources are asked to wait until further notice before submitting supporting documentation via the customer inquiry dispute and information tool (CIDI). Page 70

  21. Early 2016 – CPM & RSI Onsite Market Simulation 3-Day Onsite Market Simulation, Session 2  April 5 – 7, 2016 The ISO will hold an OPTIONAL onsite market simulation for market participants in addition to the already scheduled market simulation session. Information : – Schedule for onsite market simulation for Session 2: 4/5 – 4/7 – Onsite Session will be during testing of Week 3 structured scenario testing – Mini-monthly Settlements statements are not available during the onsite market simulation, but are available for the 3-week offsite session – MPs need to bring their own laptops, because they have their certifications on them. – Please RSVP to the RR mailbox (reliabilityrequirements@caiso.com) Page 71

  22. Early 2016 – Commitment Costs Phase 2 Milestone Details/Date Status For the Early Jan 2016 release , the project will • Clarify definition, qualifications, and requirements for use-limited resources • Implementation of the use limited definition (No longer applicable) • Implement revised must-offer rules • Application Software Changes Impacted Systems: • MF • SIBR CCE2 Early 2016 release implementation will be coordinated as part of the Reliability Services Initiative (RSI) project Board Approval Yes. March 26-27, 2015 Filed: May 28, 2015 Approved in Part: September 9, 2015 Tariff (FERC rejected the proposed revisions to the definition of “use limited resources”, but approved all other tariff revisions.) Market Operations (Use Plan) – issued PRR #887 on 1/11/16 BPM Changes Business Process Changes No External Business Requirements November 24, 2015 Technical Specifications No January 6, 2016: Session 2 – Onsite w/ optional Webinar, Full Day External Training • Training Materials – post 1/5 Draft Configuration Guides No 3/16 – 3/24; 4/5 – 4/7: Session 2 (Updated) Market Simulation Deployment Target - 4/21/2016 Production Activation Effective Date – 5/1/2016 Page 72

  23. Early 2016 – Post Implementation OMS Enhancements Project Info Details/Date OMS Enhancements project will implement the following functionalities: • Transmission Outage Report Enhancements • Manage Broadcast Status Update (deferred until Fall 2016) • Manage RetrieveResourceOutage API - add Invalid and Inconsistent flags • The API will be backwards compatible. OMS will support both V1 and V2 of B2B submit and retrieve outage API. The same applies to the transmission outage API as well. • System change to validate the "ChangeThreshold" only at time of submission of a change request, and allow change request to be accepted or rejected at any time. Application Software Changes The project is also addressing the backlog of known issues. Other roadmap items (Substitutions, Additional Natures of Work, and Removal of SCP exempt flag/Inclusion of RAAIM exempt flag) will be part of the Reliability Services Initiative (RSI) project. The implementation will impact the following systems: • Outage Management System (OMS) • Market Systems (IFM/RTN) • EMS • CIRA • Settlements TBD External Training Disable external SLIC API and UI access: January 15, 2016 SLIC Decommissioning Page 73

  24. Early 2016 – OMS Enhancements (Continued) OMS Enhancements Market Sim Target Date Production Target Date Broadcast Status Updates Deferred scope Deferred scope Transmission Outage Report N/A April 20, 2016 Resource Outage API Updates (Inconsistent/Invalid flags & New Already in map stage March 23, 2016 Natures of Work – RIMS_OUTAGE, RIMS_TESTING) Note: V1 and V2 will be supported Transmission Outage API Updates (New Natures of Work - April 6, 2016 May 18, 2016 RIMS_OUTAGE, RIMS_TESTING, New PSR Type – SYNCHRONOUS_MACHINE and multiple instances of Adjusted Operational Limit per equipment) Note: V1 and V2 will be supported (CIDI 169719): Validation of change threshold only at the time of N/A March 23, 2016 submission Ability to open “Notes” boxes to full size window N/A April 20, 2016 Additional server side filtering to warning summary N/A March 23, 2016 Rules engine updates to allow for auto-approval of certain types of N/A May 18, 2016 outages Removal of search date range limitation on Outage summary N/A March 23, 2016 Market Impact Updates Deferred scope Deferred scope Maximum Curtailment Generation Report N/A April 20, 2016 Page 74

  25. Early 2016 – OMS Enhancements (Continued) Milestone Type Milestone Name Dates Status Board Approval Board Approval N/A BPMs Publish Final Business Practice Manuals N/A  External BRS External Business Requirements Jun 12, 2015 Tariff Tariff N/A Config Guides Config Guide N/A Tech Spec Create ISO Interface Spec (Tech spec) N/A Market Sim Market Sim Window Feb 16, 2016 - Mar 07, 2016 Production Activation Post Implementation OMS Enhancements Mar 23, 2016 Page 75

  26. 2016 – Application Identity Management (AIM) Enhancements Milestone Type Milestone Name Dates Status Board Approval Board Approval N/A BPMs BPMs N/A External BRS External BRS N/A Tariff Tariff N/A Config Guides Config Guide N/A Tech Spec Tech Spec N/A Production Activation AIM 2015 Enhancements Mar 17, 2016 Page 76

  27. 2016 – Expanding Metering and Telemetry Options Phase 2 Milestone Details/Date Status Distributed Energy Resource Provider (DERP) Agreement: 1. General functions of the DERP, • Offer Energy and AS: aggregated resources in Sub-Lap • Provide ISO with accurate Information • Responsible for operating and maintain DER 2. Specify data concentrator functionality for real time monitoring, control and after the fact metering data • disaggregate ISO signals to sub-resources; obtain a resource response Application Software Changes • aggregate sub-resource operational and settlement meter data within a sub-Lap 3. Define the provision of technical and operational information to the ISO , • metering and communications requirements, • submission of economic bids and self-schedules and • provision of ancillary services 4. Identify responsibility for fulfilling the terms of the agreement • penalties and sanctions, cost responsibility, dispute resolution, representations and warranties, liability, uncontrollable forces and other miscellaneous terms BPM Changes Metering, Direct Telemetry Revised straw proposal May 12, 2015 Draft final proposal June 10, 2015 Board Approval July 16, 2015 External Business Requirements N/A Updated BPMs February 25, 2016, submitted PRR 892 Technical Specifications N/A Draft Configuration Guides N/A Tariff filing March 4, 2016 Production Activation N/A Page 77

  28. 2016 – Demand Response Registration Enhancements Project Info Details/Date Enhance Demand Response Registration functionality and processes Develop new registration user interface for DRRS Application Software Changes Develop new APIs for support of enhanced registration processes • CPG meeting (tech spec review) on March 22, 2016 BPM Changes Metering; Settlements & Billing Business Process Changes Automation of internal registration-related processes User Training TBD Milestone Type Milestone Name Dates Status Board Approval Board Approval N/A Publish Final Business Practice Manuals (Metering; BPMs Apr 18, 2016 Settlements & Billing) Draft BPM changes (Metering; Settlements & Billing) Apr 06, 2016 Post Draft BPM changes (Metering; Settlements & Apr 07, 2016 Billing) External BRS - Enabling Demand Response Phase 2  External BRS Jun 04, 2015 - Registration Tariff Tariff N/A Config Guides Config Guide N/A Market Sim Market Sim Window Apr 21, 2016 - May 11, 2016 Production Activation Post-Mrkt Consol - DRRS Phase 2 - Reg May 26, 2016 Page 78

  29. 2016 – RIMS Functional Enhancements Project Info Details/Date Status Functional enhancements resulting from the Customer Partnership Group CPG. Application Software Changes More details to be provided in the future. Generator Interconnection and Deliverability Allocation Procedures Generator Interconnection Procedures Managing Full Network Model BPM Changes Metering Generator Management Transmission Planning Process Customer Partnership Group 10/16/15 Application and Study Webinar 3/31/16 Milestone Type Milestone Name Dates Status Board Approval Board approval not reqiured N/A BPMs No BPMs required N/A External BRS External BRS not Required N/A Tariff No Tariff Required N/A Config Guides Configuration Guides not required N/A Tech Spec No Tech Specifications Required N/A Production Activation RIMS5 App & Study Mar 21, 2016 RIMS5 Generation, Transmission and QM Jul 29, 2016 Page 79

  30. 2016 – Year 1 Enhancements 2015 - Available Balancing Capacity Milestone Details/Date Status SIBR : EIM Participating Resources to include their assigned Regulation capacity in their Energy Bids submitted to the EIM. RTM : • The market will not dispatch this capacity, unless it is required to resolve a power balance infeasibility in an EIM BAA. • Formulate the solution so that the energy from the Regulation dispatch is consumed Application Software Changes within the BAA and does not exit through the EIM Transfer; • Regulation should only be dispatched to the extent necessary to resolve power balance infeasibility; it should not be used to displace other capacity made available in the BAA for EIM participation. • If the infeasibility persists after dispatching all available Regulation, the price will be set at the applicable administrative price. Board Approval N/A Approved on December 17, 2015. ISO requested waiver to go-live no later than March 1, 2016. Tariff http://www.caiso.com/Documents/Dec17_2015_OrderAcceptingComplia nceFiling_AvailableBalancingCapacity_ER15-861-006.pdf BPM Changes PRR posted February 1, 2016 Business Process Changes N/A External Business Requirements Please see Draft EIM BPM changes. Technical Specifications N/A External Training N/A Draft Configuration Guides Implemented with Year 1 Enhancements Fall 2015 Release Market Simulation N/A Production Activation March 23, 2016 Page 80

  31. 2016 – Bidding Rules Enhancements – Part A Project Info Details/Date Bidding Rules Enhancement Part A will correct a structural inefficiency by combining consideration of energy and commitment cost bidding rules to refine and improve alignment between rules. Market Participants will receive the following enhancements to the existing Minimum Load Cost (MLC) bid process: • Improve cost bidding flexibility to consider resource operating costs and characteristics • All the market participants to reflect actual costs through increased bid flexibility • Reduce inefficient market outcomes by inappropriate changed bid prices • Resolve market inefficiency caused by rerating the MLC where the ISO is committing less economic resources Application Software Changes DAM/RTM: Updated minimum load cost (MLC) calculations will include: • Calculate the actual Minimum Load Costs (MLC) based on the heat rate of the resource using a DEB integration method • Incremental DEB costs are added to the master file minimum load costs at the re- rated Pmin level • Support hourly MLC in optimization engine • Support rules for handling multiple Pmin rerates within same hour. • Also applies to MSG resources per configuration BPM Changes Market Operations Milestone Type Milestone Name Dates Status  Board Approval Board of Governors (BOG) approval Feb 04, 2016  External BRS External Business Requirements Feb 22, 2016  Post External BRS Feb 23, 2016 Tariff File Tariff Mar 18, 2016 Config Guides Complete ClearTrust Configuration document TBD Market Sim Market Sim Window N/A Production Activation Bidding Rules Part A May 18, 2016 Page 81

  32. Fall 2016 – BAL-003 Compliance Project Info Details/Date • To procure transferred frequency response from external BAs through a competitive solicitation process • Allocate the cost of TFR to metered demand: new charge code • Require generators to manage their plants consistent with NERC published reliability guidelines for primary frequency control • Require generators to provide governor control and plant level control system data to the ISO, including Droop Setting, Deadband, frequency Application Software Changes responsive maximum output level, Plant-level distributed control systems(DCS) with frequency bias term (Y/N), level temperature loop controls(@what output and/or temperature; Y/N) • Increase market transparency of the ISO’s frequency response performance through its Monthly Market Performances Reports • Clarify the authority of ISO to designate any reserve as contingency only reserve regardless of resource’s election Milestone Name Dates Status Board Approval BOG Approval Mar 25, 2016 BPMs Publish Final Business Practice Manuals TBD Milestone Type External Business Requirements Mar 31, 2016 Tariff File Tariff TBD Receive FERC order TBD Config Guides Draft Configuration Guides TBD Tech Spec Create ISO Interface Spec (Tech spec) N/A Market Sim Market Sim Window TBD Production Activation BAL- 003 Frequency Response Oct 01, 2016 Page 82

  33. Fall 2016 – Flexible Ramping Product System Description • EIM transfer limit congestion treatment: • Define ISL/ITC for multiple ETSR scheduling limits Master File • Define ISL/ITC for EIM BAA to support FMM • Remove GHG bid CAP from MF, always use ECIC/RLC • EIM transfer limit congestion treatment • EIM transfer congestion component by BAA share IFM/RTM • EIM transfer limit subject to LMPM • Allow multiple ETSR limits in ISL/ITC constraint • Enforce ISL for EIM BAA by intertie • EIM entity shall submit base schedule of include approved, pending and adjusted BSAP e-tags • Publish GHG bid Cap (CMRI) CMRI • Publish after fact EIM interchange schedules • Publishing by type of constraints, include EIM Transfer Constraints, HVDC, and other constraints. OASIS • Allow API for GHG bid • Publish base NSI for EIM BAA along with Base schedule test results at T-75, T-55 and T-40  ADS ADS instructions shall reflect FRU and FRD ramping awards (separately) in DOTs/DOPs to confirm flexible ramping awards in both binding and advisory intervals (for both generator and interties resource types).  Additionally, ADS shall present/indicate binding FMM interval instructions for intertie schedules/awards (for all product types inclusive of Energy, Flex Ramp Up, Flex Ramp Down). Page 83

  34. Fall 2016 – Flexible Ramping Product System Description  BPM changes Market instruments  Market Operations  Definitions & Acronyms  Settlements & Billing Milestone Type Milestone Name Dates Status  Board Approval Project Approved by Board of Governors Feb 03, 2016 BPMs Post Draft BPM changes Mar 31, 2016  External BRS Post External BRS Mar 15, 2016 Tariff File Tariff Mar 31, 2015 Config Guides Post Draft Config guides May 20, 2016 Tech Spec Publish Technical Specifications Apr 01, 2016 Market Sim Market Sim Window Jul 05, 2016 - Jul 29, 2016 Production Activation Flexible Ramping Product Oct 01, 2016 Page 84

  35. Fall 2016 – BCR Modifications and VER Settlements Project Info Details/Date Application CMRI : Shall publish the Expected Energy Allocation records with a new market service type Software ‘FCS’. Note: ‘FCS’ stands for ‘forecast’ and represents capacity above the forecast. Changes: CMRI, Settlements Policy Topics: • Ramp rate for variable energy resources. • Residual imbalance energy settlement for economic bidding variable energy resources. • Persistent deviation metric applied to variable energy resources. Proposed scope • Default energy bids for economic bidding variable energy resources. • Day-ahead metered energy adjustment factor. • Tariff clarifications following market issues bulletin. Settlements and Billing BPM Changes Milestone Type Milestone Name Dates Status  Board Approval Board Approval Jul 01, 2015 Publish Final Business Practice Manuals (Settlements; Market Settlements BPMs May 13, 2016 Design and Configurations)  External BRS Post External BRS Dec 31, 2015 Tariff File Tariff Mar 31, 2016 Config Guides Settlements Configuration Guide Apr 08, 2016 Tech Spec Publish Technical Specifications Mar 31, 2016 Market Sim Market Sim Window Jul 05, 2016 - Jul 29, 2016 Production Activation BCR Modification and VER Settlement Oct 01, 2016 Page 85

  36. Fall 2016 – Real Time Dispatch Local Market Power Mitigation Project Info Details/Date • CMRI – Display mitigated bids from RTD process • RTM (Real Time Market) • RTPD: Perform the LMPM run as an integral part of the binding interval RTPD run • RTD: Proposed mitigation in RTD run would work the same Application Software Changes way as the current RTPD run • Oasis (Open Access Sametime Information System): Display RTD reports for Market Clearing, the Pnode clearing, similar to current RTPD reports • Energy Imbalance Market (EIM): under the proposed RTD method, bids are not necessarily mitigated for the whole hour BPM Changes • RTD MPM will work the same way as the current RTPD MPM Business Process Changes TBD Page 86

  37. Fall 2016 - Real Time Dispatch Local Market Power Mitigation – RTD LMPM Milestone Type Milestone Name Dates Status Board Approval Board of Governers (BOG) approval Mar 24, 2016 BPMs Update Business Practice Manuals (BPMs) TBD External BRS Post External BRS Mar 28, 2016 Tariff File Tariff Jul 18, 2016 Config Guides Complete ClearTrust Configuration document May 26, 2016 Tech Spec Technical Specifications May 03, 2016 Market Sim Market Sim Window Jul 05, 2016 - Jul 29, 2016 Production Activation RTD - Local Market Power Mitigation Enhancement Oct 01, 2016 Page 87

  38. Fall 2016 - Bidding Rules Enhancements – Part B Project Info Details/Date Bidding Rules Enhancement Part B will evaluate multiple new features for inclusion. Developments under consideration include: • Allow resources without a day-ahead schedule to rebid commitment costs in the real-time market (SIBR rule changes) • No longer insert bids for Short Term Unit Commitment (STUC) for resources that do not have a day ahead market award and do not have a real time must offer obligation (SIBR rule changes) • Extend a filing right @ FERC for resources to seek recovery of marginal fuel procurement Application Software Changes costs exceeding the commitment cost bid cap not recovered through market revenues • Increase the flexibility of registering fuel regions and allow for cap-and-trade credits to the base gas transportation rates (Master File – RDT change) • Include resource-specific start-up electricity costs in proxy costs based on wholesale projected electricity price, unless resource verifies costs incurred are retail rates (Master File – RDT change) • Settlements reflect minimum or maximum operating level if submitted through OMS. (Settlement and Integration impact) Business Process Changes Market Instruments; Reliability Requirements, Settlements & Billing Page 88

  39. Fall 2016 – Acceptable Use Policy – CMRI Project Info0 Details/Date Scope includes enforcement of Acceptable Use Policy for CMRI services to Application Software Changes support the full implementation of 1 call per service per identity (as designated by certificate) every 5 seconds. Milestone Type Milestone Name Dates Status Board Approval Board Approval N/A BPMs BPMs N/A External BRS External BRS N/A Tariff Tariff N/A Config Guides Config Guide N/A Tech Spec Tech Spec N/A Market Sim Market Sim Window Jul 05, 2016 - Jul 29, 2016 Production Activation Acceptable Use Policy - CMRI Oct 01, 2016 Page 89

  40. Fall 2016 – OMAR Replacement Project Info Details/Date The scope of the project is to replace the current OMAR Online application with a new CUI framework based interface and provide standard B2B web services integration. B2B services will be modified to align with CIM standard and to convert to GMT, and the existing FTP solution will be replaced. The new solution will also remove the custom Application Software Changes OMAR certificates by leveraging the CAISO Multiple Application (CMA) certificates. • Targeted API review sessions to scheduled for February • API integration targeted for testing in April, in time for unstructured market sim • UI delivery targeted for end of May, with active CPG involvement BPM Changes Metering and Definitions & Acronyms (references to systems may need to change) Potential Level-II business process changes under – • Business Process Changes Manage Market & Reliability Data & Modeling • Manage Operations Support & Settlements Milestone Type Milestone Name Dates Status Board Approval Board Approval N/A BPMs Publish Final Business Practice Manuals N/A  External BRS Publish External BRS Oct 02, 2015 Tariff Receive FERC order N/A Config Guides Config Guide N/A  Tech Spec Publish Tech Specs Dec 21, 2015 Market Sim Market Sim Window Jul 05, 2016 - Jul 29, 2016 Production Activation Post-Mrkt Consol - OMAR Replacement Sep 29, 2016 Page 90

  41. Fall 2016 – PIRP System Application Decommissioning Project Info Details/Date • Forecast Data Reporting (resource -level) that was performed in PIRP will be done in CMRI. Rolling Hour Ahead, Locked Hour Ahead, and Rolling Day-Ahead forecasts Application Software Changes: • CMRI to publish ClearedMW from all markets (Day-Ahead and PIRP/CMRI Real-Time) to the Market participants. • CMRI to receive the Electricity Price Index for each resource from Potomac/RLC/ECIC, store it, and publish it to the Market Participants. BPM Changes CMRI Technical Specification; New APIs will be described. Business Process Changes MPs will receive the VER reports from CMRI rather than PIRP. Milestone Type Milestone Name Dates Status Board Approval Board Approval N/A  External BRS External Business Requirements Jun 29, 2015 Tariff Tariff Filing Activities N/A Config Guides Settlements Configuration N/A Publish Technical Specifications (Data Transparency Tech Spec Apr 15, 2016 Improvements) Tech Spec Publish Technical Specifications (CMRI / PIRP  Feb 05, 2016 Decommissioning) PIRP Decommissioning, CMRI Reports, Data Transparency Market Sim Jul 05, 2016 - Jul 29, 2016 Improvements PIRP Decommissioning, CMRI Reports, Data Transparency Production Activation Oct 01, 2016 Improvements Page 91

  42. Fall 2016 – Post Implementation OMS Enhancements Project Info Details/Date OMS Enhancements project will implement the following functionality: Application Software Changes • Manage Broadcast Status Update BPM Changes TBD Business Process Changes Yes Milestone Type Milestone Name Dates Status Board Approval Board Approval N/A BPMs Publish Final Business Practice Manuals N/A  External BRS External Business Requirements Jun 12, 2015 Tariff Tariff N/A Config Guides Config Guide N/A Tech Spec Create ISO Interface Spec (Tech spec) N/A Market Sim Market Sim Window Jul 05, 2016 - Jul 29, 2016 Production Activation Post Implementation OMS Enhancements October 1, 2016 Page 92

  43. Fall 2016 – EIM Year 1 Enhancements Phase 2 Project Info Details/Date • EIM transfer limit congestion treatment: (MF, RTM, EIM transfer congestion component by BAA share) • Dynamic competitive assessment for market power mitigation of EIM transfer limits: (IFM/RTM, LMPM configuration) • Use of e-tags to establish base schedule for import and export: (BSAP, EIM entity submit base schedule) • Application Software Outage reporting to Peak Reliability Coordinator (OMS, service provide to EIM entity) • Changes Allow multiple EIM transfer ETSRs subject to one scheduling constraint (MF,RTM) • Publish Intertie binding constraint shadow prices by type of constrains(OASIS) • Publish the LMP for SP-Tie include loss component(OASIS) • Publish Resource GHG bid at public bids(OASIS) • Publish EIM BAA base NSI at T-75, T-55, and T-40(OASIS) • Publish the EIM BAA after-the-fact interchange schedules to EIM entity(CMRI) • Publish resource GHG bid Cap(CMRI) BPM Changes Energy Imbalance Market Business Process Changes Manage market and grid, Manage operations support and Settlements Milestone Type Milestone Name Dates Status Board Approval Board Approval occurred in year 1 phase 1 N/A BPMs Draft BPM changes Jun 30, 2016  External BRS External Business Requirements Feb 16, 2016 Tariff File Tariff Aug 01, 2016 Config Guides Post Draft Config guides Jun 24, 2016 Tech Spec Create ISO Interface Spec (Tech spec) Apr 01, 2016 Market Sim Market Sim Window Jul 05, 2016 - Jul 29, 2016 EIM Year 1 – Phase 2 Production Activation Oct 01, 2016 Page 93

  44. Fall 2016 – EIM Arizona Public Service Project Info Details/Date Application Software Changes Implementation of Arizona Public Service as an EIM Entity. EIM BPM will be updated to reflect new modeling scenarios identified BPM Changes during APS implementation and feedback from APS. ISO promoted market network model including PSE area to non- production system and allow PSE exchange data in advance of Market Simulation on 3/7/16. Additional Market Sim Info Integration/Day in the Life Testing March 7 – May 30, 2016 Market Simulation July 5 – July 29, 2016 August 1 – September 30, 2016 Parallel Operations Milestone Type Milestone Name Dates Status Board Approval Board Approval N/A BPMs BPMs N/A External BRS External BRS N/A  Tariff APS files tariff revisions with FERC Feb 12, 2016 Config Guides Config Guide N/A Tech Spec Tech Specs N/A Market Sim Market Sim Window Jul 05, 2016 - Jul 29, 2016 Production Activation EIM - Arizona Public Service Sep 30, 2016 Page 94

  45. Fall 2016 – EIM Puget Sound Energy Project Info Details/Date Implementation of Puget Sound Energy as an EIM Entity. WebOMS - Provide Balancing Authorities with the ability to submit outages to Application Software Changes WebOMS and the ability to submit PeakRC through their Coordinated Outage Scheduling System (COS). BPM Changes EIM BPM will be updated based on feedback from PSE. ISO promoted market network model including PSE area to non-production system and allow PSE exchange data in advance of Market Simulation on 3/7/16. Additional Market Sim Info Integration/Day in the Life Testing March 7 – May 30, 2016 Market Simulation July 5 – July 29, 2016 August 1 – September 30, 2016 Parallel Operations Milestone Type Milestone Name Dates Status Board Approval Board Approval N/A BPMs BPMs N/A  External BRS OMS - BRS External Design Jul 24, 2015  Tariff Tariff filing at FERC Feb 12, 2016 Config Guides Settlements N/A Tech Spec Tech Specs N/A Market Sim Market Sim Window Jul 05, 2016 - Jul 29, 2016 Production Activation EIM - Puget Sound Energy Sep 30, 2016 Page 95

  46. Reliability Services Initiative Phase 1B Project Info Details/Date Status • Default flexible qualifying capacity provisions for phase 2 consideration (we might need data collection performed in order to support RSI Phase 2 • Redesign of Replacement Rule for System RA and Monthly RA Process • RA Process and Outage Rules for implementation for 2017 RA year • Scope not delivered in RSI Phase 1A (Grandfathered Contracts, RAAM Decommissioning – SCP & CPM screens from RAAM to CIRA, Acquired Application Software Changes Contracts, OASIS reporting, web services related to APIs for CSP offers, APIs for Generic/Flex Substitutions, and Release of Generic/Flex Subs – UI & API) • Impacted Systems: • CIRA • OMS • Integration Business Process Changes Manage Market & Reliability Data & Modeling Milestone Type Milestone Name Dates Status  Board Approval Board Approval Mar 25, 2015 BPM Post Draft BPM changes - Outage Management TBD PostDraft BPM changes - Reliability Requirements TBD External BRS External Business Requirements Apr 22, 2016 Tariff File Tariff TBD Receive FERC order TBD Config Guides Issue Draft Configuration Guides TBD Tech Spec Create ISO Interface Spec (Tech spec) TBD Market Sim Market Sim Window TBD Production Activation Reliability Services Initiative Phase 1b TBD Page 96

  47. Commitment Cost Enhancements Phase 3 Project Info Details/Date 1. Clarify registration process and documentation to determine opportunity costs 2. Each submission evaluated on a case-by-case basis to determine if the ISO can calculate opportunity costs • Application Software Changes ISO calculated; Modeled limitation • Market Participant calculated; Negotiated limitation 3. Enhanced definition of “use - limited” in response to FERC’s rejection of the proposed definition in Cost Commitment Enhancements Phase 2 BPM Changes Market Instruments Level II – Manage Reliability Requirements Business Process Changes Level II – Manage Day Ahead Market Page 97

  48. Stepped Constraints Milestone Details/Date Status The ISO market applies stepped penalty prices to certain constraints in the market: (1) the power balance constraint, (2) transmission constraints, and Application Software Changes (3) energy imbalance market transfer constraints, These changes would apply different penalty prices for infeasibilities depending on the level of constraint relaxation or potentially other criteria Board Approval TBD Tariff TBD BPM Changes Yes Business Process Changes N/A External Business Requirements Yes Technical Specifications N/A External Training N/A Draft Configuration Guides N/A Market Simulation N/A Production Activation TBD Page 98

  49. Energy Storage and Distributed Energy Resources (ESDER) Policy Status Project Info Details/Date 2015 scope: 1. NGR model enhancement: a. Update documentation on NGR to ISO BPMs to capture material and clarifications b. Clarify how the ISO uses state of charge in market optimization. c. Allow initial state of charge as a submitted parameter in the day-ahead market. (SIBR) d. Allow option to not provide energy limits or have ISO co-optimize an NGR based on state of charge (SIBR, IFM/RTM) Scope and 2. PDR/RDRP enhancement: Application a. Support alternative performance evaluation method: MGO Changes b. Support Baseline Type-II 3. Multiple use applications: a. DERA provides services to distribution system and wholesale market b. DERA provides services to end-use customers and wholesale market Include provisions: 1. Daily SQMD for DERA; 2. Settle DERA deviation through UIE; 3. Not address potential double payment; 4. No limitation DERA for distribution system; 5. treat PDR/RDRR as serve end-use and wholesale market. Milestone Type Milestone Name Dates Status  Board Approval Board Approval Feb 04, 2016 BPMs Post Draft BPM changes TBD External BRS External Business Requirements TBD Tariff File Tariff TBD Config Guides Draft Configuration Guide TBD Tech Spec Create ISO Interface Spec (Tech spec) TBD Market Sim Market Sim Window TBD Production Activation Storage and Aggregated DER TBD Page 99

  50. ADS UI Replacement Milestone Details/Date Status Port client from Delphi to new common user interface (ADS Query Tool and Real Application Software Changes Time Functionality) BPM Changes N/A Business Process Changes N/A Board Approval N/A External Business Requirements N/A Updated BPMs N/A Technical Specifications N/A Draft Configuration Guides N/A Market Simulation TBD Tariff N/A Production Activation TBD Page 100

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend