Market Performance and Planning Forum May 16, 2017 Objective: - - PowerPoint PPT Presentation
Market Performance and Planning Forum May 16, 2017 Objective: - - PowerPoint PPT Presentation
Market Performance and Planning Forum May 16, 2017 Objective: Enable dialogue on implementation planning and market performance issues Review key market performance topics Share updates to 2017 release plans, resulting from stakeholders
Objective: Enable dialogue on implementation planning and market performance issues
- Review key market performance topics
- Share updates to 2017 release plans, resulting from
stakeholders inputs
- Provide information on specific initiatives
–to support Market Participants in budget and resource planning
- Focus on implementation planning; not on policy
- Clarify implementation timelines
- Discuss external impacts of implementation plans
- Launch joint implementation planning process
Slide 2
Market Performance and Planning Forum
Agenda – May 16, 2017
Time: Topic: Presenter: 10:00 – 10:05 Introduction, Agenda Kristina Osborne 10:05 – 10:20 May 3 CAISO Stage 1 System Emergency Tim Beach 10:20 – 12:00 Market Performance and Quality Update Guillermo Bautista Alderete Amber Motley James Lynn 12:00 – 1:00 Lunch 1:00 – 1:30 Policy Update Brad Cooper 1:30 – 2:00 Flexible Capacity Update Amelia Blanke David Robinson 2:00 – 3:00 Release Update Adrian Chiosea Janet Morris
Slide 3
May 3 CAISO Stage 1 System Emergency
Tim Beach Shift Manager, Operations
Slide 4
May 3, 2017 Stage 1 Emergency Summary
- Peak load at 17:45 with sufficient capacity and operating
reserves
- Actual Net Scheduled Interchange (including dynamics) was
~1,150 MW below Day Ahead schedules
- ~600 MW of forced generation outages
- The HA market awarded 1,230 MW of supplemental energy
- n the interties for HE20 (19:00 to 20:00) but 830 MW of that
was declined
- At 19:01 a Stage 1 Emergency was declared and all DR
verbally dispatched (PDR & RDRR) – Two Contingency dispatches issued, RDRR enabled in the market in the second dispatch (and actually dispatched during manual implementation of DR.)
- Operating reserves recovered at 19:56
- 21:00 Stage 1 Emergency terminated
Slide 5
Market Performance and Quality Update
James Lynn Senior Advisor, Market Settlements Design Amber Motley Manager, Short Term Forecasting Guillermo Bautista Alderete, Ph.D. Director, Market Analysis and Forecasting
Congestion Revenue Right Analysis Effort
CRR Auction Effort
- Initiative is split in two phases
– Analysis phase – Policy phase
- CRR Working group session held on April 18 to discuss
the Analysis scope
- Analysis phase needed to have in-depth analysis of the
auction efficiency, and identify drivers and guide the policy phase
Slide 8
Market Analysis done in three phases along the following areas
- Auction results
- Participation
- Transparency
- Modeling
– Accuracy – ISO practices/procedures – Market events – Systemic differences
- Constraint by constraint analysis
– Analyze constraints that did not bind in the auction but had payouts in the DAM – Analyze constraints with large payouts
- Impact of changes over time
Slide 9
Over Supply Update
Frequency of negative system prices has steadily increased year over year
Slide 11
0% 5% 10% 15% 20% 25% Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Frequency
2014 2015 2016 2017
Distribution of negative prices have shifted from early morning hours to midday hours*
Slide 12
* Metric of 2017 may be over-estimated since it includes only January through April.
0% 5% 10% 15% 20% 25% 30% 35% 40% 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Frequency
2014 2015 2016 2017
Slide 13
ISO total monthly VERS schedules and forecasts
Slide 14
IFM under-scheduling of wind generation
Monthly wind (VERS) downward flexibility in FMM
Slide 15
Monthly solar (VERS) downward flexibility in FMM from 11 AM to 5 PM
Slide 16
Slide 17
Hydro production higher than recent historical production
Slide 18
RTD renewable (VERS) curtailment continued to increase in March and April
The trend of curtailments is accelerating
Slide 19
10,000 20,000 30,000 40,000 50,000 60,000 70,000 80,000 90,000 May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar APR 2014 2015 2016 2017 ENERGY CURTAILMENTS (MWH) Local Economical System Economical Local ED System ED Self Sch System Self Sch Local
Solar production and net load records have been
- bserved this Spring
Slide 20
. Saturday May 13 Sunday May 14 Maximum load 26,120 MW at 20:36 25,644 MW at 20:36 Minimum load 20,342 MW at 03:44 19,428 MW at 03:58 Minimum net load 8,804 MW at 14:44 8,493 MW at 13:03
How are curtailments determined?
- All curtailments are driven by prices, either economical bids or
penalty prices.
- Effective April 11, 2017 the step-size of the power balance constraint
relaxation for over-supply conditions was reduced to 30 MW.
- Only April 30 and May 8 have observed self schedule curtailments
and by less than 100MW
Slide 21
TOR/ETC IFM self schedule RMT Price taker PBC violation Economical bids
Slide 22
Hydro production is trending upward for Spring but still lower than historical high hydro year of 2006
1,000 2,000 3,000 4,000 5,000 6,000 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2006 2014 2015 2016 2017 GWh
Hydro vs. Solar Monthly Production
Hydro Solar
Slide 23
Self scheduled interties in the real-time market remain high
Flexible Ramp Update
Flexible Ramp Product Up Requirement
Slide 25
Flexible Ramp Product Down Requirement
Slide 26
Flexible Ramp Product Up Awards
Slide 27
Flexible Ramp Product Down Awards
Slide 28
How is FRP settled?
Slide 29
Forecasted Upper limit Lower limit Net system demand at t t+1 (advisory interval) t (binding interval) Time Net system demand
Minimum requirement Demand curve Demand curve
Forecasted movement known with certainty
- e.g. self-schedule supply expected to ramp (up) from t to t+1; or load forecast that’s known to increase
from time t to t+1, requires an equivalent ramp up.
Uncertainty movement (forecast error)
- the requirements for this is derived from demand curve modeling based on historical forecast errors
Demand Curve to Meet FRD Uncertainty
Slide 30
t (binding interval) t+1 (advisory interval) Forecast net demand FRU forecasted net load change FRD uncertainty FRD max expected forecast error t (binding interval) t+1 (advisory interval) Forecast net demand FRU forecasted net load change FRD max expected forecast error No FRD procured
First figure – need to procure FRD uncertainty; second figure – no need to procure
Forecasted Movement has a direct settlement, uncertainty is awarded and allocated as an uplift
Binding Advisory
…
B A
…
Forecasted Movement (Market) Uncertainty A A RTD1 RTD2
Slide 31
- Supply and Interties resources (CC 7070)
– Separate FMM and Incremental RTD forecasted movement qty – (-1) * Forecasted Movement Qty * (FRU price - FRD price) – Rescind portion of forecasted movement in case of deviation (UIE/OA)
- Load resources (CC 7076)
– Allocate to SCs based on SC’s metered EIM Demand
- r metered CAISO Demand
Forecasted movement settlement
Slide 32
- Dispatchable Resources (CC 7071: FRU & CC 7081: FRD)
– Uncertainty award for FRU/FRD in FMM is settled at FMM FRU/FRD price – Uncertainty award for FRU/FRD in RTD which is incremental to FMM uncertainty award is settled at the RTD FRU/FRD price – Price has breakdown, which differentiates BAA constraint from EIM Area constraint contribution – Rescind portion of Uncertainty Capacity where resource deviation (UIE/OA) overlaps
Uncertainty Award Settlement
Slide 33
FRP Uncertainty Cost Allocation
Slide 34
I EFlexible ramping up Flexible ramping down
E I I E E ITotal Uncertainty MW by FRP Constraint Category’s Uncertainty MW Allocate to individual resource
Uncertainty
Forecasted Movement Settlement ISO – From November 1 to February 28, 2017
Scheduled Settlement Correction
Slide 35
Uncertainty Up Settlement – From Jan 2015 – April 2017
Slide 36
Once normalized for capacity procured, FRP uncertainty settlements in the same range as in prior months
Slide 37
FRP Up Uncertainty Payment Amount in EIM areas
Slide 38
FRP Down Uncertainty Payment Amount in EIM areas
Slide 39
FRP Up Payment – Hourly Distribution correlated to hourly profile
Slide 40
FRP Down Payment – Hourly Distribution correlated to hourly profile
Slide 41
Persistency Model Enhancement
Current Data Transfer Time Needed for External Forecast Service Provider (FSP)
Slide 43
CAISO is working on an enhancement based on persistency
- For Wind
– Recommendation is to use the simple lag persistence model.
- For Solar
– Recommendation is to use a persistence contour model.
Slide 44
Accounting of Market Dispatches/Curtailments of Renewables is also considered
- Market software will also handle cases of market
dispatches or curtailments of renewables – As soon as the market dispatches an EIR resource, logic will be included to take into consideration the supplemental dispatch of resource to be the EIR Resource Forecast.
Slide 45
Mean Average Percent Error for January 2017
Slide 46
PCM and Lag methods reduced External FSP MAPE by 50% for RTD
Wind Solar External FSP 6.5% 8.5% Lag 3.2% 5.9% PCM 3.5% 4.9% Forecast Type RTD
Total Mae Value for RTD SOLAR Forecast
Slide 47
0% 1% 2% 3% 4% 5% 6% 0:00 1:10 2:20 3:30 4:40 5:50 7:00 8:10 9:20 10:30 11:40 12:50 14:00 15:10 16:20 17:30 18:40 19:50 21:00 22:10 23:20
MAE Unit A
lag pcm 0% 2% 4% 6% 8% 10% 12% 0:00 1:10 2:20 3:30 4:40 5:50 7:00 8:10 9:20 10:30 11:40 12:50 14:00 15:10 16:20 17:30 18:40 19:50 21:00 22:10 23:20
MAE Unit B
lag pcm
0% 2% 4% 6% 8% 10% 12% 0:00 1:25 2:50 4:15 5:40 7:05 8:30 9:55 11:20 12:45 14:10 15:35 17:00 18:25 19:50 21:15 22:40
MAE Unit C
lag pcm 0% 2% 4% 6% 8% 10% 12% 14% 0:00 1:25 2:50 4:15 5:40 7:05 8:30 9:55 11:20 12:45 14:10 15:35 17:00 18:25 19:50 21:15 22:40
MAE Unit D
lag pcm
APPENDIX
Slide 48
Simple Lag Persistence Model
- Name Convention:
A (actual), F (forecast), E (Error) = F – A
- FH = Forecast Horizon (RTD)
- Lag Model
– F(t) = A(t-FH) (Forecast for time t = Actuals from time t-FH)
Slide 49
Recommendation for Solar Resources Persistence Counter Market Model
- Let F(t) be forecast, A(t) be actual, and FPI(t) be
estimate of full power output taking into consideration sun angle.
- The persistent forecast is then:
– F(t) = A(t-lag) / FPI(t-lag)* FPI(t) – Where A(t-lag) / FPI (t-lag) is the estimate “cloud” factor to A(t)/FPI(T) The premise is the lag forecast A(t-lag) should adjust according the track of performance under different cloudiness condition at lag time point
Slide 50
Example
- Sunny Day:
– A(t-lag) / FPI(t-lag) = 1
- Cloudy Day:
– A(t-lag) / FPI(t-lag) = .3
Slide 51
Market Update
Slide 53
Good price convergence in April based.
Note: Metric Based on System Marginal Energy Component (SMEC)
Slide 54
RT prices higher than DA prices for both NP15 and SP15 in April.
Slide 55
Insufficient upward ramping capacity in ISO continued to be at low levels since last November.
Slide 56
Insufficient downward ramping capacity declined since February.
Slide 57
Congestion revenue rights market revenue inadequacy without auction revenues.
Slide 58
Congestion revenue rights market revenue sufficiency including auction revenues.
Slide 59
Exceptional dispatch volume in the ISO area decreased since February.
Slide 60
Real-time Bid cost recovery dropped in April
Slide 61
Bid cost recovery (BCR) by Local Capacity Requirement area
Slide 62
Minimum online commitment (MOC)
MOC San Onofre Bus
Slide 63
Pmax of MOC Cleared Units
Slide 64
Enforcement of minimum online commitments in March and April
MOC Name Number (frequency) of hours in January and February Humboldt 7110 SVC In 1196 MOC Pease 994 Orange County 7630 801 Humboldt 7110 215 MOC East Nicolaus 96 MOC SAN ONOFRE BUS 90 MOC Devers Bus 41 SDGE 7820 CFEIMP_BG 34 MOC Placer 4551087 26 MOC Moss 4575683 15 SDGE 7820 9 SCIT MOC 8 MOC NP15 7 Orange county outage 7630 2
Slide 65
Renewable (VERS) schedules including net virtual supply and aligns with VER forecast in March and April
http://www.caiso.com/Pages/documentsbygroup.aspx?GroupID=EFF75C 2E-F28E-4087-B88B-8DFFAED828F8
Slide 66
Hourly distribution of maximum RTD renewable (VERS) curtailment in April
Slide 67
ISO area RTIEO increased since February.
2016 2017 (YTD) RTCO $50,398,946 $9,701,084 RTIEO
- $3,706,211
$18,633,447 Total Offset $46,692,735 $28,334,531
Slide 68
CAISO Price correction events increased in March and April
1 2 3 4 5 6 7 8 9 10 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 Count of Events Process Events Software Events Data Error Events Tariff Inconsistency
Slide 69
EIM-Related Price correction events decreased in March and April
2 4 6 8 10 12 14 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2016 2017 Count of Events Process Events Software Events Data Error Events Tariff Inconsistency
EIM Price trends
Slide 70
Robust Energy transfers observed in in 1st quarter, 2017
Average – 259MW Maximum – 1196MW Average – 186MW Maximum – 739MW Average – 108MW Maximum – 300MW Average – 173MW Maximum – 506MW Average – 0MW Maximum – 0MW Average – 84MW Maximum – 150MW Average – 80MW Maximum – 300MW Average – 118MW Maximum – 300MW Average – 231MW Maximum – 871MW Average – 222MW Maximum – 791MW Average – 141MW Maximum – 330MW Average – 136MW Maximum – 360MW Average – 165MW Maximum – 909MW Average – 184MW Maximum – 945MW Average – 144MW Maximum – 857MW Average – 0MW Maximum – 0MW
PACE CAISO PACW NEVP AZPS PSEI
Slide 71
Slide 72
EIM BCR observed a modest increased in April
Slide 73
EIM Manual Dispatch increased in April and is mostly concentrated in APS area
Day-ahead load forecast
0.0% 0.5% 1.0% 1.5% 2.0% 2.5% 3.0% Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2015 2016 2017
MAPE
Slide 74
Day-ahead peak to peak forecast accuracy
0.0% 0.5% 1.0% 1.5% 2.0% 2.5% 3.0% 3.5% Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2015 2016 2017
MAPE
Slide 75
Day-ahead wind forecast
0.0% 1.0% 2.0% 3.0% 4.0% 5.0% 6.0% 7.0% 8.0% 9.0% 10.0% Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2015 2016 2017
MAE
**In 2015-2016, Economic dispatches are not added back in to the generation data. **The 2017 generation data used for accuracy calculation contains the economically dispatched MW.
Slide 76
Day-ahead solar forecast
0.0% 1.0% 2.0% 3.0% 4.0% 5.0% 6.0% 7.0% 8.0% 9.0% 10.0% Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2015 2016 2017
MAE
**In 2015-2016, Economic dispatches are not added back in to the generation data. **The 2017 generation data used for accuracy calculation contains the economically dispatched MW.
Slide 77
Real-time wind forecast
0.0% 0.5% 1.0% 1.5% 2.0% 2.5% 3.0% 3.5% 4.0% Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2015 2016 2017
MAE
**2015-2016 represent the accuracy of the forecast made each hour at xx:55 for the following hour, i.e. the 5-65 minute ahead forecast. Economic dispatches are not added back in to the generation data. **2017 has been changed to track the RTD accuracy, i.e. the forecast made 7.5 minutes before the binding
- interval. The 2017 generation data used for accuracy calculation contains the economically dispatched MW.
**This forecast accuracy is pulled directly from the CAISO Forecasting System.
Slide 78
Real-time solar forecast
0% 1% 2% 3% 4% 5% 6% Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2015 2016 2017
MAE
**2015-2016 represent the accuracy of the forecast made each hour at xx:55 for the following hour, i.e. the 5-65 minute ahead forecast. Economic dispatches are not added back in to the generation data. **2017 has been changed to track the RTD accuracy, i.e. the forecast made 7.5 minutes before the binding
- interval. The 2017 generation data used for accuracy calculation contains the economically dispatched MW.
**This forecast accuracy is pulled directly from the CAISO Forecasting System.
Slide 79
Market Performance and Planning Forum
May 16, 2017
We are on lunch break, returning at 1:00 p.m. If you have questions, send to Kristina Osborne at kosborne@caiso.com
- r call on cell at 916-802-7631.
Policy Update
Brad Cooper Manager, Market Design and Regulatory Policy
Ongoing policy stakeholder initiatives
- Energy storage and distributed energy resources (ESDER)
Phase 2
– Publish draft final proposal in June – July EIM Governing Body and CAISO Board meetings
- Contingency modeling enhancements
- Fourth revised straw proposal including prototype results in late
June
- September CAISO Board meeting
- Generator contingency and remedial action scheme
modeling
– Draft final proposal in June – Sept EIM Governing Body and CAISO Board meetings
Slide 82
Ongoing policy stakeholder initiatives (continued)
- Commitment costs and default energy bid enhancements
– Recent stakeholder working groups – Straw proposal in June – November 2017 EIM Governing Body and CAISO board meetings
- Temporary suspension of resource operations
– Recently posted issue paper – Nov CAISO Board meeting
- Capacity Procurement Mechanism risk-of-retirement
process enhancements
– Recently posted issue paper – Nov CAISO Board meeting
Slide 83
Ongoing policy stakeholder initiatives (continued)
- EIM Greenhouse Gas Enhancements
– Draft final proposal in late May – July 2017 EIM Governing Board and ISO Board meetings (briefing) – Report evaluating two-pass solution in late Q4 2017 – Early 2018 EIM Governing Body and ISO Board meetings for approval
- Flexible resource adequacy criteria and must-offer
- bligation – phase 2
– Second revised straw proposal in July – Q2 2018 ISO Board meeting
- Congestion revenue right auction efficiency
– Stakeholder working group on analysis in April – Analysis phase in progress – Policy development phase starting after analysis complete in Q4
Slide 84
Ongoing policy stakeholder initiatives (continued)
- Frequency response – phase 2
– Developing new schedule – Early 2018 CAISO board meeting
- Bid cost recovery enhancements
– Suspended due to FERC uplift allocation NOPR
Slide 85
Upcoming policy stakeholder initiatives
- Aliso Canyon mitigation measures extension
– Straw and draft final proposals in June – July EIM Governing Body and ISO Board meetings
- Management of EIM Imbalance settlement for bilateral
schedule changes
– Issue paper in June – Oct EIM Governing Body and Nov ISO Board meetings
- Donation by third party of transmission capacity available
for EIM transfers
– Issue paper in June – Oct EIM Governing Body and Nov ISO Board meetings
Slide 86
Upcoming policy stakeholder initiatives (continued)
- Planned to start in Q3 2017
– EIM net wheeling charge – Review Transmission Access Charge Structure – Resource adequacy reform – Real-time market enhancements
Slide 87
2016 Annual Report
Amelia Blanke Manager, Monitoring & Reporting Department of Market Monitoring
Total market costs were down by about 4 percent after accounting for natural gas and greenhouse gas price changes.
Slide 89
$0 $1 $2 $3 $4 $5 $6 $7 $0 $10 $20 $30 $40 $50 $60 $70 2012 2013 2014 2015 2016 Average annual gas price ($/MMBtu) Average annual cost ($/MWh) Average cost (nominal) Average cost normalized to gas price, including greenhouse gas adjustment Average daily gas price, including greenhouse gas adjustments ($/MMBtu)
Estimated average wholesale energy costs per MWh (2012 – 2016)
Slide 90
2012 2013 2014 2015 2016 Change '15-'16 Day-ahead energy costs 32.57 $ 44.14 $ 48.57 $ 34.54 $ 30.70 $ (3.84) $ Real-time energy costs (incl. flex ramp) 0.99 $ 0.57 $ 1.98 $ 0.69 $ 1.02 $ 0.33 $ Grid management charge 0.80 $ 0.80 $ 0.80 $ 0.80 $ 0.81 $ 0.01 $ Bid cost recovery costs 0.45 $ 0.47 $ 0.40 $ 0.39 $ 0.33 $ (0.06) $ Reliability costs (RMR and CPM) 0.14 $ 0.10 $ 0.14 $ 0.12 $ 0.11 $ (0.01) $ Average total energy costs 34.96 $ 46.08 $ 51.89 $ 36.54 $ 32.97 $ (3.58) $ Reserve costs (AS and RUC) 0.37 $ 0.26 $ 0.30 $ 0.27 $ 0.54 $ 0.26 $ Average total costs of energy and reserve 35.33 $ 46.34 $ 52.19 $ 36.81 $ 33.50 $ (3.31) $
Markets continued to perform close to competitive benchmarks.
Slide 91
$0 $10 $20 $30 $40 $50 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Average price ($/MWh) Competitive baseline ($/MWh) Average load-weighted day-ahead price Average load-weighted 15-minute price Average load-weighted 5-minute price
Estimated net revenue of a hypothetical new unit 2012 - 2015
$0 $20 $40 $60 $80 $100 $120 $140 $160 $180 $200 $220 2012 2013 2014 2015 $/kW-year Net revenues (NP15) Net revenues (SP15) Levelized fixed cost target $0 $20 $40 $60 $80 $100 $120 $140 $160 $180 $200 $220 2012 2013 2014 2015 $/kW-year Net revenues (NP15) Net revenues (SP15) Levelized fixed cost target
Combined Cycle Combustion Turbine
Slide 92
DMM updated net revenue analysis assumptions in 2016
- Not directly comparable to prior analysis
- Optimized dispatch of hypothetical resource
– Objective: maximize profit subject to resource constraints – 2016 NP15 and SP15 prices
- Combined cycle: day-ahead and five minute prices
- Combustion turbine: 15 and 5 minute prices
– Incremental energy cost = default energy bid – Commitment cost = proxy start up and minimum load
http://www.caiso.com/Documents/2016AnnualReportonMarketIssuesandPerformance.pdf
Slide 93
Financial analysis of new combined cycle unit (2016)
Slide 94
Zone Scenario Capacity factor Total energy revenues ($/kW-yr) Operating costs ($/kW-yr) Net revenue ($/kW-yr) Day-ahead prices and default energy bids 21% $75.88 $64.65 $11.23 Day-ahead prices and default energy bids without adder 23% $83.12 $70.45 $12.67 Day-ahead commitment with dispatch to day-ahead and 5-minute prices using default energy bids 22% $79.73 $66.82 $12.91 Day-ahead prices and default energy bids 29% $104.92 $84.40 $20.52 Day-ahead prices and default energy bids without adder 32% $111.20 $88.83 $22.37 Day-ahead commitment with dispatch to day-ahead and 5-minute prices using default energy bids 30% $108.51 $86.38 $22.13 NP15 SP15
Significantly below California Energy Commission’s estimate of annualized fixed costs for a hypothetical combined cycle is $166/kW-yr
Financial analysis of new combustion turbine (2016)
Slide 95
Zone Scenario Capacity factor Real-time energy revenues ($/kW-yr) Operating costs ($/kW-yr) Net revenue ($/kW-yr) 15-minute prices and default energy bids 4.5% $23.46 $18.67 $4.80 15-minute prices and default energy bids without adder 5.6% $27.85 $22.17 $5.68 15-minute commitment with dispatch to 15-minute and 5-minute prices using default energy bids 5% $31.41 $21.03 $10.38 15-minute prices and default energy bids 7% $41.37 $28.87 $12.50 15-minute prices and default energy bids without adder 9% $48.20 $34.33 $13.87 15-minute commitment with dispatch to 15-minute and 5-minute prices using default energy bids 8% $50.07 $32.79 $17.29 NP15 SP15
Significantly below California Energy Commission’s estimate of annualized fixed costs for a hypothetical combustion turbine is $177/kW-yr
Flexible ramping payments
Slide 96
$0.00 $0.02 $0.04 $0.06 $0.08 $0.10 $0.0 $0.5 $1.0 $1.5 $2.0 $2.5 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2015 2016 Payments per MWh load ($/MWh) Total payments ($ million) California ISO PacifiCorp East PacifiCorp West NV Energy Puget Sound Energy Arizona Public Service Payments per MWh of load
Flexible ramping product implementation
Release Plan Update Janet Morris Director, Program Office Adrian Chiosea Manager, Strategic Initiative Management
Release Plan 2017
Slide 98
Independent 2017
- MRI-S ACL Groups + CPG Enhancements (formerly OMAR Replacement)
- RIMS Functional Enhancements
- Black Start and System Restoration Phase 2
- Forecasting & Data Transparency Improvements (PIRP System Decommissioning)
- Aliso Canyon mitigation measures extension
Fall 2017 (11/1/17)
- EIM Portland General Electric (PGE) – 10/1/17
- Bidding Rules Enhancements – Part B
- Commitment Cost Enhancement Phase 3
- RM & EIM 2017 Enhancements
- Gas Burn Report
- SIBR UI Upgrade
Release Plan – 2018 and subject to further planning
Slide 99
Spring 2018
- Reliability Services Initiative 2017
- EIM 2018 Idaho Power Company
Fall 2018 – tentative, subject to impact assessment
- Contingency Modeling Enhancements
- Flexible Resource Adequacy Criteria and Must-offer Obligation Phase 2
- Commitment Costs and Default Energy Bid Enhancements
- Energy Storage and DER Phase 2
- Temporary Suspension of Resource Operations
- Capacity Procurement Mechanism – risk-of-retirement process enhancements
- Management of EIM imbalance settlement for bilateral schedule changes
- ADS User Interface Replacement
- CIRA Technology Upgrade
Spring 2019
- EIM 2019 Seattle City Light
- EIM 2019 Balancing Authority of Northern California (BANC)
Fall 2019 – tentative, subject to impact assessment
- Regional Integration and EIM Greenhouse Gas Compliance
- Generation Contingency and Remedial Action Scheme
- Frequency Response Phase 2
- Congestion Revenue Right auction efficiency
Spring 2020
- EIM 2020 Salt River Project
Subject to further release planning:
- DRS Replacement
2017 - MRI-S ACL Groups+ CPG Enhancements
Project Info Details/Date Application Software Changes
The MRI-S metering (MRI-S) application cannot currently support ACL (Access Control List) groups functionality for defining a subset of resources belonging to an SCID. Enhancements to the Application Identity Management (AIM) application will enable the use of ACL groups for SCID-level read-only access for MRI-S. A customer partnership group is scheduled for May 11, 2017 to address issues encountered during market sim, and to discuss the steps necessary for cut-over from OMAR Online to MRI-S Metering. OMAR Online will be decommissioned four months after the May 2nd re-opening of the MRI-S Metering: September 1, 2017.
BPM Changes
None
Business Process Changes
Potential Level-II business process changes under –
- Manage Market & Reliability Data & Modeling
- Manage Operations Support & Settlements
Slide 100
Milestone Type Milestone Name Dates Status
Board Approval Board Approval N/A BPMs BPMs N/A External BRS Post External BRS Nov 14, 2016
Tariff Tariff N/A Config Guides Config Guide N/A Tech Spec Publish Tech Specs Nov 02, 2016
Market Simulation Phase 2 - MRI-S Metering Enhancements Mar 13, 2017 – June 9, 2017 Production Activation Phase 1 - ACL Groups Mar 10, 2017
Phase 2 - MRI-S Metering CPG Enhancements Jun 13, 2017
2017 – RIMS Functional Enhancements
Project Info Details/Date Status
Application Software Changes Functional enhancements resulting from the Customer Partnership Group CPG. More details to be provided in the future. BPM Changes Generator Interconnection and Deliverability Allocation Procedures Generator Interconnection Procedures Managing Full Network Model Metering Generator Management Transmission Planning Process Customer Partnership Group 10/16/15 Application and Study Webinar 3/31/16
Slide 101
Milestone Type Milestone Name Dates Status
Board Approval Board approval not required N/A BPMs Generator Interconnection and Delivery Allocation Apr 29, 2016
External BRS External BRS not Required N/A Tariff No Tariff Required N/A Tech Spec No Tech Specifications Required N/A Production Activation Ph1 RIMS5 App & Study Mar 21, 2016
Production Activation Ph2 RIMS5 Queue Management, Transmission and Generation Dec 14, 2017
2017- Black Start and System Restoration Phase 2
Project Info
Details/Date
Application Software Changes Settlements:
- Modifications to existing charge codes for Black Start capacity and
Black Start allocations will need to occur. MPP (Market Participant Portal):
- Possibility to use current functionality for receiving RMR invoices
for Black Start units. BPM Changes Definitions & Acronyms:
- Revision of the following definitions to match the Tariff language:
- Ancillary Services (AS)
- Black Start Generator
- Black Start Generating Unit
- Interim Black Start Agreement
- Reliability Services Costs
Settlements & Billing:
- Pending Settlements review. Revisions will be directly based on
Tariff changes. Business Process Changes N/A
Slide 102
Milestone Type Milestone Name Dates Status
Board Approval Board approval May 1, 2017
BPMs BPM Changes Required TBD External BRS External BRS not Required N/A Tariff Draft tariff Web Conference to finalize tariff May 1, 2017 May 15, 2017
Tech Spec No Tech Specifications Required N/A
2017 – Forecasting and Data Transparency Improvements (PIRP System Decommissioning)
Project Info
Details/Date
Application Software Changes: PIRP/CMRI
- Forecast Data Reporting (resource-level) that was performed in PIRP will be done in
- CMRI. Rolling Hour Ahead, Locked Hour Ahead, and Rolling Day-Ahead forecasts.
- PIRP Decommissioning to occur in 2017
- CMRI to receive the Electricity Price Index for each resource and publish it to the
Market Participants.
- 60 Day PIRP / CMRI parallel production to start when AIM/ACL becomes available.
BPM Changes CMRI Technical Specification; New APIs will be described. Data Transparency
- Independent changes, won’t
impact existing services
- Will be made available in
Production and cutover schedule is discretionary Atlas Reference:
- 1. Price Correction Messages (ATL_PRC_CORR_MSG)
- 2. Scheduling Point Definition (ATL_SP)
- 3. BAA and Tie Definition (ATL_BAA_TIE)
- 4. Scheduling Point and Tie Definition (ATL_SP_TIE)
- 5. Intertie Constraint and Scheduling Point Mapping (ATL_ITC_SP)
- 6. Intertie Scheduling Limit and Tie Mapping (ATL_ISL_TIE)
Energy
- EIM Transfer Limits By Tie (ENE_EIM_TRANSFER_LIMITS_TIE)
- Wind and Solar Summary (ENE_WIND_SOLAR_SUMMARY)
Prices
- MPM Default Competitive Path Assessment List (PRC_MPM_DEFAULT_CMP)
Business Process Changes MPs will receive the VER reports from CMRI rather than PIRP.
Slide 103
2017 – Forecasting and Data Transparency Improvements (PIRP System Decommissioning)
Project Info
Details/Date
User-Provisioning process for CMRI in preparation of Market Simulation and subsequently for production
- Client Services will reach out to the User Access Administrator (UAA)
- Updated AIM User Guide, detailing how to create new ACL groups, was posted on
February 21, 2017 - The market notice was posted on February 23, 2017
- If a user is at the SC level, there is no need to provision ACL access
- Exceptions - (Non-SC Level Users) – provisioning via AIM will be required
- Provisioning will be required to be done prior to Market Simulation
- Provisioning for PIRP via AARF will discontinue on Feb 16, 2017 for Map Stage and
Mar 20, 2017 for Production.
- Participants should begin to download their PIRP data (all reports) as soon as possible
as the data will not be available after June 20, 2017
- PIRP application including all the UI and API reports will be decommissioned June 20,
2017
- If you have any questions please contact your client services representative
Slide 104
2017 – Forecasting and Data Transparency Improvements (PIRP System Decommissioning)
Slide 105
Milestone Type Milestone Name Dates Status
Board Approval Board Approval N/A BPMs Publish Draft Business Practice Manuals (Market Instruments; PRR 936) Sep 06, 2016
External BRS External Business Requirements Jun 29, 2015
Tariff Tariff Filing Activities N/A Config Guides Settlements Configuration N/A Tech Spec Publish Technical Specifications (CMRI; Wind and Solar) Apr 15, 2016
Publish Technical Specifications (CMRI: PIRP Decommissioning) Feb 05, 2016
Market Sim CMRI Reports; VER Forecast & EPI (Fall 2016 Release) Aug 23, 2016 - Sep 23, 2016
New Renewables CMRI reports and APIs Market Simulation Apr 04, 2017 - Apr 18, 2017
Production Activation CMRI Reports; VER Forecast & EPI (Fall 2016 Release) Oct 01, 2016
OASIS API Enhancements; 9 Reports Dec 20, 2016
New Renewables CMRI reports and APIs Production Deployment Apr 20, 2017
PIRP Decommission PIRP Decommissioning Jun 20, 2017
Fall 2017 Release – Overview
Slide 106 Board Approval BPMs External BRS Tariff Config Guide Tech Spec Market Sim Production Activation
Fall 2017 Release
EIM Portland General Electric N/A N/A N/A 8/31/17 N/A N/A 6/6/17 - 7/6/17 10/1/17 Bidding Rules Enhancements - Part B 3/25/16 6/15/17 1/13/17 6/1/17 6/27/17
- 4/3/17
(MF)
- 4/3/17
(OASIS)
- 4/17/17
(CMRI)
- 4/25/17
(CMRI)
- 5/2/17
(OASIS) 8/8/17 - 9/8/17 11/1/17 Commitment Cost Enhancement Phase 3 3/25/16 1/6/17 4/10/17 6/15/17 RM & EIM 2017 Enhancements N/A N/A 1/23/17 2/17/17 4/10/17 N/A Gas Burn Reports N/A N/A 7/29/16 N/A N/A N/A SIBR UI Upgrade N/A N/A N/A N/A N/A N/A N/A COMPLETE N/A
Fall 2017 – EIM Portland General Electric
Project Info Details/Date Application Software Changes Implementation of Portland General Electric as an EIM Entity. BPM Changes EIM BPM will be updated to reflect new modeling scenarios identified during PGE implementation and feedback from PGE. Market Simulation PGE continues Day in the Life and unstructured scenario testing in a non- production environment in preparation for Market Simulation. Parallel Operations August 1 – September 30, 2017
Slide 107
Milestone Type Milestone Name Dates Status
Tariff File Readiness Certification Aug 31, 2017 Market Sim Market Sim Window Jun 6, 2017 – Jul 6, 2017 Parallel Operations Parallel Operations Window Aug 1, 2017 – Sep 30, 2017 Production Activation EIM - Portland General Electric Oct 01, 2017
Fall 2017 - Bidding Rules Enhancements – Part B
Slide 108
Project Info Details/Date Application Software Changes
- MasterFile:
- Electric Region added to GRDT as non-modifiable
- CMRI:
- Resource-level monthly EPI (calculated on daily basis) based on wholesale or reatil
electric region type.
- CAISO.COM:
- Only publish total monthly fuel region GPI (existing) and eliminate publishing the
monthly fuel region GPI components as PDF file. (public information)
Business Process Change
- Manage Transmission & Resource Implementation
- Manage Entity & Resource Maintenance Updates
- Manage Full Network Model Maintenance
BPMs
Market Instruments Milestone Type Milestone Name Dates Status
BPMs Post Draft BPM changes June 15, 2017 Board Approval BOG Approval Mar 25, 2016
External BRS Post External BRS Jan 13, 2017
Config Guides Prepare Draft Configuration Guides Jun 27, 2017 Tech Spec Publish CMRI Tech Specs Apr 17, 2017
Publish MF Tech Specs Apr 03, 2017
Market Sim Market Sim Window Aug 08, 2017 - Sep 08, 2017 Production Activation Bidding Rules Part B Nov 01, 2017
Project Info Details/Date
Application Software Changes Scope: 1. Clarify use-limited registration process and documentation to determine opportunity costs 2. Determine if the ISO can calculate opportunity costs
- ISO calculated; Modeled limitation Start/run hour/energy output
- Market Participant calculated; Negotiated limitation
3. Clarify definition of “use-limited” 4. Change Nature of Work attributes (Outage cards)
- Modify use-limited reached for RAAIM Treatment
- Allow PDR to submit use-limit outage card for fatigue break.
5. Market Characteristics
- Maximum Daily Starts
- Maximum MSG transitions
- Ramp rates
Impacted Systems: 1. Master File: Set use-limited resource types and limits; Set market-based values 2. ECIC: Process use limited resource input values for and Receive opportunity cost adders from
- pportunity cost tool
3. CIRA: RAAIM exempt rule for “use-limited reached” 4. CMRI: Publish opportunity cost 5. IFM/RTN: Use market-based values MDS, MDMT and RR 6. SIBR: Add Opportunity cost adders on bid caps, remove daily bid RR 7. MasterFile: Set use-limited resource types and limits; Set market-based values 8. OMS: “Use-Limited Reached” nature of work attribute for Generation Outage Card 9. Settlements: Publish the actual start up, run hour and energy output for the use-limited resources
- 10. Opportunity cost calculator (OCC): Calculate and publish opportunity costs for start-up, MLC and
DEB BPM Changes Market Instruments, Outage Management, Reliability Requirement, Market Operations Business Process Changes
- Manage Market & Reliability Data & Modeling
- Manage Markets & Grid
Slide 109
Fall 2017 - Commitment Cost Enhancements Phase 3
Slide 110
Fall 2017 - Commitment Cost Enhancements Phase 3 (cont.)
Milestone Type Milestone Name Dates Status
Board Approval Board of Governors (BOG) Approval Mar 25, 2016
BPMs Post Draft BPM changes Jun 15, 2017 External BRS Post External BRS Jan 06, 2016
Tariff File Tariff Jun 15, 2017 Config Guides Config Guide Jun 27, 2017 Tech Spec Publish ISO Interface Spec (Tech spec) – MF Publish ISO Interface Spec (Tech spec) – CMRI Apr 03, 2017 Apr 17, 2017
Market Sim Market Sim Window Aug 08, 2017 – Sep 8, 2017 Production Activation Commitment Costs Phase 3 Nov 01, 2017
Fall 2017 – RM & EIM Enhancements 2017
Project Info
Details/Date
Application Software Changes
Address enhancements identified by policy, operations, technology, business and market participants. Scope:
- 1. Access & Integration Enhancements: EIM Entity Access in ALFS, MF,
OASIS, WebOMS, and CMRI. 2. EIM data report enhancements to support market participant and EIM entity settlements 3. EIM software enhancements 4. Change to ETSR formulation to separate base energy transfer to distinct non-optimizable ETSRs. Out of Scope: 1. BAAOP provisioning in AIM 2. Joint Owned Unit/Shared BAA Resource Modeling
BPM Changes
Energy Imbalance Market: Access & Integration, Data Report Outage Management: Access & Integration Market Instruments: Access & Integration, Data Reports Market Operations: Data Report Settlements & Billing: Data Report
Business Process Changes
N/A
Slide 111
Fall 2017 – RM & EIM Enhancements 2017
Slide 112
Milestone Type Milestone Name Dates Status
External BRS Post External BRS Jan 23, 2017
Post Updated External BRS Feb 17, 2017
Post Updated (v1.2) External BRS to public site Apr 10, 2017
Config Guides Config Guide Jun 27, 2017 Tech Spec Publish Technical Specifications (CMRI) Apr 17, 2017
Publish Technical Specifications (OASIS) Apr 03, 2017
Publish Technical Specifications (MF) Apr 03, 2017
Market Sim Market Simulation Aug 08 – Sept 08, 2017 Production Activation RM & EIM Enhancements 2017 Nov 01, 2017
Fall 2017 – Gas Burn Report
Slide 113
Project Info Details/Date Application Software Changes
CMRI - implement ISO Market software functionality to calculate and present gas burn estimates to gas companies serving electric generation located within the CAISO BAA OASIS - Control Area Generating Capability List report
Business Process Change
- Develop Infrastructure
- Manage Market & Reliability Data & Modeling
Milestone Type Milestone Name Dates Status
Board Approval BOG Approval N/A BPMs Post Draft BPM changes N/A External BRS External Business Requirements Jul 29, 2016
Tariff Receive FERC order N/A Config Guides Configuration Guides N/A Tech Spec Publish Technical Specifications - CMRI Apr 25, 2017
Publish Technical Specifications - OASIS May 02, 2017
Market Sim Market Sim Window N/A Production Activation GenDB MF Consol and Gas Burn Report Nov 01, 2017
Fall 2017 – SIBR UI Upgrade
Slide 114
Project Info Details/Date Application Software Changes
SIBR – The CASIO will be upgrading the underlying SDK platform utilized for displaying the user interface. This latest SDK version will strengthen the security of the SIBR application and will improve compatibility with the latest version of Internet Explorer. It is anticipated no functional changes or API will be impacted by this upgrade. Milestone Type Milestone Name Dates Status
Board Approval Board Approval N/A BPMs Publish Final Business Practice Manuals N/A External BRS Post Draft BRS N/A Tariff Receive FERC order N/A Tech Spec Publish Tech Specs N/A Market Sim Market Sim Window N/A Production Activation SIBR UI Upgrade Nov 01, 2017
Spring 2018 - Reliability Services Initiative 2017
Project Info
Details/Date Application Software Changes
Developments under consideration include: Scope:
Redesign of Replacement Rule for System RA and Monthly RA Process.
- RA Process and Outage Rules for implementation for 2017 RA year.
- CSP Offer Publication (RSI 1A scope)
- Local and system RA capacity designation
- RA showing requirements for small load serving entities (LSEs)
- RA showing tracking and notification
Impacted Systems:
- OASIS
- Settlements
- CIRA
CIRA:
- Modifications to the RA and Supply Plan to show breakdown of local and system. Validation
rules need to be updated.
- Update planned/forced outage substitution rules
- Allow market participants to select how much system/local MWs to substitute.
- Modification of UI screens to accommodate system/local MW split.
- Enhance system to allow exemption from submission of RA Plans for LSE that have a RA
- bligation < 1 MW for a given capacity product.
Settlements:
- Splitting local from system in upstream RA system could potentially impact the RAAIM
calculation.
BPM Changes
- Reliability Requirements: Changes to the monthly RA process
- Settlements and Billing
Business Process Changes
Manage Market & Reliability Data & Modeling
- Manage Monthly & Intra-Monthly Reliability Requirements
- Manage Yearly Reliability Requirements
Slide 115
Spring 2018 - Reliability Services Initiative 2017
Slide 116
Milestone Type Milestone Name Dates Status
Board Approval Board Approval May 12, 2015
BPMs Post Draft BPM changes Jun 15, 2017 External BRS Post Updated External BRS v1.1 (RSI 2) Apr 07, 2017
Post Updated External BRS v1.3 (RSI 1B) Mar 03, 2017
Post RSI 2017 External BRS v2.0 Apr 19, 2017
Tariff File Tariff Q3 2017 Config Guides Config Guide Jun 27, 2017 Tech Spec Publish Technical Specifications Apr 03, 2017
Market Sim Market Sim Window Oct 30, 2017 - Dec 08, 2017 Production Activation RSI 2017 Feb 13, 2018
Spring 2018 – EIM Idaho Power Company
Project Info Details/Date Application Software Changes Implementation of Idaho Power Company as an EIM Entity. BPM Changes EIM BPM will be updated if needed to reflect new modeling scenarios identified during Idaho Power implementation and feedback from Idaho Power. Market Simulation The ISO approved the Idaho Power network model and continues to make progress integrating the Idaho model into the ISO non-production environment in preparation for integration testing. Parallel Operations February 1, 2018 – March 30, 2018
Slide 117
Milestone Type Milestone Name Dates Status Tariff File Readiness Certification Feb 28, 2018 Market Sim Market Sim Window Dec 01, 2017 - Jan 31, 2018 Parallel Operations Parallel Operations Window Feb 01, 2018 - Mar 30, 2018 Production Activation EIM - Idaho Power Apr 04, 2018
The ISO offers comprehensive training programs
Slide 118
All classes are offered at our Folsom, CA location unless noted otherwise. Training calendar - http://www.caiso.com/participate/Pages/Training/default.aspx Contact us - CustomerTraining@caiso.com Date Training May 24-25 Get to Know the ISO Jul 6 Welcome to the ISO - webinar Aug 16 Settlements 101 Aug 17 Settlements 201
ISO Daily Briefing
- A digest version of ISO market notices
- Distributed daily, Mon-Fri around 1:30 p.m. (PST)
- NEW: Upcoming Events - Every Thursday the briefing
will include stakeholder activities for the following week
- To subscribe to the Daily Briefing:
- Go to www.caiso.com
- Under “Stay Informed” tab
- Select “Notifications”
- Click under Market notices heading
- Select Daily Briefing from the list of categories
Note: If you currently receive ISO market notices and you re-subscribe, the system will override your previous category selections. If you still want to receive market notices in other categories, you’ll need to reselect those categories of interest.
Slide 119
Market Performance and Planning Forum 2017 Schedule
- July 18
- October 5 – Rescheduled from September 19
- November 14
Questions or meeting topic suggestions: Submit through CIDI - select the “Market Performance and Planning Forum” category
Slide 120