march 20 2002 public meeting on reactor pressure vessel
play

March 20, 2002 Public Meeting on Reactor Pressure Vessel Head - PowerPoint PPT Presentation

March 20, 2002 Public Meeting on Reactor Pressure Vessel Head Degradation MARCH 20, 2002 PUBLIC MEETING on REACTOR PRESSURE VESSEL HEAD DEGRADATION PURPOSE: To exchange information with stakeholders and respond to questions regarding


  1. March 20, 2002 Public Meeting on Reactor Pressure Vessel Head Degradation

  2. MARCH 20, 2002 PUBLIC MEETING on REACTOR PRESSURE VESSEL HEAD DEGRADATION PURPOSE: To exchange information with stakeholders and respond to questions regarding degradation of the reactor pressure vessel head found at the Davis Besse Nuclear Power plant and NRC’s actions to address the issue. SUCCESS: Participants leave the meeting with clear understanding of the issue, stakeholder perspectives and concerns, and NRC’s actions to address the issue and protect public health and safety. AGENDA I. INTRODUCTIONS Tony Mendiola, Section Chief DLPM, NRR U.S. NRC II. OVERVIEW OF ISSUE ( 25 minutes) Jack Strosnider, Director Division of Engineering, NRR U.S. NRC III. QUESTION AND DISCUSSION PERIOD IV. ADJOURNMENT Page 1 of 12

  3. OVERVIEW OF ISSUE I. Basic Plant and Reactor Pressure Vessel Overview II. Description of Degradation found at Davis Besse III. Safety Implications IV. Industry / licensee actions V. NRC Actions Page 2 of 12

  4. FIG 1: BASIC PLANT SYSTEMS Page 3 of 12

  5. FIG 2: REACTOR PRESSURE VESSEL HEAD Page 4 of 12

  6. DESCRIPTION OF DEGRADATION FOUND AT DAVIS BESSE C INSPECTIONS WERE BEING PERFORMED IN RESPONSE TO NRC BULLETIN 2001-01 REGARDING CRACKING OF CRDM NOZZLE PENETRATION TUBE C NOZZLES INSPECTED WITH ULTRASONIC TESTING S nozzles 1, 2, and 3 had through-wall cracks that leaked S nozzles 5 and 47 had cracks that were not through-wall C PROBLEMS ENCOUNTERED DURING REPAIR OF NOZZLE 3 C NOZZLE 3 REMOVED FROM REACTOR VESSEL HEAD AND BORIC ACID DEPOSITS REMOVED C IDENTIFIED DEGRADED AREAS ADJACENT TO NOZZLES 1, 2, AND 3 Page 5 of 12

  7. FIG 3: TOP VIEW OF REACTOR VESSEL HEAD Page 6 of 12

  8. FIG 4: CROSS-SECTIONAL SKETCH OF DEGRADED AREA ADJACENT TO NOZZLE 3 Page 7 of 12

  9. FIG 5: PHOTO OF DEGRADED AREA ADJACENT TO NOZZLE 3 Page 8 of 12

  10. SAFETY IMPLICATIONS C VERY SERIOUS DEGRADATION S Structural Margins Were Significantly Degraded S Potential for Loss of Reactor Coolant Accident C PLANT IS DESIGNED TO DEAL WITH A LOSS OF COOLANT ACCIDENT S Emergency Core Cooling Systems, Control of Nuclear Reaction, Containment S Unwanted Challenge to Systems and Operators C PROMPT ACTION REQUIRED TO CONFIRM THAT SIMILAR PROBLEMS DON’T EXIST AT OTHER PLANTS Page 9 of 12

  11. LICENSEE / INDUSTRY ACTIONS C LICENSEE ACTIONS S Plant is in safe, shutdown condition S Licensee investigating extent and cause of degradation S Licensee evaluating repair or replacement options C INDUSTRY ACTION S Industry survey to collect information on status of all pressurized water reactor plants S Information presented at March 19 public meeting Page 10 of 12

  12. NRC Actions C INFORMATION NOTICE 2002-11 ISSUED MARCH 12, 2002 C NRC AUGMENTED INSPECTION TEAM (AIT) SENT TO SITE C CONFIRMATORY ACTION LETTER ISSUED TO LICENSEE C BULLETIN 2002-01 ISSUED ON MARCH 18, 2002 Page 11 of 12

  13. BULLETIN REQUIRED INFORMATION WITHIN 15 DAYS: C SUMMARY OF RPV HAD INSPECTION & MAINTENANCE PROGRAMS C EVALUATION OF ABILITY OF INSPECTION AND MAINTENANCE PROGRAMS TO IDENTIFY DEGRADATION C DESCRIPTION OF CONDITIONS THAT COULD LEAD TO DEGRADATION AND CORRECTIVE ACTIONS TAKEN TO ADDRESS SUCH CONDITIONS C PLANS, BASIS AND SCHEDULE FOR FUTURE INSPECTIONS OF THE REACTOR VESSEL HEAD AND VESSEL HEAD PENETRATION NOZZLES C BASIS FOR CONTINUED OPERATION UNTIL THE INSPECTIONS ARE PERFORMED WITHIN 30 DAYS: C RESULTS OF INSPECTIONS WITHIN 60 DAYS: C BASIS FOR CONCLUDING BORIC ACID INSPECTION PROGRAM IS EFFECTIVELY MAINTAINING REACTOR COOLANT PRESSURE BOUNDARY INTEGRITY Page 12 of 12

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend